IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake Macbride State Park | Date: 11/15/2018 | Project No. |
| Pavement Repair | County: | JOHNSON | Time: 11:00 a.m. | 17-06-52-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $345,000.00 | Contractor: | Hansen Asphalt | L L Pelling Company Inc | Fahrner Asphalt Sealers LLC | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | PO Box 1668 | 1425 W Penn St Box 230 | 7680 Commerce Park Section C | ||||||||||
| Iowa City IA 52244 | North Liberty IA 52317 | Dubuque IA 52002 | |||||||||||
| Plan Sets Requested: 1 | Quantities | 319-321-8395 | (319) 626-4600 | 563-556-6231 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2306 - BITUMINOUS FOG SEAL (PAVEMENT) | 2447 | GAL. | $16.00 | $39,152.00 | $6.50 | $15,905.50 | $26.89 | $65,799.83 | ||||
| 2 | 2518 - SAFETY CLOSURE | 3 | Each | $700.00 | $2,100.00 | $100.00 | $300.00 | $1,200.00 | $3,600.00 | ||||
| 3 | 2527 - PAINTED PAVEMENT MARKINGS, HIGH-BUILD WATERBORNE | 740 | STA. | $30.00 | $22,200.00 | $20.30 | $15,022.00 | $15.00 | $11,100.00 | ||||
| 4 | 2528 - TRAFFIC CONTROL | 1 | L.S. | $7,500.00 | $7,500.00 | $46,100.00 | $46,100.00 | $15,000.00 | $15,000.00 | ||||
| 5 | 2529 - PATCHES, FULL-DEPTH REPAIR, 5-IN., HMA | 191 | S.Y. | $150.00 | $28,650.00 | $74.30 | $14,191.30 | $132.00 | $25,212.00 | ||||
| 6 | 2529 - PATCHES, BY COUNT (REPAIR) | 17 | Each | $400.00 | $6,800.00 | $525.50 | $8,933.50 | $220.00 | $3,740.00 | ||||
| 7 | 2533 - MOBILIZATION | 1 | L.S. | $34,000.00 | $34,000.00 | $23,700.00 | $23,700.00 | $56,000.00 | $56,000.00 | ||||
| 8 | 2540 - LONGITUDINAL JOINT REPAIR | 1250 | L.F. | $20.00 | $25,000.00 | $14.75 | $18,437.50 | $13.20 | $16,500.00 | ||||
| 9 | 2543 - TRANSVERSE JOINT REPAIR | 240 | Tons | $350.00 | $84,000.00 | $534.10 | $128,184.00 | $440.00 | $105,600.00 | ||||
| 10 | 2544 - CLEANING AND FILLING CRACKS (PAVEMENT MAINTENANCE) HMA | 7.1 | MI. | $4,500.00 | $31,950.00 | $3,500.00 | $24,850.00 | $6,500.00 | $46,150.00 | ||||
| 11 | 2544 - HOT MIX ASPHALT FOR CRACK FILLING | 1 | Tons | $500.00 | $500.00 | $900.00 | $900.00 | $2,500.00 | $2,500.00 | ||||
| 12 | 2544 - FILLER MATERIAL (MAINTENANCE) | 1420 | GAL. | $6.00 | $8,520.00 | $5.00 | $7,100.00 | $7.00 | $9,940.00 | ||||
| 13 | INLET COVER | 4 | Each | $800.00 | $3,200.00 | $2,420.00 | $9,680.00 | $1,200.00 | $4,800.00 | ||||
| $293,572.00 | $313,303.80 | $365,941.83 | |||||||||||
Hansen Asphalt, Iowa City, IA
12/21/2025