IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Odessa Wildlife Unit | Date: 8/17/2017 | Project No. |
Boat Ramp Replacement | County: | LOUISA | Time: 3:00 p.m. | 17-06-58-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $20,000.00 | Contractor: | Triple B Construction Corp. | |||||||||||
Funding Source: 100% Marine Fuel Tax, | 2272 Spicer Ave | ||||||||||||
Wilton IA 52778 | |||||||||||||
Plan Sets Requested: 0 | Quantities | 319-631-0320 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $6,500.00 | $6,500.00 | $0.00 | $0.00 | ||||||
2 | Removal of Existing Boat Ramp | 50 | S.Y. | $20.00 | $1,000.00 | $0.00 | $0.00 | ||||||
3 | Granular Subbase | 24 | Tons | $50.00 | $1,200.00 | $0.00 | $0.00 | ||||||
4 | PCC Boat Ramp, 6" Reinforced | 60 | S.Y. | $75.00 | $4,500.00 | $0.00 | $0.00 | ||||||
5 | Class A Stone | 100 | Tons | $30.00 | $3,000.00 | $0.00 | $0.00 | ||||||
$16,200.00 | $0.00 | $0.00 | |||||||||||