IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Boone Water Works | Date: 3/23/2017 | Project No. |
Create loop and parking | County: | BOONE | Time: 11:00 a.m. | 16-02-08-05 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $116,880.00 | Contractor: | Cerebral Group, LLC | TK Concrete, Inc. | Hymbaugh Construction | |||||||||
Funding Source: 100% Marine Fuel Tax, | 1540 High St, Ste 102 | 1608 Fifield Rd | 821 Quiet Harbor | ||||||||||
Des Moines IA 50309 | Pella IA 50219 | Creston IA 50801 | |||||||||||
Plan Sets Requested: 5 | Quantities | 515-331-7700 | 641-628-4590 | 641-340-0232 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | CLEARING AND GRUBBING | 1 | L.S. | $7,000.00 | $7,000.00 | $7,500.00 | $7,500.00 | $2,000.00 | $2,000.00 | ||||
2 | GRADING | 1 | L.S. | $5,950.00 | $5,950.00 | $20,000.00 | $20,000.00 | $5,000.00 | $5,000.00 | ||||
3 | FULL DEPTH SAW CUT | 14 | L.F. | $8.00 | $112.00 | $10.00 | $140.00 | $50.00 | $700.00 | ||||
4 | SUBGRADE PREPARATION | 1638 | S.Y. | $8.00 | $13,104.00 | $3.00 | $4,914.00 | $10.00 | $16,380.00 | ||||
5 | GRANULAR SUBBASE | 498 | Tons | $35.00 | $17,430.00 | $26.00 | $12,948.00 | $30.00 | $14,940.00 | ||||
6 | 6-INCH REINFORCED PCC PAVEMENT | 1494 | S.Y. | $39.00 | $58,266.00 | $36.00 | $53,784.00 | $50.00 | $74,700.00 | ||||
7 | GRAVEL CONNECTION TO EXISTING BUILDING ACCESS | 6.5 | Tons | $150.00 | $975.00 | $40.00 | $260.00 | $20.00 | $130.00 | ||||
8 | 8-INCH FILTER SOCK | 221 | L.F. | $3.00 | $663.00 | $5.00 | $1,105.00 | $10.00 | $2,210.00 | ||||
9 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $3,500.00 | $3,500.00 | $5,000.00 | $5,000.00 | $1,000.00 | $1,000.00 | ||||
10 | PARKING SPACE STRIPING, HANDICAP MARKINGS, HC SIGNAGE AND ROAD SIGNAGE | 1 | L.S. | $845.00 | $845.00 | $2,000.00 | $2,000.00 | $1,000.00 | $1,000.00 | ||||
11 | NPDES GENERAL PERMIT #2 & SWPPP | 1 | L.S. | $1,000.00 | $1,000.00 | $5,000.00 | $5,000.00 | $2,000.00 | $2,000.00 | ||||
12 | CONSTRUCTION SURVEY STAKING | 1 | L.S. | $2,500.00 | $2,500.00 | $3,500.00 | $3,500.00 | $1,000.00 | $1,000.00 | ||||
13 | MOBILIZATION | 1 | L.S. | $2,500.00 | $2,500.00 | $10,000.00 | $10,000.00 | $3,000.00 | $3,000.00 | ||||
$113,845.00 | $126,151.00 | $124,060.00 | |||||||||||
Alternate | |||||||||||||
14 | SUBGRADE PREPARATION FOR PEDESTRIAN WALKWAY | 174 | S.Y. | $8.00 | $1,392.00 | $3.00 | $522.00 | $20.00 | $3,480.00 | ||||
Alternate | |||||||||||||
15 | GRANULAR SUBBASE FOR PEDESTRIAN WALKWAY | 35 | Tons | $35.00 | $1,225.00 | $30.00 | $1,050.00 | $20.00 | $700.00 | ||||
Alternate | |||||||||||||
16 | 5-INCH REINFORCED PCC PAVEMENT FOR PEDESTRIAN WALKWAY | 180 | S.Y. | $35.00 | $6,300.00 | $36.00 | $6,480.00 | $40.00 | $7,200.00 | ||||
$122,762.00 | $134,203.00 | $135,440.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $116,880.00 | Contractor: | Jensen Builders LTD | Weidner Construction, Inc. | Kingston Services PC | |||||||||
Funding Source: 100% Marine Fuel Tax, | 2097 NE 60th Ave | 2607 255th St | 1444 Illinois St | ||||||||||
Des Moines IA 50313 | Marshalltown IA 50158 | Des Moines IA 50314 | |||||||||||
Plan Sets Requested: 5 | Quantities | 515-292-5000 | 641-752-6665 | 515-447-3847 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | CLEARING AND GRUBBING | 1 | L.S. | $9,200.00 | $9,200.00 | $700.00 | $700.00 | $7,400.00 | $7,400.00 | ||||
2 | GRADING | 1 | L.S. | $17,150.00 | $17,150.00 | $16,000.00 | $16,000.00 | $16,880.00 | $16,880.00 | ||||
3 | FULL DEPTH SAW CUT | 14 | L.F. | $11.50 | $161.00 | $21.43 | $300.02 | $20.00 | $280.00 | ||||
4 | SUBGRADE PREPARATION | 1638 | S.Y. | $2.30 | $3,767.40 | $1.53 | $2,506.14 | $2.50 | $4,095.00 | ||||
5 | GRANULAR SUBBASE | 498 | Tons | $33.40 | $16,633.20 | $20.00 | $9,960.00 | $31.00 | $15,438.00 | ||||
6 | 6-INCH REINFORCED PCC PAVEMENT | 1494 | S.Y. | $40.45 | $60,432.30 | $60.69 | $90,670.86 | $47.25 | $70,591.50 | ||||
7 | GRAVEL CONNECTION TO EXISTING BUILDING ACCESS | 6.5 | Tons | $32.00 | $208.00 | $25.38 | $164.97 | $54.00 | $351.00 | ||||
8 | 8-INCH FILTER SOCK | 221 | L.F. | $5.75 | $1,270.75 | $5.43 | $1,200.03 | $3.00 | $663.00 | ||||
9 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $5,200.00 | $5,200.00 | $1,500.00 | $1,500.00 | $2,685.00 | $2,685.00 | ||||
10 | PARKING SPACE STRIPING, HANDICAP MARKINGS, HC SIGNAGE AND ROAD SIGNAGE | 1 | L.S. | $1,660.00 | $1,660.00 | $1,500.00 | $1,500.00 | $1,295.00 | $1,295.00 | ||||
11 | NPDES GENERAL PERMIT #2 & SWPPP | 1 | L.S. | $5,000.00 | $5,000.00 | $200.00 | $200.00 | $2,500.00 | $2,500.00 | ||||
12 | CONSTRUCTION SURVEY STAKING | 1 | L.S. | $3,100.00 | $3,100.00 | $2,500.00 | $2,500.00 | $3,875.00 | $3,875.00 | ||||
13 | MOBILIZATION | 1 | L.S. | $10,150.00 | $10,150.00 | $1,500.00 | $1,500.00 | $10,865.00 | $10,865.00 | ||||
Alternate | |||||||||||||
14 | SUBGRADE PREPARATION FOR PEDESTRIAN WALKWAY | 174 | S.Y. | $5.75 | $1,000.50 | $14.37 | $2,500.38 | $5.00 | $870.00 | ||||
Alternate | |||||||||||||
15 | GRANULAR SUBBASE FOR PEDESTRIAN WALKWAY | 35 | Tons | $35.00 | $1,225.00 | $25.00 | $875.00 | $35.00 | $1,225.00 | ||||
Alternate | |||||||||||||
