| Bids For: | Location: | Spirit Lake Hatchery | Date: 12/17/2015 | Project No. |
| Fish Rearing Water Pipe Replacement | County: | DICKINSON | Time: 3:00 p.m. | 16-01-30-07 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $40,000.00 | Contractor: | Beemer Companies | Christensen Construction & Design Company | ||||||||||
| Funding Source: 75% Federal-DJ, 25% REAP Land Management, | 1988 135th st. | 821 S 28th St | |||||||||||
| Fairmont MN 56031 | Estherville IA 51334 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 507-235-6779 | 712-362-7755 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Water System Replacement | 1 | L.S. | $41,500.00 | $41,500.00 | $45,000.00 | $45,000.00 | $0.00 | |||||
| $41,500.00 | $45,000.00 | $0.00 | |||||||||||
| Alternate | |||||||||||||
| 2 | Cold Water Pipe Insulation | 1 | L.S. | $5,620.00 | $5,620.00 | $4,500.00 | $4,500.00 | $0.00 | |||||
| $47,120.00 | $49,500.00 | $0.00 | |||||||||||
Beemer Companies, Fairmont, MN