Bids For: | Location: | Rice Lake WMA | Date: 6/22/2017 | Project No. |
Boat Ramp Upgrades | County: | WORTH | Time: 3:00 p.m. | 17-03-98-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $12,000.00 | Contractor: | Larson Contracting Central, LLC | Burr Oak Springs | Matt Construction, Inc. | |||||||||
Funding Source: 100% Marine Fuel Tax, | 508 West Main St | 2113 Co. Rd W14 | 203 Y Ave | ||||||||||
Lake Mills IA 50450 | Ridgeway IA 52165 | Sumner IA 50674 | |||||||||||
Plan Sets Requested: 0 | Quantities | 641-592-5800 | 563-737-2510 | 563-578-8418 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $600.00 | $600.00 | $1,000.00 | $1,000.00 | $2,000.00 | $2,000.00 | ||||
2 | Special Backfill | 50 | Tons | $11.06 | $553.00 | $20.00 | $1,000.00 | $18.70 | $935.00 | ||||
3 | Ramp Shoulder, Clean 3" Cr. Stone | 27 | Tons | $18.76 | $506.52 | $20.00 | $540.00 | $19.40 | $523.80 | ||||
4 | Excavation, Class 10, Roadway | 14 | C.Y. | $3.70 | $51.80 | $20.00 | $280.00 | $10.00 | $140.00 | ||||
5 | PC Concrete 6", Ramp Site A | 148 | S.Y. | $60.00 | $8,880.00 | $30.00 | $4,440.00 | $64.00 | $9,472.00 | ||||
6 | PC Concrete 6", Walkway Site B | 315 | S.F. | $4.75 | $1,496.25 | $30.00 | $9,450.00 | $4.50 | $1,417.50 | ||||
7 | Painted Pavement Markings | 8.09 | STA. | $136.96 | $1,108.006 | $25.00 | $202.25 | $300.00 | $2,427.00 | ||||
8 | Painted Handicap Symbol | 2 | Each | $146.50 | $293.00 | $100.00 | $200.00 | $150.00 | $300.00 | ||||
$13,488.576 | $17,112.25 | $17,215.30 | |||||||||||