IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Black Hawk Wildlife Unit | Date: 6/15/2017 | Project No. |
| Shimon Boat Ramp and Channel Cleaning | County: | POCAHONTAS | Time: 3:00 p.m. | 17-02-76-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $25,000.00 | Contractor: | Central Iowa Dirt & Demo | Schmitt Construction Co. | Lund Construction, Inc. | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 2066 290th St | 3766 Otter Ave | 1185 250th St PO Box 181 | ||||||||||
| Kamrar IA 50132 | Wall Lake IA 51466 | Eagle Grove IA 50533 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 515-539-4054 | 712-664-2419 | 515-448-4398 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $2,000.00 | $2,000.00 | $750.00 | $750.00 | $2,500.00 | $2,500.00 | ||||
| 2 | Channel Cleaning Between Pools | 1 | L.S. | $2,500.00 | $2,500.00 | $3,000.00 | $3,000.00 | $3,125.00 | $3,125.00 | ||||
| 3 | Channel Excavation at Ramp | 1 | L.S. | $9,600.00 | $9,600.00 | $10,000.00 | $10,000.00 | $10,800.00 | $10,800.00 | ||||
| 4 | Parking Lot Construction | 1 | L.S. | $1,000.00 | $1,000.00 | $2,500.00 | $2,500.00 | $1,800.00 | $1,800.00 | ||||
| 5 | Class ‘A’ Rock for Parking & Ramp | 240 | Tons | $20.00 | $4,800.00 | $22.00 | $5,280.00 | $23.05 | $5,532.00 | ||||
| 6 | Remove Existing Concrete Culvert | 1 | L.S. | $750.00 | $750.00 | $1,000.00 | $1,000.00 | $550.00 | $550.00 | ||||
| 7 | 18” CMP Culvert | 40 | L.F. | $25.00 | $1,000.00 | $25.00 | $1,000.00 | $17.77 | $710.80 | ||||
| 8 | 18” CMP Apron | 2 | Each | $250.00 | $500.00 | $125.00 | $250.00 | $120.95 | $241.90 | ||||
| 9 | 30” Concrete Apron | 1 | Each | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | $825.00 | $825.00 | ||||
| $23,650.00 | $24,780.00 | $26,084.70 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $25,000.00 | Contractor: | Richards Construction Co., Inc. | Apex Companies, LLC | ||||||||||
| Funding Source: 100% Marine Fuel Tax, | 2721 Sierra Ave | 10052 Justin Dr., Ste L | |||||||||||
| Sac City IA 50583 | Urbandale IA 50322 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 712-662-4421 | 515-727-8025 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,000.00 | $3,000.00 | $3,999.20 | $3,999.20 | $0.00 | |||||
| 2 | Channel Cleaning Between Pools | 1 | L.S. | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $0.00 | |||||
| 3 | Channel Excavation at Ramp | 1 | L.S. | $2,000.00 | $2,000.00 | $12,000.00 | $12,000.00 | $0.00 | |||||
| 4 | Parking Lot Construction | 1 | L.S. | $3,000.00 | $3,000.00 | $6,000.00 | $6,000.00 | $0.00 | |||||
| 5 | Class ‘A’ Rock for Parking & Ramp | 240 | Tons | $28.00 | $6,720.00 | $24.17 | $5,800.80 | $0.00 | |||||
| 6 | Remove Existing Concrete Culvert | 1 | L.S. | $2,500.00 | $2,500.00 | $3,200.00 | $3,200.00 | $0.00 | |||||
| 7 | 18” CMP Culvert | 40 | L.F. | $37.50 | $1,500.00 | $37.50 | $1,500.00 | $0.00 | |||||
| 8 | 18” CMP Apron | 2 | Each | $250.00 | $500.00 | $250.00 | $500.00 | $0.00 | |||||
| 9 | 30” Concrete Apron | 1 | Each | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 | $0.00 | |||||
| $26,720.00 | $41,000.00 | $0.00 | |||||||||||
4/1/2026