| Bids For: | Location: | Manchester Hatchery | Date: 5/18/2017 | Project No. |
| Fish Room Remodel | County: | DELAWARE | Time: 11:00 a.m. | 17-03-28-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $154,000.00 | Contractor: | Loecke Building Service, Inc. | Matt Construction, Inc. | ||||||||||
| Funding Source: 75% Federal-DJ, 25% REAP Land Management, | 1501 210th St | 203 Y Ave | |||||||||||
| Manchester IA 52057 | Sumner IA 50674 | ||||||||||||
| Plan Sets Requested: 18 | Quantities | 563-927-5677 | 563-578-8418 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | DEMOLITION | 1 | L.S. | $17,525.00 | $17,525.00 | $5,000.00 | $5,000.00 | $0.00 | |||||
| 2 | ELECTRICAL & LIGHTING | 1 | L.S. | $56,400.00 | $56,400.00 | $62,000.00 | $62,000.00 | $0.00 | |||||
| 3 | DOORS, FRAMES & HARDWARE | 1 | L.S. | $16,500.00 | $16,500.00 | $11,000.00 | $11,000.00 | $0.00 | |||||
| 4 | SPRAY FOAM INSULATION | 1 | L.S. | $13,411.00 | $13,411.00 | $17,000.00 | $17,000.00 | $0.00 | |||||
| 5 | HDPE CEILING, MOLDING AND NAILERS | 1 | L.S. | $28,400.00 | $28,400.00 | $47,000.00 | $47,000.00 | $0.00 | |||||
| 6 | WALL INFILLS | 1 | L.S. | $1,960.00 | $1,960.00 | $1,000.00 | $1,000.00 | $0.00 | |||||
| 7 | EXHAUST FAN | 1 | L.S. | $4,320.00 | $4,320.00 | $3,000.00 | $3,000.00 | $0.00 | |||||
| 8 | MOBILIZATION | 1 | L.S. | $1,500.00 | $1,500.00 | $10,000.00 | $10,000.00 | $0.00 | |||||
| $140,016.00 | $156,000.00 | $0.00 | |||||||||||
| Alternate | |||||||||||||
| 9 | MECHANICAL: UNIT HEATERS | 1 | L.S. | $11,950.00 | $11,950.00 | $17,000.00 | $17,000.00 | $0.00 | |||||
| Alternate | |||||||||||||
| 10 | MECHANICAL: DEHUMIDIFICATION SYSTEM | 1 | L.S. | $39,630.00 | $39,630.00 | $67,000.00 | $67,000.00 | $0.00 | |||||
| Alternate | |||||||||||||
| 11 | WINDOWS | 1 | L.S. | $15,115.00 | $15,115.00 | $9,000.00 | $9,000.00 | $0.00 | |||||
| $206,711.00 | $249,000.00 | $0.00 | |||||||||||