 Bids For:  Location:   Big Spring Hatchery  Date: 7/20/2017  Project No.  
  Replace main water inlet pipe  County:   CLAYTON  Time: 11:00 a.m.  17-03-22-02

 

 
1
2
3
Estimated Cost: $289,000.00
Contractor: 
Rays Excavating, LLCMatt Construction Inc.Tschigffrie Excavating Co
Funding Source: 75% Federal-DJ, 25% REAP Land Management, 404 E Union St
203 Y Ave
425 Julian Dubuque Dr
PO Box 3280
Edgewood IA  52042Sumner IA  50674Dubuque IA  52003
Plan Sets Requested: 2
Quantities
56392872905635788418563-557-7450
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$40,000.00$40,000.00 $10,000.00$10,000.00 $28,400.00$28,400.00 
230 INCH DIA. C 905-DR 26 PVC PIPE700L.F.$87.21$61,047.00 $252.00$176,400.00 $269.00$188,300.00 
324 INCH DIA. C 905-DR 26 PVC PIPE163L.F.$62.23$10,143.49 $155.00$25,265.00 $219.00$35,697.00 
48 INCH DIA. C 900-DR 26 PVC CONNECTION PIPE240L.F.$24.91$5,978.40 $123.00$29,520.00 $96.80$23,232.00 
530 INCH C-20 WATERMAN CANAL GATE WITH STAINLESS STEEL GUIDE RAILS & STEM3Each$6,000.00$18,000.00 $4,885.00$14,655.00 $4,900.00$14,700.00 
624 INCH C-20 WATERMAN CANAL GATE WITH STAINLESS STEEL GUIDE RAILS & STEM1Each$2,000.00$2,000.00 $3,570.00$3,570.00 $3,600.00$3,600.00 
78 INCH C-20 WATERMAN CANAL GATE WITH STAINLESS STEEL GUIDE RAILS & STEM24Each$1,400.00$33,600.00 $1,149.75$27,594.00 $1,400.00$33,600.00 
8CONNECTING 30 INCH PIPE TO SPRING HEADWALL1L.S.$5,000.00$5,000.00 $10,000.00$10,000.00 $1,100.00$1,100.00 
9CONNECTING 30 INCH PIPE TO MANHOLE4Each$5,000.00$20,000.00 $2,000.00$8,000.00 $872.00$3,488.00 
10CONNECTING 24 INCH PIPE TO MANHOLE1Each$5,000.00$5,000.00 $2,000.00$2,000.00 $872.00$872.00 
11CONNECTING 8 INCH PIPE TO RACEWAYS24Each$3,000.00$72,000.00 $1,000.00$24,000.00 $568.00$13,632.00 
12FULL DEPTH SAW CUT650L.F.$6.00$3,900.00 $2.50$1,625.00 $2.70$1,755.00 
13PAVEMENT REMOVAL510S.Y.$7.50$3,825.00 $20.00$10,200.00 $3.35$1,708.50 
146 INCH OF CLASS "A" CRUSHED STONE164Tons$14.00$2,296.00 $23.00$3,772.00 $12.60$2,066.40 
152 WEEK OF PUMP RENTAL & OPERATIONAL COST1L.S.$14,000.00$14,000.00 $7,000.00$7,000.00 $2,700.00$2,700.00 
      $296,789.89  $353,601.00  $354,850.90 
 



 