IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Grant Park | Date: 9/20/2018 | Project No. |
| Enhancement Project | County: | SAC | Time: 11:00 a.m. | 18-01-81-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $95,612.00 | Contractor: | LA Carlson Contracting, Inc. | |||||||||||
| Funding Source: 100% Marine Fuel Tax, | 20984 C-43 | ||||||||||||
| Merrill IA 51038-8674 | |||||||||||||
| Plan Sets Requested: 1 | Quantities | 7129470002 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | TOE WOOD BANK STABILIZATION | 3000 | Units | $14.00 | $42,000.00 | $0.00 | $0.00 | ||||||
| 2 | BANK SHAPING FOR TOE WOOD CONSTRUCTION | 1900 | C.Y. | $5.65 | $10,735.00 | $0.00 | $0.00 | ||||||
| 3 | 3x3x3 CUT WEIR STONE, 2.5 SPECIFIC GRAVITY | 170 | Each | $420.00 | $71,400.00 | $0.00 | $0.00 | ||||||
| 4 | CLASS ‘B’ RIPRAP | 700 | Tons | $52.00 | $36,400.00 | $0.00 | $0.00 | ||||||
| 5 | 6-INCH REINFORCED PCC PAVEMENT | 33.4 | S.Y. | $115.00 | $3,841.00 | $0.00 | $0.00 | ||||||
| 6 | REINFORCED PCC BOAT RAMP PUSH-IN SLAB | 40 | S.Y. | $115.00 | $4,600.00 | $0.00 | $0.00 | ||||||
| 7 | CLASS ‘A’ CRUSHED STONE | 50 | Tons | $41.75 | $2,087.50 | $0.00 | $0.00 | ||||||
| 8 | CLASS ‘D’ RIPRAP | 100 | Tons | $52.00 | $5,200.00 | $0.00 | $0.00 | ||||||
| 9 | 700 GRAM COYER EROSION FABRIC | 11000 | S.F. | $0.50 | $5,500.00 | $0.00 | $0.00 | ||||||
| 10 | MACADAM STONE | 11.7 | Tons | $52.00 | $608.40 | $0.00 | $0.00 | ||||||
| 11 | SURFACE RESTORATION | 1 | L.S. | $4,000.00 | $4,000.00 | $0.00 | $0.00 | ||||||
| 12 | NPDES GENERAL PERMIT #2 | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
| 13 | MOBILIZATION | 1 | L.S. | $10,000.00 | $10,000.00 | $0.00 | $0.00 | ||||||
| $198,871.90 | $0.00 | $0.00 | |||||||||||