IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Ledges State Park | Date: 7/20/2017 | Project No. |
| River Access/Parking, DSM River | County: | BOONE | Time: 11:00 a.m. | 16-02-08-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $242,652.00 | Contractor: | TK Concrete, Inc. | Kingston Services PC | Caliber Concrete LLC | |||||||||
| Funding Source: 100% Marine Fuel Tax -Minors, | 1608 Fifield Rd | 1444 Illinois St | 309 Audubon St | ||||||||||
| Pella IA 50219 | Des Moines IA 50314 | Adair IA 50002 | |||||||||||
| Plan Sets Requested: 3 | Quantities | 641-628-4590 | 515-681-7215 | 515-979-2004 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | CLEARING AND GRUBBING | 1 | L.S. | $2,500.00 | $2,500.00 | $3,800.00 | $3,800.00 | $1,500.00 | $1,500.00 | ||||
| 2 | GRADING | 1 | L.S. | $12,500.00 | $12,500.00 | $12,465.00 | $12,465.00 | $19,000.00 | $19,000.00 | ||||
| 3 | FULL DEPTH SAW CUT | 75 | L.F. | $5.00 | $375.00 | $4.00 | $300.00 | $4.00 | $300.00 | ||||
| 4 | 12-INCH RCP CLASS III | 40 | L.F. | $55.00 | $2,200.00 | $56.00 | $2,240.00 | $37.50 | $1,500.00 | ||||
| 5 | 12-INCH RCP CLASS III FES W/APRON GUARDS | 2 | Each | $2,750.00 | $5,500.00 | $1,485.00 | $2,970.00 | $750.00 | $1,500.00 | ||||
| 6 | SUBGRADE PREPARATION | 3370 | S.Y. | $2.00 | $6,740.00 | $2.00 | $6,740.00 | $2.70 | $9,099.00 | ||||
| 7 | GRANULAR SUBBASE | 1010 | Tons | $29.00 | $29,290.00 | $22.50 | $22,725.00 | $31.00 | $31,310.00 | ||||
| 8 | 6-INCH NON-REINFORCED PCC PAVEMENT | 1960 | S.Y. | $32.50 | $63,700.00 | $36.00 | $70,560.00 | $39.00 | $76,440.00 | ||||
| 9 | 6-INCH REINFORCED PCC PAVEMENT | 1128 | S.Y. | $36.00 | $40,608.00 | $41.00 | $46,248.00 | $43.00 | $48,504.00 | ||||
| 10 | 6-INCH STANDARD PCC CURB | 20 | L.F. | $40.00 | $800.00 | $21.00 | $420.00 | $20.00 | $400.00 | ||||
| 11 | CLASS 'D' RIPRAP | 605 | Tons | $49.00 | $29,645.00 | $54.00 | $32,670.00 | $50.00 | $30,250.00 | ||||
| 12 | MACADAM STONE | 22 | Tons | $40.00 | $880.00 | $42.00 | $924.00 | $40.00 | $880.00 | ||||
| 13 | CLASS 'A' CRUSHED STONE | 38 | Tons | $30.00 | $1,140.00 | $38.00 | $1,444.00 | $40.00 | $1,520.00 | ||||
| 14 | GROOVED REINFORCED PCC BOAT RAMP | 106.7 | S.Y. | $50.00 | $5,335.00 | $48.00 | $5,121.60 | $57.00 | $6,081.90 | ||||
| 15 | 8-INCH FILTER SOCK | 135 | L.F. | $8.00 | $1,080.00 | $2.50 | $337.50 | $4.00 | $540.00 | ||||
| 16 | PARKING SPACE STRIPING, HANDICAP MARKINGS & HC SIGN | 1 | L.S. | $8,000.00 | $8,000.00 | $3,600.00 | $3,600.00 | $2,500.00 | $2,500.00 | ||||
| 17 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $2,000.00 | $2,000.00 | $4,200.00 | $4,200.00 | $1,000.00 | $1,000.00 | ||||
| 18 | NPDES GENERAL PERMIT #2 & SWPPP | 1 | L.S. | $6,000.00 | $6,000.00 | $3,200.00 | $3,200.00 | $2,500.00 | $2,500.00 | ||||
