IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Stephens State Forest, Unionville Unit | Date: 4/28/2016 | Project No. |
Pond Spillway Repair | County: | APPANOOSE | Time: 3:00 p.m. | 15-05-04-10 |
![]() | 1 | 2 | 3 | ![]() | |||||||||
Estimated Cost: $15,000.00 | Contractor: | ![]() | Savage Dirt Works, LLC | Dingman Const. | Hymbaugh Construction | ![]() | |||||||
Funding Source: 100% REAP OS Acquisition & Development, | ![]() | 48499 Hy-Vee Rd | ![]() | 1265 240th St | ![]() | 821 Quiet Harbor | ![]() | ||||||
![]() | Chariton IA 50049 | ![]() | Creston IA 50801 | ![]() | Creston IA 50801 | ![]() | |||||||
Plan Sets Requested: 0 | Quantities | ![]() | 641-203-2357 | ![]() | 641-247-1431 | ![]() | 641-340-0232 | ![]() | |||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Contractor Supplied Fill Dirt, Placed & Compacted | 370 | C.Y. | ![]() | $13.88 | $5,135.60 | ![]() | $43.71 | $16,172.70 | ![]() | $60.00 | $22,200.00 | ![]() |
2 | Engineering Fabric | 111 | S.Y. | ![]() | $3.50 | $388.50 | ![]() | $2.00 | $222.00 | ![]() | $20.00 | $2,220.00 | ![]() |
3 | Class E Riprap | 140 | Tons | ![]() | $48.50 | $6,790.00 | ![]() | $68.39 | $9,574.60 | ![]() | $60.00 | $8,400.00 | ![]() |
4 | Mobilization, Site Restoration | 1 | L.S. | ![]() | $3,500.00 | $3,500.00 | ![]() | $2,700.00 | $2,700.00 | ![]() | $6,000.00 | $6,000.00 | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$15,814.10 | ![]() | $28,669.30 | ![]() | $38,820.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
![]() | 4 | 5 | 6 | ![]() | |||||||||
Estimated Cost: $15,000.00 | Contractor: | ![]() | Joiner Construction Co. Inc. | ![]() | |||||||||
Funding Source: 100% REAP OS Acquisition & Development, | ![]() | 11996 490th St | ![]() | ![]() | ![]() | ||||||||
![]() | Plano IA 52581 | ![]() | ![]() | ![]() | |||||||||
Plan Sets Requested: 0 | Quantities | ![]() | 641-6419-2646 | ![]() | ![]() | ![]() | |||||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Contractor Supplied Fill Dirt, Placed & Compacted | 370 | C.Y. | ![]() | $95.00 | $35,150.00 | ![]() | $0.00 | ![]() | $0.00 | ![]() | ||
2 | Engineering Fabric | 111 | S.Y. | ![]() | $4.00 | $444.00 | ![]() | $0.00 | ![]() | $0.00 | ![]() | ||
3 | Class E Riprap | 140 | Tons | ![]() | $91.25 | $12,775.00 | ![]() | $0.00 | ![]() | $0.00 | ![]() | ||
4 | Mobilization, Site Restoration | 1 | L.S. | ![]() | $6,500.00 | $6,500.00 | ![]() | $0.00 | ![]() | $0.00 | ![]() | ||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$54,869.00 | ![]() | $0.00 | ![]() | $0.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |