| Bids For: | Location: | Marble Beach State Recreation Area | Date: 3/24/2016 | Project No. |
| Marble Beach Fish Cleaning Station Replacement | County: | DICKINSON | Time: 3:00 p.m. | 16-01-30-9 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $47,500.00 | Contractor: | Christensen Construction & Design Co., Inc. | Midstates Builders, Inc. | ||||||||||
| Funding Source: 100% Marine Fuel Tax, | 821 South 28th St | 520 S Grand Ave PO Box 1357 | |||||||||||
| Estherville IA 51334 | Spencer IA 51301 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 712-362-7755 | 712-262-2227 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $892.00 | $892.00 | $4,465.00 | $4,465.00 | $0.00 | |||||
| 2 | Removals | 1 | L.S. | $420.00 | $420.00 | $3,300.00 | $3,300.00 | $0.00 | |||||
| 3 | Sewer Upgrade & Relocation | 1 | L.S. | $4,830.00 | $4,830.00 | $3,675.00 | $3,675.00 | $0.00 | |||||
| 4 | Water Service Relocation | 1 | L.S. | $978.00 | $978.00 | $700.00 | $700.00 | $0.00 | |||||
| 5 | Electrical Upgrade & Relocation | 1 | L.S. | $3,450.00 | $3,450.00 | $1,000.00 | $1,000.00 | $0.00 | |||||
| 6 | 6" Thick Reinforced PCC Slab | 48 | S.F. | $28.75 | $1,380.00 | $72.00 | $3,456.00 | $0.00 | |||||
| 7 | Barracuda I Fish Cleaning Station | 1 | L.S. | $42,401.00 | $42,401.00 | $44,000.00 | $44,000.00 | $0.00 | |||||
| 8 | Fish Cleaning Station Utility Connections & Testing | 1 | L.S. | $282.00 | $282.00 | $1,243.00 | $1,243.00 | $0.00 | |||||
| $54,633.00 | $61,839.00 | $0.00 | |||||||||||
12/23/2025