IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Fort Defiance State Park | Date: 2/21/2019 | Project No. |
Lodge Restoration | County: | EMMET | Time: 3:00 p.m. | 17-01-32-02 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $88,500.00 | Contractor: | Under Construction | |||||||||||
Funding Source: 100% REAP Land Management, | 902 Oak Hill Rd | ||||||||||||
Estherville IA 51334 | |||||||||||||
Plan Sets Requested: 0 | Quantities | 7123807757 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Demolition & Salvage | 1 | L.S. | $4,750.00 | $4,750.00 | $0.00 | $0.00 | ||||||
2 | Roof Sheathing (OSB) | 10 | Each | $125.00 | $1,250.00 | $0.00 | $0.00 | ||||||
3 | Roofing & Flashing | 1 | L.S. | $17,500.00 | $17,500.00 | $0.00 | $0.00 | ||||||
4 | Timber Railing Replacement | 1 | L.S. | $8,625.00 | $8,625.00 | $0.00 | $0.00 | ||||||
5 | Wood Repair & Replacement | 1 | L.S. | $5,225.00 | $5,225.00 | $0.00 | $0.00 | ||||||
6 | Log Chinking & Exterior Staining | 1 | L.S. | $27,250.00 | $27,250.00 | $0.00 | $0.00 | ||||||
7 | Stair Repair & Repointing | 1 | L.S. | $6,750.00 | $6,750.00 | $0.00 | $0.00 | ||||||
8 | Mobilization | 1 | L.S. | $10,000.00 | $10,000.00 | $0.00 | $0.00 | ||||||
$81,350.00 | $0.00 | $0.00 | |||||||||||