| 19 | CONSTRUCTION SURVEY STAKING | 1 | L.S. | $5,500.00 | $5,500.00 | $3,600.00 | $3,600.00 | $4,000.00 | $4,000.00 | ||||
| 20 | MOBILIZATION | 1 | L.S. | $10,000.00 | $10,000.00 | $17,464.90 | $17,464.90 | $4,000.00 | $4,000.00 | ||||
| $233,793.00 | $241,030.00 | $242,824.90 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $242,652.00 | Contractor: | Absolute Concrete Construction Inc | Con-Struct, Inc. | Berkey Home Builders dba Concrete Professionals | |||||||||
| Funding Source: 100% Marine Fuel Tax -Minors, | 505 1st Ave | 305 S Dayton Ave | 8538 NE 54th Ave | ||||||||||
| Slater IA 50244 | Ames IA 50010 | Altoona IA 50009 | |||||||||||
| Plan Sets Requested: 3 | Quantities | 515-228-3030 | 515-232-6443 | 515-967-3136 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | CLEARING AND GRUBBING | 1 | L.S. | $1,500.00 | $1,500.00 | $2,530.00 | $2,530.00 | $5,325.00 | $5,325.00 | ||||
| 2 | GRADING | 1 | L.S. | $8,500.00 | $8,500.00 | $18,700.00 | $18,700.00 | $23,980.00 | $23,980.00 | ||||
| 3 | FULL DEPTH SAW CUT | 75 | L.F. | $7.00 | $525.00 | $8.00 | $600.00 | $6.50 | $487.50 | ||||
| 4 | 12-INCH RCP CLASS III | 40 | L.F. | $46.50 | $1,860.00 | $64.00 | $2,560.00 | $101.00 | $4,040.00 | ||||
| 5 | 12-INCH RCP CLASS III FES W/APRON GUARDS | 2 | Each | $1,795.00 | $3,590.00 | $1,710.00 | $3,420.00 | $2,205.00 | $4,410.00 | ||||
| 6 | SUBGRADE PREPARATION | 3370 | S.Y. | $1.80 | $6,066.00 | $1.45 | $4,886.50 | $3.70 | $12,469.00 | ||||
| 7 | GRANULAR SUBBASE | 1010 | Tons | $28.80 | $29,088.00 | $34.00 | $34,340.00 | $34.75 | $35,097.50 | ||||
| 8 | 6-INCH NON-REINFORCED PCC PAVEMENT | 1960 | S.Y. | $42.00 | $82,320.00 | $42.00 | $82,320.00 | $40.30 | $78,988.00 | ||||
| 9 | 6-INCH REINFORCED PCC PAVEMENT | 1128 | S.Y. | $51.50 | $58,092.00 | $51.00 | $57,528.00 | $55.90 | $63,055.20 | ||||
| 10 | 6-INCH STANDARD PCC CURB | 20 | L.F. | $48.50 | $970.00 | $40.00 | $800.00 | $92.00 | $1,840.00 | ||||
| 11 | CLASS 'D' RIPRAP | 605 | Tons | $58.55 | $35,422.75 | $65.00 | $39,325.00 | $78.00 | $47,190.00 | ||||
| 12 | MACADAM STONE | 22 | Tons | $45.50 | $1,001.00 | $58.00 | $1,276.00 | $98.00 | $2,156.00 | ||||
| 13 | CLASS 'A' CRUSHED STONE | 38 | Tons | $26.80 | $1,018.40 | $40.00 | $1,520.00 | $64.70 | $2,458.60 | ||||
| 14 | GROOVED REINFORCED PCC BOAT RAMP | 106.7 | S.Y. | $55.50 | $5,921.85 | $85.00 | $9,069.50 | $87.50 | $9,336.25 | ||||
| 15 | 8-INCH FILTER SOCK | 135 | L.F. | $6.50 | $877.50 | $7.00 | $945.00 | $7.00 | $945.00 | ||||
| 16 | PARKING SPACE STRIPING, HANDICAP MARKINGS & HC SIGN | 1 | L.S. | $9,500.00 | $9,500.00 | $4,385.00 | $4,385.00 | $8,210.00 | $8,210.00 | ||||
