Bids For: | Location: | Kiowa Marsh Wetland Complex | Date: 5/18/2017 | Project No. |
Kiowa Marsh Culvert Replacement | County: | SAC | Time: 3:00 p.m. | 17-01-81-04 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $49,000.00 | Contractor: | Spring Lake Construction | John Healy dba Healy Excavating | BRS Tiling and Excavation | |||||||||
Funding Source: 100% REAP OS Acquisition & Development, | 4123 NW 95th PL | 3483 Perkins Ave | 3260 Fletcher Ave | ||||||||||
Polk City IA 50226 | Lake View IA 51450 | Lake City IA 51449 | |||||||||||
Plan Sets Requested: 0 | Quantities | 712-830-4515 | 712-665-4500 | 712-210-3049 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $3,000.00 | $3,000.00 | $1,500.00 | $1,500.00 | ||||
2 | Remove & Dispose of Existing Culverts | 1 | L.S. | $4,400.00 | $4,400.00 | $8,500.00 | $8,500.00 | $8,500.00 | $8,500.00 | ||||
3 | Install 87"x63" Arch CMP Culvert | 70 | L.F. | $125.00 | $8,750.00 | $175.00 | $12,250.00 | $247.00 | $17,290.00 | ||||
4 | Granular Pipe Bedding | 45 | Tons | $25.00 | $1,125.00 | $45.50 | $2,047.50 | $50.00 | $2,250.00 | ||||
5 | Rolled Erosion Control Matting | 800 | S.Y. | $3.00 | $2,400.00 | $2.75 | $2,200.00 | $1.25 | $1,000.00 | ||||
6 | Site Restoration/Seeding | 1 | L.S. | $1,000.00 | $1,000.00 | $1,800.00 | $1,800.00 | $500.00 | $500.00 | ||||
$22,675.00 | $29,797.50 | $31,040.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $49,000.00 | Contractor: | Richards Construction Co., Inc. | JNC Construction, LLC | Landau Golf Corp | |||||||||
Funding Source: 100% REAP OS Acquisition & Development, | 2721 Sierra Ave | 609 3rd St | 16601 300th St | ||||||||||
Sac City IA 50583 | Clearfield IA 50840 | Mason City IA 50401 | |||||||||||
Plan Sets Requested: 0 | Quantities | 712-662-4421 | 641-344-4119 | 641-430-8491 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $1,000.00 | $1,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | ||||
2 | Remove & Dispose of Existing Culverts | 1 | L.S. | $15,000.00 | $15,000.00 | $13,600.00 | $13,600.00 | $11,900.00 | $11,900.00 | ||||
3 | Install 87"x63" Arch CMP Culvert | 70 | L.F. | $160.00 | $11,200.00 | $168.93 | $11,825.10 | $140.00 | $9,800.00 | ||||
4 | Granular Pipe Bedding | 45 | Tons | $40.00 | $1,800.00 | $40.00 | $1,800.00 | $60.00 | $2,700.00 | ||||
5 | Rolled Erosion Control Matting | 800 | S.Y. | $2.68 | $2,144.00 | $1.88 | $1,504.00 | $2.00 | $1,600.00 | ||||
6 | Site Restoration/Seeding | 1 | L.S. | $2,000.00 | $2,000.00 | $3,000.00 | $3,000.00 | $6,000.00 | $6,000.00 | ||||
$33,144.00 | $37,729.10 | $38,000.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $49,000.00 | Contractor: | Nagle Land Tiling Inc. | Leroy & Son's Inc. | L.A. Carlson Contracting, Inc. | |||||||||
Funding Source: 100% REAP OS Acquisition & Development, | 1326 230th St | 405 Dunlap St | 20984 C-43 | ||||||||||
Garwin IA 50632 | Arcadia IA 51430 | Merrill IA 51038-8674 | |||||||||||
Plan Sets Requested: 0 | Quantities | 641-751-8614 | 712-689-2470 | 712-947-0002 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $7,500.00 | $7,500.00 | $4,000.00 | $4,000.00 | $6,000.00 | $6,000.00 | ||||
2 | Remove & Dispose of Existing Culverts | 1 | L.S. | $7,500.00 | $7,500.00 | $16,000.00 | $16,000.00 | $32,000.00 | $32,000.00 | ||||
3 | Install 87"x63" Arch CMP Culvert | 70 | L.F. | $165.00 | $11,550.00 | $380.00 | $26,600.00 | $420.00 | $29,400.00 | ||||
4 | Granular Pipe Bedding | 45 | Tons | $45.00 | $2,025.00 | $65.00 | $2,925.00 | $53.00 | $2,385.00 | ||||
5 | Rolled Erosion Control Matting | 800 | S.Y. | $5.25 | $4,200.00 | $2.50 | $2,000.00 | $5.00 | $4,000.00 | ||||
6 | Site Restoration/Seeding | 1 | L.S. | $5,500.00 | $5,500.00 | $2,000.00 | $2,000.00 | $5,000.00 | $5,000.00 | ||||
$38,275.00 | $53,525.00 | $78,785.00 | |||||||||||
10 | 11 | 12 | |||||||||||
Estimated Cost: $49,000.00 | Contractor: | Joy Dirt Construction | |||||||||||
Funding Source: 100% REAP OS Acquisition & Development, | 202 State Street | ||||||||||||
Cushing IA 51018 | |||||||||||||
Plan Sets Requested: 0 | Quantities | 712-384-2700 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $8,900.00 | $8,900.00 | $0.00 | $0.00 | ||||||
2 | Remove & Dispose of Existing Culverts | 1 | L.S. | $45,800.00 | $45,800.00 | $0.00 | $0.00 | ||||||
3 | Install 87"x63" Arch CMP Culvert | 70 | L.F. | $214.00 | $14,980.00 | $0.00 | $0.00 | ||||||
4 | Granular Pipe Bedding | 45 | Tons | $72.00 | $3,240.00 | $0.00 | $0.00 | ||||||
5 | Rolled Erosion Control Matting | 800 | S.Y. | $20.00 | $16,000.00 | $0.00 | $0.00 | ||||||
6 | Site Restoration/Seeding | 1 | L.S. | $13,500.00 | $13,500.00 | $0.00 | $0.00 | ||||||
$102,420.00 | $0.00 | $0.00 | |||||||||||