16 | 5-INCH REINFORCED PCC PAVEMENT FOR PEDESTRIAN WALKWAY | 180 | S.Y. | $51.50 | $9,270.00 | $76.50 | $13,770.00 | $47.25 | $8,505.00 | ||||
$145,428.15 | $145,847.40 | $147,518.50 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $116,880.00 | Contractor: | Cameron Mitchell Inc | Absolute Concrete Construction Inc | Majors Concrete Co. | |||||||||
Funding Source: 100% Marine Fuel Tax, | 1588 NE 58th Ave | PO Box 148 | 205 S Story St | ||||||||||
Des Moines IA 50313 | Slater IA 50244 | Boone IA 50036 | |||||||||||
Plan Sets Requested: 5 | Quantities | 515-264-8666 | 515-228-3030 | 515-230-0338 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | CLEARING AND GRUBBING | 1 | L.S. | $8,000.00 | $8,000.00 | $11,275.00 | $11,275.00 | $3,408.00 | $3,408.00 | ||||
2 | GRADING | 1 | L.S. | $16,400.00 | $16,400.00 | $14,000.00 | $14,000.00 | $23,784.00 | $23,784.00 | ||||
3 | FULL DEPTH SAW CUT | 14 | L.F. | $11.00 | $154.00 | $6.00 | $84.00 | $21.43 | $300.02 | ||||
4 | SUBGRADE PREPARATION | 1638 | S.Y. | $2.20 | $3,603.60 | $2.70 | $4,422.60 | $4.34 | $7,108.92 | ||||
5 | GRANULAR SUBBASE | 498 | Tons | $32.00 | $15,936.00 | $36.50 | $18,177.00 | $40.03 | $19,934.94 | ||||
6 | 6-INCH REINFORCED PCC PAVEMENT | 1494 | S.Y. | $44.00 | $65,736.00 | $43.50 | $64,989.00 | $49.46 | $73,893.24 | ||||
7 | GRAVEL CONNECTION TO EXISTING BUILDING ACCESS | 6.5 | Tons | $30.00 | $195.00 | $61.50 | $399.75 | $142.56 | $926.64 | ||||
8 | 8-INCH FILTER SOCK | 221 | L.F. | $5.00 | $1,105.00 | $7.70 | $1,701.70 | $5.25 | $1,160.25 | ||||
9 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $4,950.00 | $4,950.00 | $5,125.00 | $5,125.00 | $4,725.00 | $4,725.00 | ||||
10 | PARKING SPACE STRIPING, HANDICAP MARKINGS, HC SIGNAGE AND ROAD SIGNAGE | 1 | L.S. | $4,235.00 | $4,235.00 | $1,476.00 | $1,476.00 | $1,512.00 | $1,512.00 | ||||
11 | NPDES GENERAL PERMIT #2 & SWPPP | 1 | L.S. | $4,785.00 | $4,785.00 | $4,100.00 | $4,100.00 | $4,567.50 | $4,567.50 | ||||
12 | CONSTRUCTION SURVEY STAKING | 1 | L.S. | $3,000.00 | $3,000.00 | $2,788.00 | $2,788.00 | $3,549.00 | $3,549.00 | ||||
13 | MOBILIZATION | 1 | L.S. | $10,000.00 | $10,000.00 | $8,500.00 | $8,500.00 | $7,815.47 | $7,815.47 | ||||
Alternate | |||||||||||||
14 | SUBGRADE PREPARATION FOR PEDESTRIAN WALKWAY | 174 | S.Y. | $9.60 | $1,670.40 | $1.90 | $330.60 | $13.61 | $2,368.14 | ||||
Alternate | |||||||||||||
15 | GRANULAR SUBBASE FOR PEDESTRIAN WALKWAY | 35 | Tons | $33.00 | $1,155.00 | $47.00 | $1,645.00 | $27.28 | $954.80 | ||||
Alternate | |||||||||||||
16 | 5-INCH REINFORCED PCC PAVEMENT FOR PEDESTRIAN WALKWAY | 180 | S.Y. | $40.00 | $7,200.00 | $58.50 | $10,530.00 | $57.58 | $10,364.40 | ||||
