IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Bellevue | Date: 5/18/2017 | Project No. |
PCC Sidewalk and Trail Improvements | County: | JACKSON | Time: 3:00 pm | 17-06-49-03 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $67,000.00 | Contractor: | Lansing Brothers Construction | Ardo Schmidt Construction, Inc. | ||||||||||
Funding Source: 100% Infrastructure 2017, | 101 East First St | 35010 Hwy 64 | |||||||||||
Luxemburg IA 52056-0036 | Preston IA 52069 | ||||||||||||
Plan Sets Requested: 0 | Quantities | 563-563-7360 | 563-689-4875 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $5,250.00 | $5,250.00 | $3,000.00 | $3,000.00 | $0.00 | |||||
2 | Granular Subbase | 640 | Tons | $23.00 | $14,720.00 | $23.20 | $14,848.00 | $0.00 | |||||
3 | 3/8 Minus Trail Sufacing | 480 | Tons | $16.00 | $7,680.00 | $19.70 | $9,456.00 | $0.00 | |||||
4 | Macadam Stone | 50 | Tons | $30.00 | $1,500.00 | $25.00 | $1,250.00 | $0.00 | |||||
5 | Engineering Fabric | 110 | S.Y. | $5.00 | $550.00 | $3.50 | $385.00 | $0.00 | |||||
6 | PCC Sidewalk, 5" Depth Reinforced | 680 | S.Y. | $36.00 | $24,480.00 | $47.00 | $31,960.00 | $0.00 | |||||
7 | PCC Pavement, 6" Depth Reinforced | 40 | S.Y. | $45.00 | $1,800.00 | $50.00 | $2,000.00 | $0.00 | |||||
8 | A.D.A. Striping, Signage and Bumper Block | 1 | L.S. | $600.00 | $600.00 | $500.00 | $500.00 | $0.00 | |||||
9 | Site Restoration | 1 | L.S. | $5,000.00 | $5,000.00 | $1,000.00 | $1,000.00 | $0.00 | |||||
$61,580.00 | $64,399.00 | $0.00 | |||||||||||
5/2/2024