IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Black Hawk Marsh WMA | Date: 4/21/2016 | Project No. |
Inlet Dredging | County: | SAC | Time: 11:00 AM | 13-01-81-06 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $2,500,000.00 | Contractor: | Bedrock Gravel, Inc. | Dredge America, Inc. | Dubuque Barge & Fleeting Service Co. dba | |||||||||
Funding Source: 100% Lake Restoration, | 1108 Hwy 59 | 9555 NW Hwy N | 5 Jones St | ||||||||||
Schleswig IA 51461 | Kansas City MO 64153 | Dubuque IA 52001 | |||||||||||
Plan Sets Requested: 2 | Quantities | 712-830-2591 | 816-330-3100 | 563-557-1855 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | DREDGING, HYDRAULIC | 330000 | C.Y. | $6.00 | $1,980,000.00 | $5.68 | $1,874,400.00 | $6.70 | $2,211,000.00 | ||||
2 | CONTROL STRUCTION | 1 | L.S. | $44,000.00 | $44,000.00 | $50,000.00 | $50,000.00 | $40,000.00 | $40,000.00 | ||||
3 | MOBILIZATOIN | 1 | L.S. | $75,000.00 | $75,000.00 | $450,000.00 | $450,000.00 | $285,000.00 | $285,000.00 | ||||
$2,099,000.00 | $2,374,400.00 | $2,536,000.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $2,500,000.00 | Contractor: | Magruder Construction Co. Inc. | Southwind Construction Corp | ||||||||||
Funding Source: 100% Lake Restoration, | 243 West Outer Rd | 14649 Hwy 41 N Suite 100 | |||||||||||
Eolia MO 63344 | Evansville IN 47725 | ||||||||||||
Plan Sets Requested: 2 | Quantities | 573-485-2161 | 812-867-7220 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | DREDGING, HYDRAULIC | 330000 | C.Y. | $6.85 | $2,260,500.00 | $7.01 | $2,313,300.00 | $0.00 | |||||
2 | CONTROL STRUCTION | 1 | L.S. | $78,000.00 | $78,000.00 | $35,603.36 | $35,603.36 | $0.00 | |||||
3 | MOBILIZATOIN | 1 | L.S. | $378,000.00 | $378,000.00 | $594,216.65 | $594,216.65 | $0.00 | |||||
$2,716,500.00 | $2,943,120.01 | $0.00 | |||||||||||
5/5/2024