$148,125.00 | $149,543.65 | $166,372.32 | |||||||||||
10 | 11 | 12 | |||||||||||
Estimated Cost: $116,880.00 | Contractor: | Con-Struct, Inc. | JAS Construction LLC | Speck USA | |||||||||
Funding Source: 100% Marine Fuel Tax, | 305 S Dayton Ave | 208 3rd St SW | PO Box 21009 | ||||||||||
Ames IA 50010 | Altoona IA 50009 | Des Moines IA 50321 | |||||||||||
Plan Sets Requested: 5 | Quantities | 515-232-6443 | 515-339-1200 | 515-285-4649 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | CLEARING AND GRUBBING | 1 | L.S. | $25,698.00 | $25,698.00 | $20,400.00 | $20,400.00 | $17,000.00 | $17,000.00 | ||||
2 | GRADING | 1 | L.S. | $24,352.00 | $24,352.00 | $14,720.00 | $14,720.00 | $37,000.00 | $37,000.00 | ||||
3 | FULL DEPTH SAW CUT | 14 | L.F. | $12.60 | $176.40 | $5.00 | $70.00 | $1.00 | $14.00 | ||||
4 | SUBGRADE PREPARATION | 1638 | S.Y. | $1.25 | $2,047.50 | $3.00 | $4,914.00 | $5.00 | $8,190.00 | ||||
5 | GRANULAR SUBBASE | 498 | Tons | $26.10 | $12,997.80 | $27.00 | $13,446.00 | $35.00 | $17,430.00 | ||||
6 | 6-INCH REINFORCED PCC PAVEMENT | 1494 | S.Y. | $44.20 | $66,034.80 | $52.00 | $77,688.00 | $40.00 | $59,760.00 | ||||
7 | GRAVEL CONNECTION TO EXISTING BUILDING ACCESS | 6.5 | Tons | $37.30 | $242.45 | $30.00 | $195.00 | $35.00 | $227.50 | ||||
8 | 8-INCH FILTER SOCK | 221 | L.F. | $5.10 | $1,127.10 | $6.78 | $1,498.38 | $5.00 | $1,105.00 | ||||
9 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $4,579.00 | $4,579.00 | $10,000.00 | $10,000.00 | $4,500.00 | $4,500.00 | ||||
10 | PARKING SPACE STRIPING, HANDICAP MARKINGS, HC SIGNAGE AND ROAD SIGNAGE | 1 | L.S. | $3,918.00 | $3,918.00 | $4,250.00 | $4,250.00 | $1,500.00 | $1,500.00 | ||||
11 | NPDES GENERAL PERMIT #2 & SWPPP | 1 | L.S. | $4,427.00 | $4,427.00 | $6,250.00 | $6,250.00 | $4,350.00 | $4,350.00 | ||||
12 | CONSTRUCTION SURVEY STAKING | 1 | L.S. | $2,768.00 | $2,768.00 | $2,000.00 | $2,000.00 | $5,700.00 | $5,700.00 | ||||
13 | MOBILIZATION | 1 | L.S. | $7,135.00 | $7,135.00 | $4,500.00 | $4,500.00 | $7,500.00 | $7,500.00 | ||||
Alternate | |||||||||||||
14 | SUBGRADE PREPARATION FOR PEDESTRIAN WALKWAY | 174 | S.Y. | $1.10 | $191.40 | $3.00 | $522.00 | $5.00 | $870.00 | ||||
Alternate | |||||||||||||
15 | GRANULAR SUBBASE FOR PEDESTRIAN WALKWAY | 35 | Tons | $37.00 | $1,295.00 | $27.00 | $945.00 | $35.00 | $1,225.00 | ||||
Alternate | |||||||||||||
16 | 5-INCH REINFORCED PCC PAVEMENT FOR PEDESTRIAN WALKWAY | 180 | S.Y. | $60.40 | $10,872.00 | $48.00 | $8,640.00 | $70.00 | $12,600.00 | ||||
$167,861.45 | $170,038.38 | $178,971.50 | |||||||||||
