IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Geode State Park | Date: 12/22/2016 | Project No. |
Sediment Ponds | County: | HENRY | Time: 11:00 a.m. | 16-06-44-03 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $389,000.00 | Contractor: | Kloubec Earthworks | Hammes Bulldozing Inc. | Meller Excavating & Asphalt | |||||||||
Funding Source: 50% Lake Restoration, 50% Federal-EPA, | 3352 Southridge Dr. | 16520 Hwy 92 | 3321 190th St | ||||||||||
Amana IA 52203 | Sigourney IA 52591 | Ft Madison IA 52627 | |||||||||||
Plan Sets Requested: 15 | Quantities | 319-241-8990 | 641-660-1610 | (319) 372-7410 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $14,400.00 | $14,400.00 | $15,000.00 | $15,000.00 | $5,800.00 | $5,800.00 | ||||
2 | 12" Dia. Smooth Steel Pipe | 445 | L.F. | $16.67 | $7,418.15 | $17.00 | $7,565.00 | $17.96 | $7,992.20 | ||||
3 | 18" Dia. Smooth Steel Pipe | 340 | L.F. | $34.65 | $11,781.00 | $35.00 | $11,900.00 | $35.18 | $11,961.20 | ||||
4 | 36" Dia. Smooth Steel Pipe Riser | 20 | L.F. | $99.00 | $1,980.00 | $100.00 | $2,000.00 | $152.59 | $3,051.80 | ||||
5 | Trash Rack for Canopy Inlet (12") | 2 | Each | $1,290.00 | $2,580.00 | $600.00 | $1,200.00 | $925.85 | $1,851.70 | ||||
6 | Trash Rack for Vertical Riser (36") | 2 | Each | $1,650.00 | $3,300.00 | $1,000.00 | $2,000.00 | $1,285.85 | $2,571.70 | ||||
7 | Fine Drainfill | 400 | Tons | $22.09 | $8,836.00 | $23.00 | $9,200.00 | $17.75 | $7,100.00 | ||||
8 | Earthwork / Fill / Grade | 36000 | C.Y. | $1.17 | $42,120.00 | $1.45 | $52,200.00 | $2.05 | $73,800.00 | ||||
9 | Core Trench | 2870 | C.Y. | $1.38 | $3,960.60 | $1.55 | $4,448.50 | $9.00 | $25,830.00 | ||||
10 | Seed & Mulch | 11.6 | Acres | $1,551.00 | $17,991.60 | $1,500.00 | $17,400.00 | $416.00 | $4,825.60 | ||||
11 | Clearing & Grubbing | 16.2 | Acres | $2,000.00 | $32,400.00 | $1,250.00 | $20,250.00 | $2,800.00 | $45,360.00 | ||||
12 | 6" Stripping and Respread | 9400 | C.Y. | $1.90 | $17,860.00 | $1.05 | $9,870.00 | $1.45 | $13,630.00 | ||||
13 | Class D Rip Rap | 1200 | Tons | $26.27 | $31,524.00 | $38.00 | $45,600.00 | $27.25 | $32,700.00 | ||||
14 | Field Fence | 1220 | L.F. | $4.80 | $5,856.00 | $6.00 | $7,320.00 | $1.95 | $2,379.00 | ||||
15 | Silt Fence | 1000 | L.F. | $1.60 | $1,600.00 | $2.00 | $2,000.00 | $1.85 | $1,850.00 | ||||
16 | Temporary Seeding | 0 | Acres | $500.00 | $0.00 | $0.00 | $0.00 | $2,250.00 | $0.00 | ||||
$203,607.35 | $207,953.50 | $240,703.20 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $389,000.00 | Contractor: | River Construction Co | Fye Excavating, Inc. | James Waterhouse Construction | |||||||||
Funding Source: 50% Lake Restoration, 50% Federal-EPA, | 10874 J Ave | 10165 Sperru Rd | 1235 Hoot Owl Hollow | ||||||||||
Wapello IA 52653 | Sperry IA 52650 | Keota IA 52248 | |||||||||||
Plan Sets Requested: 15 | Quantities | 319-523-5108 | 319-985-2200 | 319-698-2102 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $11,000.00 | $11,000.00 | $9,200.00 | $9,200.00 | $11,500.00 | $11,500.00 | ||||
