IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Three Mile Lake  Date: 11/10/2016  Project No.  
  Shoreline Stabilization  County:   UNION  Time: 11:00 a.m.  17-04-88-02

 

 
1
2
3
Estimated Cost: $700,000.00
Contractor: 
Tri-Smith Construction LLCTK Concrete, Inc.Peterson Contractors, Inc.
Funding Source: 100% Marine Fuel Tax, 21239 CR 366
1608 Fifield Rd
104 Black Hawk St
Carrollton MO  64633Pella IA  50219Reinbeck IA  50669
Plan Sets Requested: 6
Quantities
660-542-2738641-628-4590319-415-6719
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$30,570.00$30,570.00 $32,500.00$32,500.00 $24,000.00$24,000.00 
2Class E Revetment6500Tons$44.86$291,590.00 $53.50$347,750.00 $52.50$341,250.00 
3Shoreline Deepening900L.F.$7.44$6,696.00 $3.00$2,700.00 $7.25$6,525.00 
4Engineering Fabric1260S.Y.$8.00$10,080.00 $2.25$2,835.00 $3.25$4,095.00 
5Access Route1L.S.$7,000.00$7,000.00 $1,500.00$1,500.00 $2,350.00$2,350.00 
6Site Restoration1L.S.$5,000.00$5,000.00 $4,000.00$4,000.00 $7,500.00$7,500.00 
      $350,936.00  $391,285.00  $385,720.00 
Alternate        
7Class E Revetment1439Tons$44.86$64,553.54 $54.00$77,706.00 $52.75$75,907.25 
Alternate        
8Shoreline Deepening400L.F.$7.44$2,976.00 $3.00$1,200.00 $7.25$2,900.00 
Alternate        
9Engineering Fabric560S.Y.$8.00$4,480.00 $2.25$1,260.00 $3.25$1,820.00 
Alternate        
10Access Route1L.S.$1,500.00$1,500.00 $1,500.00$1,500.00 $475.00$475.00 
Alternate        
11Site Restoration1L.S.$3,000.00$3,000.00 $3,500.00$3,500.00 $3,500.00$3,500.00 
Alternate        
12Class E Revetment4500Tons$44.86$201,870.00 $53.50$240,750.00 $55.25$248,625.00 
Alternate        
13Shoreline Deepening3000L.F.$7.44$22,320.00 $2.50$7,500.00 $7.25$21,750.00 
Alternate        
14Engineering Fabric4200S.Y.$8.00$33,600.00 $2.25$9,450.00 $3.25$13,650.00 
Alternate        
15Access Route1L.S.$3,500.00$3,500.00 $1,500.00$1,500.00 $2,450.00$2,450.00 
Alternate        
16Site Restoration1L.S.$2,000.00$2,000.00 $3,500.00$3,500.00 $7,000.00$7,000.00 
Alternate        
17Class E Revetment525Tons$44.86$23,551.50 $54.00$28,350.00 $54.00$28,350.00 
Alternate        
18Access Route1L.S.$1,000.00$1,000.00 $1,500.00$1,500.00 $730.00$730.00 
Alternate        
19Site Restoration1L.S.$1,000.00$1,000.00 $2,500.00$2,500.00 $3,500.00$3,500.00 
      $716,287.04  $771,501.00  $796,377.25 
 
