IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Mount Ayr Fisheries Management Unit | Date: 11/10/2016 | Project No. |
Repair Fogle Lake jetties | County: | RINGGOLD | Time: 11:00 a.m. | 17-04-80-02 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $20,000.00 | Contractor: | Schaefer Excavating, Inc. | JNC Construction, LLC | Jeff Sickels Dozing LLC | |||||||||
Funding Source: 80% Marine Fuel Tax, 20% REAP Land Management, | 1864 215th St | 609 3rd St | 2047 220th St | ||||||||||
Mt Ayr IA 50854 | Clearfield IA 50840 | Mt Ayr IA 50854 | |||||||||||
Plan Sets Requested: 0 | Quantities | 641-344-6873 | 641-344-4119 | 515-250-2148 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Class "E" Riprap | 350 | Tons | $53.50 | $18,725.00 | $54.77 | $19,169.50 | $60.00 | $21,000.00 | ||||
2 | Class "A" Surfacing | 50 | Tons | $27.30 | $1,365.00 | $24.56 | $1,228.00 | $50.00 | $2,500.00 | ||||
$20,090.00 | $20,397.50 | $23,500.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $20,000.00 | Contractor: | Michael J. Lamb dba Lamb Tiling | |||||||||||
Funding Source: 80% Marine Fuel Tax, 20% REAP Land Management, | 2751 Marion Ave | ||||||||||||
Greenfield IA 50849 | |||||||||||||
Plan Sets Requested: 0 | Quantities | 641-743-8312 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Class "E" Riprap | 350 | Tons | $74.00 | $25,900.00 | $0.00 | $0.00 | ||||||
2 | Class "A" Surfacing | 50 | Tons | $60.00 | $3,000.00 | $0.00 | $0.00 | ||||||
$28,900.00 | $0.00 | $0.00 | |||||||||||
9/27/2024