| 17 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $1,450.00 | $1,450.00 | $10,000.00 | $10,000.00 | $996.00 | $996.00 | ||||
| 18 | NPDES GENERAL PERMIT #2 & SWPPP | 1 | L.S. | $4,000.00 | $4,000.00 | $4,200.00 | $4,200.00 | $5,860.00 | $5,860.00 | ||||
| 19 | CONSTRUCTION SURVEY STAKING | 1 | L.S. | $5,000.00 | $5,000.00 | $3,850.00 | $3,850.00 | $1,410.00 | $1,410.00 | ||||
| 20 | MOBILIZATION | 1 | L.S. | $16,500.00 | $16,500.00 | $14,650.00 | $14,650.00 | $10,430.00 | $10,430.00 | ||||
| $273,202.50 | $296,905.00 | $318,684.05 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $242,652.00 | Contractor: | Jensen Builders LTD | |||||||||||
| Funding Source: 100% Marine Fuel Tax -Minors, | 2097 NE 60th Ave | ||||||||||||
| Des Moines IA 50313 | |||||||||||||
| Plan Sets Requested: 3 | Quantities | 515-292-5000 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | CLEARING AND GRUBBING | 1 | L.S. | $3,300.00 | $3,300.00 | $0.00 | $0.00 | ||||||
| 2 | GRADING | 1 | L.S. | $24,700.00 | $24,700.00 | $0.00 | $0.00 | ||||||
| 3 | FULL DEPTH SAW CUT | 75 | L.F. | $6.40 | $480.00 | $0.00 | $0.00 | ||||||
| 4 | 12-INCH RCP CLASS III | 40 | L.F. | $80.00 | $3,200.00 | $0.00 | $0.00 | ||||||
| 5 | 12-INCH RCP CLASS III FES W/APRON GUARDS | 2 | Each | $21.60 | $43.20 | $0.00 | $0.00 | ||||||
| 6 | SUBGRADE PREPARATION | 3370 | S.Y. | $1.85 | $6,234.50 | $0.00 | $0.00 | ||||||
| 7 | GRANULAR SUBBASE | 1010 | Tons | $43.15 | $43,581.50 | $0.00 | $0.00 | ||||||
| 8 | 6-INCH NON-REINFORCED PCC PAVEMENT | 1960 | S.Y. | $48.75 | $95,550.00 | $0.00 | $0.00 | ||||||
| 9 | 6-INCH REINFORCED PCC PAVEMENT | 1128 | S.Y. | $54.50 | $61,476.00 | $0.00 | $0.00 | ||||||
| 10 | 6-INCH STANDARD PCC CURB | 20 | L.F. | $40.00 | $800.00 | $0.00 | $0.00 | ||||||
| 11 | CLASS 'D' RIPRAP | 605 | Tons | $92.50 | $55,962.50 | $0.00 | $0.00 | ||||||
| 12 | MACADAM STONE | 22 | Tons | $74.00 | $1,628.00 | $0.00 | $0.00 | ||||||
| 13 | CLASS 'A' CRUSHED STONE | 38 | Tons | $49.25 | $1,871.50 | $0.00 | $0.00 | ||||||
| 14 | GROOVED REINFORCED PCC BOAT RAMP | 106.7 | S.Y. | $151.00 | $16,111.70 | $0.00 | $0.00 | ||||||
| 15 | 8-INCH FILTER SOCK | 135 | L.F. | $7.40 | $999.00 | $0.00 | $0.00 | ||||||
| 16 | PARKING SPACE STRIPING, HANDICAP MARKINGS & HC SIGN | 1 | L.S. | $8,650.00 | $8,650.00 | $0.00 | $0.00 | ||||||
| 17 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $1,050.00 | $1,050.00 | $0.00 | $0.00 | ||||||
| 18 | NPDES GENERAL PERMIT #2 & SWPPP | 1 | L.S. | $6,165.00 | $6,165.00 | $0.00 | $0.00 | ||||||
| 19 | CONSTRUCTION SURVEY STAKING | 1 | L.S. | $4,200.00 | $4,200.00 | $0.00 | $0.00 | ||||||
| 20 | MOBILIZATION | 1 | L.S. | $26,420.30 | $26,420.30 | $0.00 | $0.00 | ||||||
| $362,423.20 | $0.00 | $0.00 | |||||||||||
Kingston Services PC, Des Moines, IA
4/2/2026