IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Rock Creek State Park | Date: 4/13/2017 | Project No. |
| Boat Ramp Repairs | County: | JASPER | Time: 3:00 p.m. | 16-05-50-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $49,558.00 | Contractor: | Boulder Contracting, LLC | Strand Excavating Inc | ||||||||||
| Funding Source: 68% Marine Fuel Tax -Minors, 32% Federal-Other, | 25789 N Ave | 13895 Hwy 6E | |||||||||||
| Grundy Center IA 50638 | Grinnell IA 50112 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 319-269-8680 | 641-498-7373 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Articulated Concrete Block @ Beach Ramp | 208 | S.F. | $30.00 | $6,240.00 | $23.00 | $4,784.00 | $0.00 | |||||
| 2 | Class "A" Crushed Stone @ Beach Ramp | 16 | Tons | $40.00 | $640.00 | $92.25 | $1,476.00 | $0.00 | |||||
| 3 | Dock Connection Pad @ Beach Ramp | 1 | L.S. | $750.00 | $750.00 | $540.00 | $540.00 | $0.00 | |||||
| 4 | Demolitions @ Beach Ramp | 1 | L.S. | $600.00 | $600.00 | $600.00 | $600.00 | $0.00 | |||||
| 5 | Sidewalk @ Beach Ramp | 23.33 | S.Y. | $60.00 | $1,399.80 | $78.60 | $1,833.738 | $0.00 | |||||
| 6 | Class "E" Riprap @ Beach Ramp | 16 | Tons | $60.00 | $960.00 | $70.00 | $1,120.00 | $0.00 | |||||
| 7 | Articulated Concrete Block @ NW Ramp | 208 | S.F. | $30.00 | $6,240.00 | $23.00 | $4,784.00 | $0.00 | |||||
| 8 | Class "A" Crushed Stone @ NW Ramp | 16 | Tons | $40.00 | $640.00 | $92.25 | $1,476.00 | $0.00 | |||||
| 9 | Demolitions @ NW Ramp | 1 | L.S. | $1,800.00 | $1,800.00 | $2,350.00 | $2,350.00 | $0.00 | |||||
| 10 | Sidewalk @ NW Ramp | 56.67 | S.Y. | $60.00 | $3,400.20 | $73.90 | $4,187.913 | $0.00 | |||||
| 11 | Class "E" Riprap @ NW Ramp | 16 | Tons | $60.00 | $960.00 | $70.00 | $1,120.00 | $0.00 | |||||
| 12 | Ramp Patches @ NW Ramp | 1 | L.S. | $1,500.00 | $1,500.00 | $1,825.00 | $1,825.00 | $0.00 | |||||
| 13 | Articulated Concrete Block @ Campground Ramp | 112 | S.F. | $35.00 | $3,920.00 | $30.45 | $3,410.40 | $0.00 | |||||
| 14 | Class "A" Crushed Stone @ Campground Ramp | 16 | Tons | $40.00 | $640.00 | $92.25 | $1,476.00 | $0.00 | |||||
| 15 | Dock Connection Pad @ Campground Ramp | 1 | L.S. | $750.00 | $750.00 | $540.00 | $540.00 | $0.00 | |||||
| 16 | Demolitions @ Campground Ramp | 1 | L.S. | $800.00 | $800.00 | $950.00 | $950.00 | $0.00 | |||||
| 17 | Sidewalk @ Campground Ramp | 32.22 | S.Y. | $60.00 | $1,933.20 | $80.40 | $2,590.488 | $0.00 | |||||
| 18 | Class "E" Riprap @ Campground Ramp | 16 | Tons | $60.00 | $960.00 | $70.00 | $1,120.00 | $0.00 | |||||
| 19 | Articulated Concrete Block @ South Ramp | 128 | S.F. | $32.00 | $4,096.00 | $23.00 | $2,944.00 | $0.00 | |||||
| 20 | Class "A" Crushed Stone @ South Ramp | 16 | Tons | $40.00 | $640.00 | $92.25 | $1,476.00 | $0.00 | |||||
| 21 | Class "E" Riprap @ South Ramp | 16 | Tons | $60.00 | $960.00 | $70.00 | $1,120.00 | $0.00 | |||||
| 22 | Mobilization & Site Restoration | 1 | L.S. | $5,500.00 | $5,500.00 | $5,500.00 | $5,500.00 | $0.00 | |||||
| $45,329.20 | $47,223.539 | $0.00 | |||||||||||