13 | 14 | 15 | |||||||||||
Estimated Cost: $116,880.00 | Contractor: | Godbersen-Smith Construction Co., Inc. | Howrey Construction | ||||||||||
Funding Source: 100% Marine Fuel Tax, | 5784 State Highway 175 PO Box 33 | 316 Austin St | |||||||||||
Ida Grove IA 51445 | Rockwell City IA 50579 | ||||||||||||
Plan Sets Requested: 5 | Quantities | 712-364-3388 | 712-297-8182 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | CLEARING AND GRUBBING | 1 | L.S. | $10,000.00 | $10,000.00 | $11,550.00 | $11,550.00 | $0.00 | |||||
2 | GRADING | 1 | L.S. | $18,000.00 | $18,000.00 | $29,500.00 | $29,500.00 | $0.00 | |||||
3 | FULL DEPTH SAW CUT | 14 | L.F. | $12.00 | $168.00 | $16.00 | $224.00 | $0.00 | |||||
4 | SUBGRADE PREPARATION | 1638 | S.Y. | $4.00 | $6,552.00 | $6.00 | $9,828.00 | $0.00 | |||||
5 | GRANULAR SUBBASE | 498 | Tons | $40.00 | $19,920.00 | $40.00 | $19,920.00 | $0.00 | |||||
6 | 6-INCH REINFORCED PCC PAVEMENT | 1494 | S.Y. | $54.00 | $80,676.00 | $62.50 | $93,375.00 | $0.00 | |||||
7 | GRAVEL CONNECTION TO EXISTING BUILDING ACCESS | 6.5 | Tons | $45.00 | $292.50 | $40.00 | $260.00 | $0.00 | |||||
8 | 8-INCH FILTER SOCK | 221 | L.F. | $5.00 | $1,105.00 | $5.25 | $1,160.25 | $0.00 | |||||
9 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $2,000.00 | $2,000.00 | $4,725.00 | $4,725.00 | $0.00 | |||||
10 | PARKING SPACE STRIPING, HANDICAP MARKINGS, HC SIGNAGE AND ROAD SIGNAGE | 1 | L.S. | $4,200.00 | $4,200.00 | $4,050.00 | $4,050.00 | $0.00 | |||||
11 | NPDES GENERAL PERMIT #2 & SWPPP | 1 | L.S. | $1,500.00 | $1,500.00 | $4,570.00 | $4,570.00 | $0.00 | |||||
12 | CONSTRUCTION SURVEY STAKING | 1 | L.S. | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $0.00 | |||||
13 | MOBILIZATION | 1 | L.S. | $28,000.00 | $28,000.00 | $10,500.00 | $10,500.00 | $0.00 | |||||
Alternate | |||||||||||||
14 | SUBGRADE PREPARATION FOR PEDESTRIAN WALKWAY | 174 | S.Y. | $5.00 | $870.00 | $8.00 | $1,392.00 | $0.00 | |||||
Alternate | |||||||||||||
15 | GRANULAR SUBBASE FOR PEDESTRIAN WALKWAY | 35 | Tons | $40.00 | $1,400.00 | $40.00 | $1,400.00 | $0.00 | |||||
Alternate | |||||||||||||
16 | 5-INCH REINFORCED PCC PAVEMENT FOR PEDESTRIAN WALKWAY | 180 | S.Y. | $54.00 | $9,720.00 | $75.00 | $13,500.00 | $0.00 | |||||
$188,403.50 | $209,954.25 | $0.00 | |||||||||||
Weidner Construction, Inc., Marshalltown, IA
Con-Struct, Inc., Ames, IA
TK Concrete, Inc., Pella, IA
Jensen Builders LTD, Des Moines, IA
Cameron Mitchell Inc, Des Moines, IA
Majors Concrete Co., Boone, IA
Godbersen-Smith Construction Co., Inc., Ida Grove, IA
5/8/2024