IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lost Grove Lake W.M.A. | Date: 10/29/2015 | Project No. |
| Joint Repairs | County: | SCOTT | Time: 11:00 a.m. | 16-06-82-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $9,000.00 | Contractor: | Valley Construction Company | |||||||||||
| Funding Source: 100% Marine Fuel Tax -Minors, | 3610 78th Ave West | ||||||||||||
| Rock Island IL 61201 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 309-787-0292 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | PCC Joint Stitching | 100 | Each | $116.00 | $11,600.00 | $0.00 | $0.00 | ||||||
| 2 | PCC Joint Cleaning and Resealing with Hot Pour Sealant | 1800 | L.F. | $5.70 | $10,260.00 | $0.00 | $0.00 | ||||||
| $21,860.00 | $0.00 | $0.00 | |||||||||||
12/22/2025