2 | 12" Dia. Smooth Steel Pipe | 445 | L.F. | $25.65 | $11,414.25 | $31.00 | $13,795.00 | $30.00 | $13,350.00 | ||||
3 | 18" Dia. Smooth Steel Pipe | 340 | L.F. | $40.03 | $13,610.20 | $49.00 | $16,660.00 | $47.00 | $15,980.00 | ||||
4 | 36" Dia. Smooth Steel Pipe Riser | 20 | L.F. | $212.50 | $4,250.00 | $190.00 | $3,800.00 | $100.00 | $2,000.00 | ||||
5 | Trash Rack for Canopy Inlet (12") | 2 | Each | $300.00 | $600.00 | $550.00 | $1,100.00 | $400.00 | $800.00 | ||||
6 | Trash Rack for Vertical Riser (36") | 2 | Each | $1,320.00 | $2,640.00 | $910.00 | $1,820.00 | $700.00 | $1,400.00 | ||||
7 | Fine Drainfill | 400 | Tons | $24.00 | $9,600.00 | $28.25 | $11,300.00 | $50.00 | $20,000.00 | ||||
8 | Earthwork / Fill / Grade | 36000 | C.Y. | $1.75 | $63,000.00 | $1.70 | $61,200.00 | $1.79 | $64,440.00 | ||||
9 | Core Trench | 2870 | C.Y. | $1.45 | $4,161.50 | $2.75 | $7,892.50 | $2.00 | $5,740.00 | ||||
10 | Seed & Mulch | 11.6 | Acres | $1,950.00 | $22,620.00 | $1,575.00 | $18,270.00 | $1,900.00 | $22,040.00 | ||||
11 | Clearing & Grubbing | 16.2 | Acres | $2,500.00 | $40,500.00 | $1,750.00 | $28,350.00 | $2,500.00 | $40,500.00 | ||||
12 | 6" Stripping and Respread | 9400 | C.Y. | $2.00 | $18,800.00 | $3.00 | $28,200.00 | $2.00 | $18,800.00 | ||||
13 | Class D Rip Rap | 1200 | Tons | $34.00 | $40,800.00 | $42.50 | $51,000.00 | $35.00 | $42,000.00 | ||||
14 | Field Fence | 1220 | L.F. | $4.80 | $5,856.00 | $5.00 | $6,100.00 | $4.80 | $5,856.00 | ||||
15 | Silt Fence | 1000 | L.F. | $1.65 | $1,650.00 | $3.70 | $3,700.00 | $1.55 | $1,550.00 | ||||
16 | Temporary Seeding | 0 | Acres | $600.00 | $0.00 | $900.00 | $0.00 | $2,500.00 | $0.00 | ||||
$250,501.95 | $262,387.50 | $265,956.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $389,000.00 | Contractor: | Seaton Construction | Steger Construction Inc | Miller Trucking & Excavating | |||||||||
Funding Source: 50% Lake Restoration, 50% Federal-EPA, | 602 Locust St PO Box 213 | 3297 Vine Rd | 3303 John Deere Road | ||||||||||
Deep River IA 522220213 | Dyersville IA 52040 | Silvis IL 31282 | |||||||||||
Plan Sets Requested: 15 | Quantities | 6415952261 | 563-875-7876 | 309-755-7644 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $9,300.00 | $9,300.00 | $16,000.00 | $16,000.00 | $14,000.00 | $14,000.00 | ||||
2 | 12" Dia. Smooth Steel Pipe | 445 | L.F. | $35.00 | $15,575.00 | $59.00 | $26,255.00 | $90.00 | $40,050.00 | ||||
3 | 18" Dia. Smooth Steel Pipe | 340 | L.F. | $52.00 | $17,680.00 | $84.00 | $28,560.00 | $120.00 | $40,800.00 | ||||
4 | 36" Dia. Smooth Steel Pipe Riser | 20 | L.F. | $20.00 | $400.00 | $280.00 | $5,600.00 | $600.00 | $12,000.00 | ||||
5 | Trash Rack for Canopy Inlet (12") | 2 | Each | $450.00 | $900.00 | $2,250.00 | $4,500.00 | $1,500.00 | $3,000.00 | ||||
6 | Trash Rack for Vertical Riser (36") | 2 | Each | $1,500.00 | $3,000.00 | $9,000.00 | $18,000.00 | $1,500.00 | $3,000.00 | ||||
