IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Pleasant Creek State Recreation Area  Date: 4/21/2016  Project No.  
  Shoreline Stabilization  County:   LINN  Time: 11:00 AM  15-06-57-03

 

 
1
2
3
Estimated Cost: $2,700,000.00
Contractor: 
Peterson Contractors, Inc.CJ Moyna & Sons, Inc.Cornerstone Excavating Inc
Funding Source: 50% Lake Restoration, 25% Marine Fuel Tax, 25% Federal-Boat Safety (Coast Guard), 104 Black Hawk St
24412 Hwy 13
PO Box 429
1320 West Main St
PO Box 928
Reinbeck IA  50669Elkader IA  52043Washington IA  52353
Plan Sets Requested: 0
Quantities
319-345-2713563-245-1442319-653-3957
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1EXCAVATION, CLASS 1037207C.Y.$3.15$117,202.05 $2.50$93,017.50 $1.95$72,553.65 
2REVETMENT, CLASS E - SHORELINE47318Tons$32.00$1,514,176.00 $37.50$1,774,425.00 $36.70$1,736,570.60 
3REVETMENT, CLASS E - ISLAND1330Tons$36.00$47,880.00 $37.50$49,875.00 $36.70$48,811.00 
4ENGINEERING FABRIC - SHORELINE15310S.Y.$1.50$22,965.00 $1.27$19,443.70 $1.35$20,668.50 
5ENGINEERING FABRIC - ISLAND3356S.Y.$1.70$5,705.20 $1.50$5,034.00 $1.35$4,530.60 
6ENGINEERING FABRIC - HABITAT1010S.Y.$1.80$1,818.00 $1.50$1,515.00 $1.35$1,363.50 
7CONCRETE GROUT334C.Y.$191.00$63,794.00 $235.00$78,490.00 $205.00$68,470.00 
8SHOT ROCK - WASTE POINTS4120Tons$21.65$89,198.00 $17.50$72,100.00 $19.45$80,134.00 
9SHOT ROCK - HABITAT2990Tons$26.00$77,740.00 $16.00$47,840.00 $19.45$58,155.50 
103/8" MINUS CRUSHED STONE51Tons$24.00$1,224.00 $15.00$765.00 $12.25$624.75 
116" STRUCTURAL CONCRETE - BOAT RAMP1314S.Y.$50.00$65,700.00 $48.24$63,387.36 $75.00$98,550.00 
126" PCC SIDEWALK72S.Y.$54.00$3,888.00 $45.09$3,246.48 $65.00$4,680.00 
13CLASS A CRUSHED STONE3734Tons$14.75$55,076.50 $16.00$59,744.00 $13.25$49,475.50 
14ROAD GRADING5069L.F.$0.35$1,774.15 $1.50$7,603.50 $2.00$10,138.00 
15DITCH CLEANOUT10138L.F.$1.15$11,658.70 $1.00$10,138.00 $2.85$28,893.30 
16PAVEMENT REMOVAL955S.Y.$3.15$3,008.25 $3.50$3,342.50 $4.00$3,820.00 
17GEOCELL, 6"8388S.F.$2.00$16,776.00 $3.00$25,164.00 $3.40$28,519.20 
18POROUS BACKFILL (IDOT GRAD. 20, 21) PEA GRAVEL614Tons$25.50$15,657.00 $29.00$17,806.00 $27.00$16,578.00 
19SHEET PILE940S.F.$31.47$29,581.80 $40.00$37,600.00 $27.50$25,850.00 
20BRIDGE PLANKS282L.F.$31.50$8,883.00 $25.00$7,050.00 $36.00$10,152.00 
21ALUMINUM RAIL SECTION5Each$966.80$4,834.00 $3,000.00$15,000.00 $1,250.00$6,250.00 
22RELOCATE POWER POLE1Each$800.00$800.00 $1,500.00$1,500.00 $3,150.00$3,150.00 
23SITE RESTORATION1L.S.$23,000.00$23,000.00 $35,000.00$35,000.00 $20,000.00$20,000.00 
24CONSTRUCTION SURVEY1L.S.$14,000.00$14,000.00 $5,000.00$5,000.00 $10,000.00$10,000.00 
25MOBILIZATION1L.S.$34,200.00$34,200.00 $25,000.00$25,000.00 $75,000.00$75,000.00 
      $2,230,539.65  $2,459,087.04  $2,482,938.10 
Alternate        
26LOWER LAKE EARLY1L.S.$0.00$0.00 $0.00$0.00 $0.00$0.00 
      $2,230,539.65  $2,459,087.04  $2,482,938.10 
 
