IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Prairie Resource Center | Date: 11/10/2016 | Project No. |
Greenhouse Replacement | County: | LEE | Time: 11:00 a.m. | 16-06-56-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $51,000.00 | Contractor: | Hennigar Construction LC | Kingdom Construction | ||||||||||
Funding Source: 75% Federal-FEMA 1, 25% F&W Trust - Other, | 1853 303rd Ave | 1961 KK Ave | |||||||||||
Fort Madison IA 52627 | Marengo IA 52301 | ||||||||||||
Plan Sets Requested: 0 | Quantities | 319-470-1588 | 319-530-3601 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | DEMOLITION (INCLUDING DISPOSAL) | 1 | L.S. | $1,200.00 | $1,200.00 | $2,500.00 | $2,500.00 | $0.00 | |||||
2 | PROPOSED GREEN HOUSE BUILDING AND ALL ASSOCIATED ITEMS | 1 | L.S. | $23,416.95 | $23,416.95 | $24,000.00 | $24,000.00 | $0.00 | |||||
3 | INDIRECT FIRED UNIT HEATER AND ALL ASSOCIATED ITEMS | 1 | L.S. | $5,178.33 | $5,178.33 | $3,800.00 | $3,800.00 | $0.00 | |||||
4 | HVAC FANS AND ALL ASSOCIATED ITEMS | 1 | L.S. | $9,577.60 | $9,577.60 | $6,400.00 | $6,400.00 | $0.00 | |||||
5 | MISCELLANEOUS ITEMS | 1 | L.S. | $8,049.00 | $8,049.00 | $10,000.00 | $10,000.00 | $0.00 | |||||
6 | MOBILIZATION, LABOR AND INSTALLATION OF ALL ITEMS | 1 | L.S. | $20,644.69 | $20,644.69 | $25,000.00 | $25,000.00 | $0.00 | |||||
$68,066.57 | $71,700.00 | $0.00 | |||||||||||
5/18/2024