4
5
6
Estimated Cost: $700,000.00
Contractor: 
Murphy Heavy Const.Empire Construction and Trenching, Inc.Michael J. Lamb dba Lamb Tiling
Funding Source: 100% Marine Fuel Tax, 101 Roosevelt Dr.
1665 200th St
2751 Marion Ave
Anita IA  50020Red Oak IA  51566Greenfield IA  50849
Plan Sets Requested: 6
Quantities
712-762-3386712-623-9435641-743-8312
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$10,000.00$10,000.00 $5,000.00$5,000.00 $27,500.00$27,500.00 
2Class E Revetment6500Tons$55.30$359,450.00 $57.68$374,920.00 $62.00$403,000.00 
3Shoreline Deepening900L.F.$18.00$16,200.00 $4.11$3,699.00 $5.00$4,500.00 
4Engineering Fabric1260S.Y.$3.00$3,780.00 $8.75$11,025.00 $3.75$4,725.00 
5Access Route1L.S.$8,575.00$8,575.00 $3,578.20$3,578.20 $5,000.00$5,000.00 
6Site Restoration1L.S.$8,500.00$8,500.00 $10,403.20$10,403.20 $5,000.00$5,000.00 
Alternate        
7Class E Revetment1439Tons$55.30$79,576.70 $61.62$88,671.18 $60.00$86,340.00 
Alternate        
8Shoreline Deepening400L.F.$18.00$7,200.00 $5.84$2,336.00 $6.00$2,400.00 
Alternate        
9Engineering Fabric560S.Y.$3.00$1,680.00 $9.62$5,387.20 $4.00$2,240.00 
Alternate        
10Access Route1L.S.$6,000.00$6,000.00 $1,530.67$1,530.67 $5,000.00$5,000.00 
Alternate        
11Site Restoration1L.S.$6,000.00$6,000.00 $2,045.67$2,045.67 $5,000.00$5,000.00 
Alternate        
12Class E Revetment4500Tons$55.30$248,850.00 $61.03$274,635.00 $65.00$292,500.00 
Alternate        
13Shoreline Deepening3000L.F.$10.00$30,000.00 $2.87$8,610.00 $4.00$12,000.00 
Alternate        
14Engineering Fabric4200S.Y.$2.00$8,400.00 $8.02$33,684.00 $4.00$16,800.00 
Alternate        
15Access Route1L.S.$10,800.00$10,800.00 $2,289.10$2,289.10 $5,000.00$5,000.00 
Alternate        
16Site Restoration1L.S.$10,800.00$10,800.00 $10,014.10$10,014.10 $5,000.00$5,000.00 
Alternate        
17Class E Revetment525Tons$55.30$29,032.50 $63.13$33,143.25 $60.00$31,500.00 
Alternate        
18Access Route1L.S.$4,150.00$4,150.00 $530.67$530.67 $1,000.00$1,000.00 
Alternate        
19Site Restoration1L.S.$4,150.00$4,150.00 $1,560.67$1,560.67 $1,000.00$1,000.00 
      $853,144.20  $873,062.91  $915,505.00 
 
7
8
9
Estimated Cost: $700,000.00
Contractor: 
Minturn, Inc.Reilly Construction Co., Inc.Boyd Construction, LLC
Funding Source: 100% Marine Fuel Tax, 309 N Orchard St

PO Box 99
1007 West 1st St
Brooklyn IA  52211Ossian IA  52161Leon IA  50144
Plan Sets Requested: 6
Quantities
641-455-0331563-532-9211641-446-6944
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$10,000.00$10,000.00 $7,500.00$7,500.00 $41,030.00$41,030.00 
2Class E Revetment6500Tons$59.00$383,500.00 $65.00$422,500.00 $62.80$408,200.00 
3Shoreline Deepening900L.F.$7.00$6,300.00 $10.00$9,000.00 $13.80$12,420.00 
4Engineering Fabric1260S.Y.$2.00$2,520.00 $2.50$3,150.00 $2.30$2,898.00 
5Access Route1L.S.$26,500.00$26,500.00 $17,500.00$17,500.00 $31,735.00$31,735.00 
6Site Restoration1L.S.$10,000.00$10,000.00 $23,000.00$23,000.00 $37,609.00$37,609.00 
Alternate        
7Class E Revetment1439Tons$59.00$84,901.00 $65.00$93,535.00 $66.40$95,549.60 
Alternate        
8Shoreline Deepening400L.F.$7.00$2,800.00 $10.00$4,000.00 $12.40$4,960.00 
Alternate        
9Engineering Fabric560S.Y.$2.00$1,120.00 $2.50$1,400.00 $4.60$2,576.00 
Alternate        
10Access Route1L.S.$9,000.00$9,000.00 $1,500.00$1,500.00 $11,738.00$11,738.00 
Alternate        
11Site Restoration1L.S.$2,000.00$2,000.00 $5,000.00$5,000.00 $13,676.00$13,676.00 
Alternate        
12Class E Revetment4500Tons$59.00$265,500.00 $65.00$292,500.00 $59.40$267,300.00 
Alternate        
13Shoreline Deepening3000L.F.$7.00$21,000.00 $10.00$30,000.00 $14.20$42,600.00 
Alternate        
14Engineering Fabric4200S.Y.$2.00$8,400.00 $2.50$10,500.00 $2.30$9,660.00 
Alternate        
15Access Route1L.S.$32,500.00$32,500.00 $28,000.00$28,000.00 $18,820.00$18,820.00 
Alternate        
16Site Restoration1L.S.$4,000.00$4,000.00 $12,500.00$12,500.00 $20,208.00$20,208.00 
Alternate        
17Class E Revetment525Tons$59.00$30,975.00 $65.00$34,125.00 $69.80$36,645.00 
Alternate        
18Access Route1L.S.$15,000.00$15,000.00 $1,500.00$1,500.00 $3,175.00$3,175.00 
Alternate        
19Site Restoration1L.S.$1,000.00$1,000.00 $2,500.00$2,500.00 $11,255.00$11,255.00 
      $917,016.00  $999,710.00  $1,072,054.60 
 



 