4
5
6
Estimated Cost: $2,700,000.00
Contractor: 
Langman Construction, Inc.Legacy Corporation of ILConnolly Construction Inc.
Funding Source: 50% Lake Restoration, 25% Marine Fuel Tax, 25% Federal-Boat Safety (Coast Guard), 220 34th Ave
16322 Barstow Rd
18409 N Cascade Rd
Rock Island IL  61201East Moline IL  61244Peosta IA  52068
Plan Sets Requested: 0
Quantities
309-786-8944309-203-1094563-876-3225
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1EXCAVATION, CLASS 1037207C.Y.$2.00$74,414.00 $4.00$148,828.00 $4.38$162,966.66 
2REVETMENT, CLASS E - SHORELINE47318Tons$36.50$1,727,107.00 $36.00$1,703,448.00 $40.05$1,895,085.90 
3REVETMENT, CLASS E - ISLAND1330Tons$36.50$48,545.00 $36.00$47,880.00 $44.28$58,892.40 
4ENGINEERING FABRIC - SHORELINE15310S.Y.$1.00$15,310.00 $2.00$30,620.00 $1.41$21,587.10 
5ENGINEERING FABRIC - ISLAND3356S.Y.$1.00$3,356.00 $2.00$6,712.00 $1.40$4,698.40 
6ENGINEERING FABRIC - HABITAT1010S.Y.$1.00$1,010.00 $2.00$2,020.00 $1.17$1,181.70 
7CONCRETE GROUT334C.Y.$125.00$41,750.00 $225.00$75,150.00 $194.40$64,929.60 
8SHOT ROCK - WASTE POINTS4120Tons$19.00$78,280.00 $19.50$80,340.00 $24.23$99,827.60 
9SHOT ROCK - HABITAT2990Tons$19.00$56,810.00 $19.50$58,305.00 $23.62$70,623.80 
103/8" MINUS CRUSHED STONE51Tons$30.00$1,530.00 $50.00$2,550.00 $26.96$1,374.96 
116" STRUCTURAL CONCRETE - BOAT RAMP1314S.Y.$60.00$78,840.00 $83.00$109,062.00 $98.58$129,534.12 
126" PCC SIDEWALK72S.Y.$60.00$4,320.00 $72.00$5,184.00 $66.55$4,791.60 
13CLASS A CRUSHED STONE3734Tons$15.00$56,010.00 $17.00$63,478.00 $17.46$65,195.64 
14ROAD GRADING5069L.F.$0.60$3,041.40 $2.50$12,672.50 $1.17$5,930.73 
15DITCH CLEANOUT10138L.F.$1.00$10,138.00 $3.25$32,948.50 $2.97$30,109.86 
16PAVEMENT REMOVAL955S.Y.$3.00$2,865.00 $8.50$8,117.50 $4.98$4,755.90 
17GEOCELL, 6"8388S.F.$1.25$10,485.00 $3.00$25,164.00 $2.20$18,453.60 
18POROUS BACKFILL (IDOT GRAD. 20, 21) PEA GRAVEL614Tons$28.00$17,192.00 $34.00$20,876.00 $36.76$22,570.64 
19SHEET PILE940S.F.$25.00$23,500.00 $30.00$28,200.00 $22.04$20,717.60 
20BRIDGE PLANKS282L.F.$6.00$1,692.00 $25.00$7,050.00 $16.49$4,650.18 
21ALUMINUM RAIL SECTION5Each$1,000.00$5,000.00 $500.00$2,500.00 $1,399.78$6,998.90 
22RELOCATE POWER POLE1Each$400.00$400.00 $5,000.00$5,000.00 $2,214.12$2,214.12 
23SITE RESTORATION1L.S.$1,000.00$1,000.00 $10,000.00$10,000.00 $30,444.81$30,444.81 
24CONSTRUCTION SURVEY1L.S.$1,000.00$1,000.00 $15,000.00$15,000.00 $9,609.09$9,609.09 
25MOBILIZATION1L.S.$251,500.00$251,500.00 $140,000.00$140,000.00 $73,625.70$73,625.70 
Alternate        
26LOWER LAKE EARLY1L.S.$0.00$0.00 -$10,000.00-$10,000.00 -$100.00-$100.00 
      $2,515,095.40  $2,631,105.50  $2,810,670.61 
 
7
8
9
Estimated Cost: $2,700,000.00
Contractor: 
Landwehr Construction, Inc.Cole Construction Co. Inc.Gehrke Inc
Funding Source: 50% Lake Restoration, 25% Marine Fuel Tax, 25% Federal-Boat Safety (Coast Guard),
PO Box 1086
24100 Queen Ave
1405 21st Ave
St Cloud MN  56302Keosauqua IA  52565Eldora IA  50627
Plan Sets Requested: 0
Quantities
320-252-1494319-592-3103641-858-3821
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1EXCAVATION, CLASS 1037207C.Y.$3.90$145,107.30 $2.85$106,039.95 $6.65$247,426.55 
2REVETMENT, CLASS E - SHORELINE47318Tons$45.25$2,141,139.50 $43.25$2,046,503.50 $38.90$1,840,670.20 
3REVETMENT, CLASS E - ISLAND1330Tons$55.00$73,150.00 $43.25$57,522.50 $44.23$58,825.90 
4ENGINEERING FABRIC - SHORELINE15310S.Y.$1.50$22,965.00 $2.10$32,151.00 $1.93$29,548.30 
5ENGINEERING FABRIC - ISLAND3356S.Y.$1.50$5,034.00 $2.10$7,047.60 $2.60$8,725.60 
6ENGINEERING FABRIC - HABITAT1010S.Y.$2.50$2,525.00 $2.10$2,121.00 $2.60$2,626.00 
7CONCRETE GROUT334C.Y.$150.00$50,100.00 $350.00$116,900.00 $150.00$50,100.00 
8SHOT ROCK - WASTE POINTS4120Tons$27.06$111,487.20 $25.50$105,060.00 $28.45$117,214.00 
9SHOT ROCK - HABITAT2990Tons$27.06$80,909.40 $25.50$76,245.00 $28.45$85,065.50 
103/8" MINUS CRUSHED STONE51Tons$29.00$1,479.00 $17.25$879.75 $36.12$1,842.12 
116" STRUCTURAL CONCRETE - BOAT RAMP1314S.Y.$10.00$13,140.00 $48.24$63,387.36 $67.00$88,038.00 
126" PCC SIDEWALK72S.Y.$25.00$1,800.00 $45.09$3,246.48 $67.00$4,824.00 
13CLASS A CRUSHED STONE3734Tons$15.10$56,383.40 $19.50$72,813.00 $20.50$76,547.00 
14ROAD GRADING5069L.F.$1.50$7,603.50 $2.96$15,004.24 $2.70$13,686.30 
15DITCH CLEANOUT10138L.F.$2.50$25,345.00 $3.00$30,414.00 $3.94$39,943.72 
16PAVEMENT REMOVAL955S.Y.$3.00$2,865.00 $7.00$6,685.00 $12.00$11,460.00 
17GEOCELL, 6"8388S.F.$2.50$20,970.00 $4.90$41,101.20 $2.50$20,970.00 
18POROUS BACKFILL (IDOT GRAD. 20, 21) PEA GRAVEL614Tons$36.71$22,539.94 $40.00$24,560.00 $43.50$26,709.00 
19SHEET PILE940S.F.$37.00$34,780.00 $50.00$47,000.00 $66.00$62,040.00 
20BRIDGE PLANKS282L.F.$20.53$5,789.46 $40.00$11,280.00 $46.00$12,972.00 
21ALUMINUM RAIL SECTION5Each$1,000.00$5,000.00 $845.00$4,225.00 $4,000.00$20,000.00 
22RELOCATE POWER POLE1Each$2,000.00$2,000.00 $2,500.00$2,500.00 $2,500.00$2,500.00 
23SITE RESTORATION1L.S.$30,000.00$30,000.00 $15,000.00$15,000.00 $42,000.00$42,000.00 
24CONSTRUCTION SURVEY1L.S.$15,000.00$15,000.00 $5,000.00$5,000.00 $10,000.00$10,000.00 
25MOBILIZATION1L.S.$18,000.00$18,000.00 $95,000.00$95,000.00 $167,000.00$167,000.00 
Alternate        
26LOWER LAKE EARLY1L.S.$0.00$0.00 -$500.00-$500.00 $0.00$0.00 
      $2,895,112.70  $2,987,186.58  $3,040,734.19 
 
10
11
12
Estimated Cost: $2,700,000.00
Contractor: 
Miller Trucking & Excavating
Funding Source: 50% Lake Restoration, 25% Marine Fuel Tax, 25% Federal-Boat Safety (Coast Guard), 3303 John Deere Rd


Silvis IL  61282    
Plan Sets Requested: 0
Quantities
309-755-7644
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1EXCAVATION, CLASS 1037207C.Y.$5.00$186,035.00 $0.00 $0.00 
2REVETMENT, CLASS E - SHORELINE47318Tons$45.00$2,129,310.00 $0.00 $0.00 
3REVETMENT, CLASS E - ISLAND1330Tons$45.00$59,850.00 $0.00 $0.00 
4ENGINEERING FABRIC - SHORELINE15310S.Y.$1.00$15,310.00 $0.00 $0.00 
5ENGINEERING FABRIC - ISLAND3356S.Y.$1.00$3,356.00 $0.00 $0.00 
6ENGINEERING FABRIC - HABITAT1010S.Y.$1.00$1,010.00 $0.00 $0.00 
7CONCRETE GROUT334C.Y.$160.00$53,440.00 $0.00 $0.00 
8SHOT ROCK - WASTE POINTS4120Tons$25.00$103,000.00 $0.00 $0.00 
9SHOT ROCK - HABITAT2990Tons$25.00$74,750.00 $0.00 $0.00 
103/8" MINUS CRUSHED STONE51Tons$25.00$1,275.00 $0.00 $0.00 
116" STRUCTURAL CONCRETE - BOAT RAMP1314S.Y.$50.00$65,700.00 $0.00 $0.00 
126" PCC SIDEWALK72S.Y.$50.00$3,600.00 $0.00 $0.00 
13CLASS A CRUSHED STONE3734Tons$15.00$56,010.00 $0.00 $0.00 
14ROAD GRADING5069L.F.$4.00$20,276.00 $0.00 $0.00 
15DITCH CLEANOUT10138L.F.$6.00$60,828.00 $0.00 $0.00 
16PAVEMENT REMOVAL955S.Y.$10.00$9,550.00 $0.00 $0.00 
17GEOCELL, 6"8388S.F.$3.00$25,164.00 $0.00 $0.00 
18POROUS BACKFILL (IDOT GRAD. 20, 21) PEA GRAVEL614Tons$40.00$24,560.00 $0.00 $0.00 
19SHEET PILE940S.F.$40.00$37,600.00 $0.00 $0.00 
20BRIDGE PLANKS282L.F.$45.00$12,690.00 $0.00 $0.00 
21ALUMINUM RAIL SECTION5Each$1,200.00$6,000.00 $0.00 $0.00 
22RELOCATE POWER POLE1Each$1,500.00$1,500.00 $0.00 $0.00 
23SITE RESTORATION1L.S.$45,000.00$45,000.00 $0.00 $0.00 
24CONSTRUCTION SURVEY1L.S.$20,000.00$20,000.00 $0.00 $0.00 
25MOBILIZATION1L.S.$75,000.00$75,000.00 $0.00 $0.00 
Alternate        
26LOWER LAKE EARLY1L.S.-$45,000.00-$45,000.00 $0.00 $0.00 
      $3,045,814.00  $0.00  $0.00 
 



 