IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Rice Lake WMA  Date: 6/22/2017  Project No.  
  Boat Ramp Upgrades  County:   WORTH  Time: 3:00 p.m.  17-03-98-01

 

 
1
2
3
Estimated Cost: $12,000.00
Contractor: 
Larson Contracting Central, LLCBurr Oak SpringsMatt Construction, Inc.
Funding Source: 100% Marine Fuel Tax, 508 West Main St
2113 Co. Rd W14
203 Y Ave
Lake Mills IA  50450Ridgeway IA  52165Sumner IA  50674
Plan Sets Requested: 0
Quantities
641-592-5800563-737-2510563-578-8418
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$600.00$600.00 $1,000.00$1,000.00 $2,000.00$2,000.00 
2Special Backfill50Tons$11.06$553.00 $20.00$1,000.00 $18.70$935.00 
3Ramp Shoulder, Clean 3" Cr. Stone27Tons$18.76$506.52 $20.00$540.00 $19.40$523.80 
4Excavation, Class 10, Roadway14C.Y.$3.70$51.80 $20.00$280.00 $10.00$140.00 
5PC Concrete 6", Ramp Site A148S.Y.$60.00$8,880.00 $30.00$4,440.00 $64.00$9,472.00 
6PC Concrete 6", Walkway Site B315S.F.$4.75$1,496.25 $30.00$9,450.00 $4.50$1,417.50 
7Painted Pavement Markings8.09STA.$136.96$1,108.006 $25.00$202.25 $300.00$2,427.00 
8Painted Handicap Symbol2Each$146.50$293.00 $100.00$200.00 $150.00$300.00 
      $13,488.576  $17,112.25  $17,215.30 
 



 

5/4/2024