7 | Fine Drainfill | 400 | Tons | $27.00 | $10,800.00 | $25.00 | $10,000.00 | $19.00 | $7,600.00 | ||||
8 | Earthwork / Fill / Grade | 36000 | C.Y. | $1.90 | $68,400.00 | $3.33 | $119,880.00 | $6.00 | $216,000.00 | ||||
9 | Core Trench | 2870 | C.Y. | $2.25 | $6,457.50 | $2.00 | $5,740.00 | $4.00 | $11,480.00 | ||||
10 | Seed & Mulch | 11.6 | Acres | $1,800.00 | $20,880.00 | $1,950.00 | $22,620.00 | $1,500.00 | $17,400.00 | ||||
11 | Clearing & Grubbing | 16.2 | Acres | $2,000.00 | $32,400.00 | $2,700.00 | $43,740.00 | $3,000.00 | $48,600.00 | ||||
12 | 6" Stripping and Respread | 9400 | C.Y. | $3.00 | $28,200.00 | $3.42 | $32,148.00 | $4.00 | $37,600.00 | ||||
13 | Class D Rip Rap | 1200 | Tons | $45.00 | $54,000.00 | $37.50 | $45,000.00 | $31.00 | $37,200.00 | ||||
14 | Field Fence | 1220 | L.F. | $8.00 | $9,760.00 | $4.80 | $5,856.00 | $5.00 | $6,100.00 | ||||
15 | Silt Fence | 1000 | L.F. | $5.00 | $5,000.00 | $1.75 | $1,750.00 | $2.50 | $2,500.00 | ||||
16 | Temporary Seeding | 0 | Acres | $900.00 | $0.00 | $1,000.00 | $0.00 | $2,500.00 | $0.00 | ||||
$282,752.50 | $385,649.00 | $497,330.00 | |||||||||||
10 | 11 | 12 | |||||||||||
Estimated Cost: $389,000.00 | Contractor: | Laverdiere Construction Inc | |||||||||||
Funding Source: 50% Lake Restoration, 50% Federal-EPA, | 4055 W Jackson | ||||||||||||
Macomb IL 61455 | |||||||||||||
Plan Sets Requested: 15 | Quantities | (309) 837-1258 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $20,000.00 | $20,000.00 | $0.00 | $0.00 | ||||||
2 | 12" Dia. Smooth Steel Pipe | 445 | L.F. | $105.00 | $46,725.00 | $0.00 | $0.00 | ||||||
3 | 18" Dia. Smooth Steel Pipe | 340 | L.F. | $130.00 | $44,200.00 | $0.00 | $0.00 | ||||||
4 | 36" Dia. Smooth Steel Pipe Riser | 20 | L.F. | $149.00 | $2,980.00 | $0.00 | $0.00 | ||||||
5 | Trash Rack for Canopy Inlet (12") | 2 | Each | $1,400.00 | $2,800.00 | $0.00 | $0.00 | ||||||
6 | Trash Rack for Vertical Riser (36") | 2 | Each | $2,900.00 | $5,800.00 | $0.00 | $0.00 | ||||||
7 | Fine Drainfill | 400 | Tons | $39.00 | $15,600.00 | $0.00 | $0.00 | ||||||
8 | Earthwork / Fill / Grade | 36000 | C.Y. | $5.95 | $214,200.00 | $0.00 | $0.00 | ||||||
9 | Core Trench | 2870 | C.Y. | $5.00 | $14,350.00 | $0.00 | $0.00 | ||||||
10 | Seed & Mulch | 11.6 | Acres | $3,500.00 | $40,600.00 | $0.00 | $0.00 | ||||||
11 | Clearing & Grubbing | 16.2 | Acres | $11,000.00 | $178,200.00 | $0.00 | $0.00 | ||||||
12 | 6" Stripping and Respread | 9400 | C.Y. | $5.75 | $54,050.00 | $0.00 | $0.00 | ||||||
13 | Class D Rip Rap | 1200 | Tons | $59.00 | $70,800.00 | $0.00 | $0.00 | ||||||
14 | Field Fence | 1220 | L.F. | $16.00 | $19,520.00 | $0.00 | $0.00 | ||||||
15 | Silt Fence | 1000 | L.F. | $6.00 | $6,000.00 | $0.00 | $0.00 | ||||||
16 | Temporary Seeding | 0 | Acres | $0.00 | $0.00 | $0.00 | $0.00 | ||||||
$735,825.00 | $0.00 | $0.00 | |||||||||||
Laverdiere Construction Inc, Macomb, IL
9/28/2024