|
IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Saylorville Wildlife Unit | Date: 8/24/2017 | Project No. |
| Dunbar slough boat ramp | County: | GREENE | Time: 3:00 p.m. | 17-02-37-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $20,000.00 | Contractor: | Caliber Concrete LLC | Richards Construction Co., Inc. | ||||||||||
| Funding Source: 100% Marine Fuel Tax, | 309 Audubon St PO Box 248 | 2721 Sierra Ave | |||||||||||
| Adair IA 50002 | Sac City IA 50583 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 515-979-2004 | 712-662-4421 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Grading and Prep | 1 | L.S. | $1,354.38 | $1,354.38 | $2,000.00 | $2,000.00 | $0.00 | |||||
| 2 | 6" Concrete Ramp, Reinforced | 1140 | S.F. | $7.64 | $8,709.60 | $14.00 | $15,960.00 | $0.00 | |||||
| 3 | Class "A" Base Material | 8 | Tons | $88.95 | $711.60 | $50.00 | $400.00 | $0.00 | |||||
| 4 | Class "D" Riprap | 32 | Tons | $82.43 | $2,637.76 | $68.00 | $2,176.00 | $0.00 | |||||
| 5 | Mobilization and Cleanup | 1 | L.S. | $5,160.00 | $5,160.00 | $2,450.00 | $2,450.00 | $0.00 | |||||
| $18,573.34 | $22,986.00 | $0.00 | |||||||||||
4/2/2026