IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Green Island WMA | Date: 5/26/2016 | Project No. |
Fish Lake Road Culvert Replacement | County: | JACKSON | Time: 3:00 pm | 16-06-49-01 |
![]() | 1 | 2 | 3 | ![]() | |||||||||
Estimated Cost: $15,000.00 | Contractor: | ![]() | Lansing Brothers Construction Co. Inc. | Mainline Excavating Co. Inc. | Miller Trucking & Excavating | ![]() | |||||||
Funding Source: 100% Park & Institutional Road Fund, | ![]() | 101 East 1st St PO Box 36 | ![]() | 8180 Seippel Court | ![]() | 3303 John Deere Rd | ![]() | ||||||
![]() | Luxemburg IA 52056 | ![]() | Dubuque IA 52002 | ![]() | Silvis IL 61282 | ![]() | |||||||
Plan Sets Requested: 0 | Quantities | ![]() | 563-543-7360 | ![]() | 563-583-1888 | ![]() | 309-755-7644 | ![]() | |||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization | 1 | L.S. | ![]() | $2,000.00 | $2,000.00 | ![]() | $8,700.00 | $8,700.00 | ![]() | $2,500.00 | $2,500.00 | ![]() |
2 | CMP Culvert Removal | 160 | L.F. | ![]() | $5.00 | $800.00 | ![]() | $32.00 | $5,120.00 | ![]() | $15.00 | $2,400.00 | ![]() |
3 | CMP Culvert, 42” Dia. | 140 | L.F. | ![]() | $70.00 | $9,800.00 | ![]() | $66.00 | $9,240.00 | ![]() | $150.00 | $21,000.00 | ![]() |
4 | CMP F.E.S., 42” Dia. | 4 | Each | ![]() | $800.00 | $3,200.00 | ![]() | $750.00 | $3,000.00 | ![]() | $750.00 | $3,000.00 | ![]() |
5 | Bedding Material, Class 1 Crushed Rock | 40 | Tons | ![]() | $20.00 | $800.00 | ![]() | $21.00 | $840.00 | ![]() | $25.00 | $1,000.00 | ![]() |
6 | Road Stone, Class A | 15 | Tons | ![]() | $30.00 | $450.00 | ![]() | $27.00 | $405.00 | ![]() | $25.00 | $375.00 | ![]() |
7 | Site Restoration | 1 | L.S. | ![]() | $1,800.00 | $1,800.00 | ![]() | $2,700.00 | $2,700.00 | ![]() | $1,500.00 | $1,500.00 | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$18,850.00 | ![]() | $30,005.00 | ![]() | $31,775.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
![]() | 4 | 5 | 6 | ![]() | |||||||||
Estimated Cost: $15,000.00 | Contractor: | ![]() | Weaver's Inc. | Dingman Construction | ![]() | ||||||||
Funding Source: 100% Park & Institutional Road Fund, | ![]() | 1524 Highway 130 | ![]() | 1265 240th St | ![]() | ![]() | |||||||
![]() | Tipton IA 52772 | ![]() | Creston IA 50801 | ![]() | ![]() | ||||||||
Plan Sets Requested: 0 | Quantities | ![]() | 563-886-6556 | ![]() | 641-247-1431 | ![]() | ![]() | ||||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization | 1 | L.S. | ![]() | $6,700.00 | $6,700.00 | ![]() | $2,500.00 | $2,500.00 | ![]() | $0.00 | ![]() | |
2 | CMP Culvert Removal | 160 | L.F. | ![]() | $49.20 | $7,872.00 | ![]() | $92.00 | $14,720.00 | ![]() | $0.00 | ![]() | |
3 | CMP Culvert, 42” Dia. | 140 | L.F. | ![]() | $102.00 | $14,280.00 | ![]() | $105.00 | $14,700.00 | ![]() | $0.00 | ![]() | |
4 | CMP F.E.S., 42” Dia. | 4 | Each | ![]() | $854.00 | $3,416.00 | ![]() | $625.00 | $2,500.00 | ![]() | $0.00 | ![]() | |
5 | Bedding Material, Class 1 Crushed Rock | 40 | Tons | ![]() | $30.00 | $1,200.00 | ![]() | $18.75 | $750.00 | ![]() | $0.00 | ![]() | |
6 | Road Stone, Class A | 15 | Tons | ![]() | $19.00 | $285.00 | ![]() | $20.00 | $300.00 | ![]() | $0.00 | ![]() | |
7 | Site Restoration | 1 | L.S. | ![]() | $500.00 | $500.00 | ![]() | $2,500.00 | $2,500.00 | ![]() | $0.00 | ![]() | |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$34,253.00 | ![]() | $37,970.00 | ![]() | $0.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |