 Bids For:  Location:   Lewis and Clark  Date: 4/21/2016  Project No.  
  Water Treatment System Replacement  County:   MONONA  Time: 11:00 a.m.  13-01-67-02

 

 
1
2
3
Estimated Cost: $293,000.00
Contractor: 
Lessard Contracting Inc.
Funding Source: 100% Infrastructure 2012, 2300 Blvd of Champions


Sioux City IA  51111    
Plan Sets Requested: 1
Quantities
712-252-4131
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION 1L.S.$33,380.00$33,380.00 $0.00 $0.00 
2CLEARING & GRUBBING1L.S.$5,700.00$5,700.00 $0.00 $0.00 
338’ X 22’ WATER TREAMENT BUILDING COMPLETE WITH GRADING1L.S.$125,470.00$125,470.00 $0.00 $0.00 
4158 GALLONS WX-451 AMTROL PRESSURE TANK2Each$7,250.00$14,500.00 $0.00 $0.00 
5STORAGE BUILDING MANIFOLD: WATER METER, VALVES, PRESSURE SWITCH, PRESSURE GAUGE, SCH. 80 PVC PIING ETC.1L.S.$21,750.00$21,750.00 $0.00 $0.00 
6CHLORINE FEED SYSTEM WITH ONE PUMP, 20 GALLON TANK AND SPILL PALLET COMPLETE1L.S.$4,650.00$4,650.00 $0.00 $0.00 
7TRIPLEX MULTI-MEDIA IRON FILTER SYSTEM COMPLETE WITH CHLORINE INJECTION PUMP, COMPLETE1L.S.$41,220.00$41,220.00 $0.00 $0.00 
8DUPLEX AUTOMAIC SOFTENER SYSTEM WITH BRINE TANK COMPLETE1L.S.$17,135.00$17,135.00 $0.00 $0.00 
9ELECTRICAL SERVICE AND PUMP CONTROLS COMPLETE WITH LIGHTING , HEATER AND 200 AMP CONTROL PANEL AND OTHER ACCESSORIES SHOWN IN PLANS1L.S.$53,628.00$53,628.00 $0.00 $0.00 
10NEW ELECTRICAL SERVICE TO THE BULDING FROM 70 FT. WITH DISCONECT.1L.S.$5,000.00$5,000.00 $0.00 $0.00 
11SUMP AND SUBMERSIBLE PUMP INSIDE BUILDING, COMPLETE1L.S.$4,135.00$4,135.00 $0.00 $0.00 
123” DIA. HDPE (DR 11) WATERMAIN, BORED OR TRENCHED IN PLACE TO SETTLING BASIN150L.F.$24.00$3,600.00 $0.00 $0.00 
13SETTLING BASIN1L.S.$21,830.00$21,830.00 $0.00 $0.00 
143” DIA. HDPE DR 11 WATERMAIN TRANCHED OR BORED IN PLACE200L.F.$24.00$4,800.00 $0.00 $0.00 
15TRACER WIRE #12 OR 3” DETACTABLE “WATER “ TAPE350L.F.$1.30$455.00 $0.00 $0.00 
16SYSTEM DISINFECTION1L.S.$1,250.00$1,250.00 $0.00 $0.00 
17DRILL 12” HOLE, FURNISH 6” PVC SDR 21 WELL CASING PIPE AND PCC GROUT80L.F.$56.00$4,480.00 $0.00 $0.00 
186” DIA X 20’ OF PVC SLOTTED WELL SCREEN WITH GRAVEL PACK IN 12” HOLE20L.F.$337.00$6,740.00 $0.00 $0.00 
192”X 60’ SCH 120 PVC DROP PIPE80L.F.$5.00$400.00 $0.00 $0.00 
205 HP 3PH SUBMERSIBLE VARIABLE SPEED PUMP RATED TO PROVIDE 65 GPM AT 70 PSI AT SURFACE. INCLUDING 3PH WIRING TO THE VFD TO TREATMENT BUILDING1L.S.$5,374.00$5,374.00 $0.00 $0.00 
21PITLESS ADAPTER UNIT1Each$5,200.00$5,200.00 $0.00 $0.00 
22STATIC WATER PRESSURE LINE AND GUAGE1L.S.$500.00$500.00 $0.00 $0.00 
23INSTALL WELL BELOW-OFF ASSEMBLY & PVC CL 160 WATER LINE FROM WELL TO BUILDING1L.S.$3,725.00$3,725.00 $0.00 $0.00 
24DEVELOP WELL AND TEST PLUMBING1L.S.$6,500.00$6,500.00 $0.00 $0.00 
25DISINFECTION AND CHEMICAL ANALYSIS1L.S.$1,200.00$1,200.00 $0.00 $0.00 
26GRADE AREA AROUND WELL HEAD AS SHOWN AND SEED1L.S.$875.00$875.00 $0.00 $0.00 
27DRILL 12” HOLE AND 6” PVC SDR 21 WELL CASING AND GROUT FOR ADDITONAL DEPTH1L.F.$54.00$54.00 $0.00 $0.00 
28REMOVE PUMP & PLUG EXISTING WELL1L.S.$2,875.00$2,875.00 $0.00 $0.00 
29DEMOLISH APP. 28’X28’ EXSTNG TREAT. BLDNG INC. ASBESTOS ABTMNT, REMOVE PRESSURE TANKS, MIXING TANKS, INTERNAL PIPING ETC. HAUL AND DISPOSE OFF SITE1L.S.$16,800.00$16,800.00 $0.00 $0.00 
30DEMOLISH 28’X24’X6’ DEEP CONCRETE STORAGE TANK AND 145’ LONG ADJUCENT FENCING, HAUL AND DISPOSE OFF SITE1L.S.$11,600.00$11,600.00 $0.00 $0.00 
31SEED ALL DISTURBED AREAS1L.S.$4,300.00$4,300.00 $0.00 $0.00 
32INSTALL A NEW 6’ HIGH COMMERCIAL GRADE CHAIN LINK FENCE155L.F.$23.00$3,565.00 $0.00 $0.00 
      $432,691.00  $0.00  $0.00 
 



 