IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Big Spring Hatchery | Date: 7/20/2017 | Project No. |
| Replace main water inlet pipe | County: | CLAYTON | Time: 11:00 a.m. | 17-03-22-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $289,000.00 | Contractor: | Rays Excavating, LLC | Matt Construction Inc. | Tschigffrie Excavating Co | |||||||||
| Funding Source: 75% Federal-DJ, 25% REAP Land Management, | 404 E Union St | 203 Y Ave | 425 Julian Dubuque Dr PO Box 3280 | ||||||||||
| Edgewood IA 52042 | Sumner IA 50674 | Dubuque IA 52003 | |||||||||||
| Plan Sets Requested: 2 | Quantities | 5639287290 | 5635788418 | 563-557-7450 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION | 1 | L.S. | $40,000.00 | $40,000.00 | $10,000.00 | $10,000.00 | $28,400.00 | $28,400.00 | ||||
| 2 | 30 INCH DIA. C 905-DR 26 PVC PIPE | 700 | L.F. | $87.21 | $61,047.00 | $252.00 | $176,400.00 | $269.00 | $188,300.00 | ||||
| 3 | 24 INCH DIA. C 905-DR 26 PVC PIPE | 163 | L.F. | $62.23 | $10,143.49 | $155.00 | $25,265.00 | $219.00 | $35,697.00 | ||||
| 4 | 8 INCH DIA. C 900-DR 26 PVC CONNECTION PIPE | 240 | L.F. | $24.91 | $5,978.40 | $123.00 | $29,520.00 | $96.80 | $23,232.00 | ||||
| 5 | 30 INCH C-20 WATERMAN CANAL GATE WITH STAINLESS STEEL GUIDE RAILS & STEM | 3 | Each | $6,000.00 | $18,000.00 | $4,885.00 | $14,655.00 | $4,900.00 | $14,700.00 | ||||
| 6 | 24 INCH C-20 WATERMAN CANAL GATE WITH STAINLESS STEEL GUIDE RAILS & STEM | 1 | Each | $2,000.00 | $2,000.00 | $3,570.00 | $3,570.00 | $3,600.00 | $3,600.00 | ||||
| 7 | 8 INCH C-20 WATERMAN CANAL GATE WITH STAINLESS STEEL GUIDE RAILS & STEM | 24 | Each | $1,400.00 | $33,600.00 | $1,149.75 | $27,594.00 | $1,400.00 | $33,600.00 | ||||
| 8 | CONNECTING 30 INCH PIPE TO SPRING HEADWALL | 1 | L.S. | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 | $1,100.00 | $1,100.00 | ||||
| 9 | CONNECTING 30 INCH PIPE TO MANHOLE | 4 | Each | $5,000.00 | $20,000.00 | $2,000.00 | $8,000.00 | $872.00 | $3,488.00 | ||||
| 10 | CONNECTING 24 INCH PIPE TO MANHOLE | 1 | Each | $5,000.00 | $5,000.00 | $2,000.00 | $2,000.00 | $872.00 | $872.00 | ||||
| 11 | CONNECTING 8 INCH PIPE TO RACEWAYS | 24 | Each | $3,000.00 | $72,000.00 | $1,000.00 | $24,000.00 | $568.00 | $13,632.00 | ||||
| 12 | FULL DEPTH SAW CUT | 650 | L.F. | $6.00 | $3,900.00 | $2.50 | $1,625.00 | $2.70 | $1,755.00 | ||||
| 13 | PAVEMENT REMOVAL | 510 | S.Y. | $7.50 | $3,825.00 | $20.00 | $10,200.00 | $3.35 | $1,708.50 | ||||
| 14 | 6 INCH OF CLASS "A" CRUSHED STONE | 164 | Tons | $14.00 | $2,296.00 | $23.00 | $3,772.00 | $12.60 | $2,066.40 | ||||
| 15 | 2 WEEK OF PUMP RENTAL & OPERATIONAL COST | 1 | L.S. | $14,000.00 | $14,000.00 | $7,000.00 | $7,000.00 | $2,700.00 | $2,700.00 | ||||
| $296,789.89 | $353,601.00 | $354,850.90 | |||||||||||