| Bids For: | Location: | Lacey-Keosauqua State Park | Date: 9/22/2016 | Project No. |
| Culvert Replacement | County: | VAN BUREN | Time: 11:00 a.m. | 16-06-89-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $135,000.00 | Contractor: | Cole Construction Co, Inc. | |||||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 24100 Queen Ave | ||||||||||||
| Keosauqua IA 52565 | |||||||||||||
| Plan Sets Requested: 3 | Quantities | 319-592-3103 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | CLEARING AND GRUBBING | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
| 2 | REMOVAL OF EXISTING STRUCTURE | 1 | L.F. | $5,000.00 | $5,000.00 | $0.00 | $0.00 | ||||||
| 3 | REMOVAL OF EXISTING PIPE | 22 | L.F. | $20.00 | $440.00 | $0.00 | $0.00 | ||||||
| 4 | REMOVAL OF PAVEMENT | 709.5 | S.Y. | $8.00 | $5,676.00 | $0.00 | $0.00 | ||||||
| 5 | SAW CUTTING EXISTING ASPHALT PAVEMENT | 40 | L.F. | $5.00 | $200.00 | $0.00 | $0.00 | ||||||
| 6 | PAVING, P.C. CONCRETE, 7" | 788.1 | S.Y. | $42.75 | $33,691.275 | $0.00 | $0.00 | ||||||
| 7 | SHOULDER CONSTRUCTION, EARTH | 7 | STA. | $300.00 | $2,100.00 | $0.00 | $0.00 | ||||||
| 8 | SPECIAL BACKFILL | 867 | S.Y. | $7.65 | $6,632.55 | $0.00 | $0.00 | ||||||
| 9 | CLASS "A" CRUSHED STONE | 11 | Tons | $25.00 | $275.00 | $0.00 | $0.00 | ||||||
| 10 | CULVERT, LOW CLEARANCE CONCRETE ROADWAY PIPE, EQUIV. DIAM. 30 IN. | 112 | L.F. | $108.50 | $12,152.00 | $0.00 | $0.00 | ||||||
| 11 | APRON, LOW CLEARANCE CONCRETE, EQUIV. DIAM. 30 IN. | 4 | Each | $925.44 | $3,701.76 | $0.00 | $0.00 | ||||||
| 12 | APRON GUARD, DR-213 | 2 | Each | $1,057.84 | $2,115.68 | $0.00 | $0.00 | ||||||
| 13 | PIPE FOOTING | 6 | Each | $700.00 | $4,200.00 | $0.00 | $0.00 | ||||||
| 14 | ANTI-SEEP COLLAR | 1 | Each | $500.00 | $500.00 | $0.00 | $0.00 | ||||||
| 15 | CULVERT, LOW CLEARANCE CONCRETE ENTRANCE PIPE, EQUIV. DIAM. 18 IN. | 22 | L.F. | $85.86 | $1,888.92 | $0.00 | $0.00 | ||||||
| 16 | APRON, LOW CLEARANCE CONCRETE, EQUIV. DIAM. 18 IN. | 2 | Each | $569.14 | $1,138.28 | $0.00 | $0.00 | ||||||
| 17 | EXCAVATION, CLASS 10, ROADWAY AND BORROW | 31.7 | C.Y. | $25.00 | $792.50 | $0.00 | $0.00 | ||||||
| 18 | EXCAVATION, CLASS 20 | 10 | C.Y. | $25.00 | $250.00 | $0.00 | $0.00 | ||||||
| 19 | EMBANKMENT-IN-PLACE | 248.5 | C.Y. | $30.00 | $7,455.00 | $0.00 | $0.00 | ||||||
| 20 | FLOWABLE MORTAR | 18.4 | C.Y. | $250.00 | $4,600.00 | $0.00 | $0.00 | ||||||
| 21 | FLOODED BACKFILL | 93.6 | C.Y. | $40.00 | $3,744.00 | $0.00 | $0.00 | ||||||
| 22 | ROCK CHECK DAM | 24 | L.F. | $45.00 | $1,080.00 | $0.00 | $0.00 | ||||||
| 23 | REVETMENT, CLASS E | 40 | Tons | $52.00 | $2,080.00 | $0.00 | $0.00 | ||||||
| 24 | FINISH GRADING | 1 | L.S. | $2,000.00 | $2,000.00 | $0.00 | $0.00 | ||||||
| 25 | SEEDING, FERTILIZING AND MULCHING | 0.11 | Acres | $10,000.00 | $1,100.00 | $0.00 | $0.00 | ||||||
| 26 | EROSION CONTROL | 895 | L.F. | $8.00 | $7,160.00 | $0.00 | $0.00 | ||||||
| 27 | TRAFFIC CONTROL | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
| 28 | CONSTRUCTION STAKING | 1 | L.S. | $1,600.00 | $1,600.00 | $0.00 | $0.00 | ||||||
| 29 | MOBILIZATION | 1 | L.S. | $5,000.00 | $5,000.00 | $0.00 | $0.00 | ||||||
| $121,572.965 | $0.00 | $0.00 | |||||||||||