IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Honey Creek Resort State Park | Date: 4/20/2017 | Project No. |
| Stormwater Project | County: | APPANOOSE | Time: 11:00 a.m. | 16-05-04-05 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $145,000.00 | Contractor: | TK Concrete, Inc. | David Kurnes DBA DC Plumbing & Excavation | Joiner Construction Co. Inc. | |||||||||
| Funding Source: 100% Marine Fuel Tax -Minors, | 1608 Fifield Rd | 17356 Husky Trl | 11996 490th St | ||||||||||
| Pella IA 50219 | Drakesville IA 52552 | Plano IA 52581 | |||||||||||
| Plan Sets Requested: 3 | Quantities | 641-628-4590 | 641-226-2049 | 641-649-2646 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2' Curb and Gutter | 333 | L.F. | $30.00 | $9,990.00 | $33.00 | $10,989.00 | $35.00 | $11,655.00 | ||||
| 2 | SW-501 Manhole #1 | 1 | Each | $5,000.00 | $5,000.00 | $5,500.00 | $5,500.00 | $6,500.00 | $6,500.00 | ||||
| 3 | SW-501 Manhole #2 | 1 | Each | $2,750.00 | $2,750.00 | $3,600.00 | $3,600.00 | $4,500.00 | $4,500.00 | ||||
| 4 | SW-501 Manhole #3 | 1 | Each | $2,500.00 | $2,500.00 | $3,200.00 | $3,200.00 | $3,600.00 | $3,600.00 | ||||
| 5 | 18" RCP Storm Sewer | 128 | L.F. | $55.00 | $7,040.00 | $100.00 | $12,800.00 | $164.00 | $20,992.00 | ||||
| 6 | 18" RCP Apron w/ Footing | 2 | Each | $3,500.00 | $7,000.00 | $2,938.50 | $5,877.00 | $3,000.00 | $6,000.00 | ||||
| 7 | Granular Shoulder | 34 | Tons | $30.00 | $1,020.00 | $76.45 | $2,599.30 | $60.50 | $2,057.00 | ||||
| 8 | Erosion Stone | 104 | Tons | $50.00 | $5,200.00 | $105.28 | $10,949.12 | $59.00 | $6,136.00 | ||||
| 9 | Revetment, Class E | 1788 | Tons | $40.00 | $71,520.00 | $36.63 | $65,494.44 | $36.00 | $64,368.00 | ||||
| 10 | Engineering Fabric | 1935 | S.Y. | $2.00 | $3,870.00 | $3.26 | $6,308.10 | $1.55 | $2,999.25 | ||||
| 11 | Mobilization | 1 | L.S. | $6,000.00 | $6,000.00 | $1,500.00 | $1,500.00 | $2,500.00 | $2,500.00 | ||||
| $121,890.00 | $128,816.96 | $131,307.25 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $145,000.00 | Contractor: | Hymbaugh Construction | Savage Dirt Works, LLC | Leffler Dirtworks, LLC | |||||||||
| Funding Source: 100% Marine Fuel Tax -Minors, | 821 Quiet Harbor | PO Box 608 | 2272 320th St | ||||||||||
| Creston IA 50801 | Chariton IA 50049 | Oskaloosa IA 52577 | |||||||||||
| Plan Sets Requested: 3 | Quantities | 641-340-0232 | 641-226-2231 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2' Curb and Gutter | 333 | L.F. | $30.00 | $9,990.00 | $17.25 | $5,744.25 | $50.00 | $16,650.00 | ||||
| 2 | SW-501 Manhole #1 | 1 | Each | $3,000.00 | $3,000.00 | $12,729.41 | $12,729.41 | $5,000.00 | $5,000.00 | ||||
| 3 | SW-501 Manhole #2 | 1 | Each | $3,000.00 | $3,000.00 | $4,891.18 | $4,891.18 | $5,000.00 | $5,000.00 | ||||
| 4 | SW-501 Manhole #3 | 1 | Each | $3,000.00 | $3,000.00 | $2,448.53 | $2,448.53 | $5,000.00 | $5,000.00 | ||||
| 5 | 18" RCP Storm Sewer | 128 | L.F. | $30.00 | $3,840.00 | $90.36 | $11,566.08 | $50.00 | $6,400.00 | ||||
| 6 | 18" RCP Apron w/ Footing | 2 | Each | $2,000.00 | $4,000.00 | $4,932.94 | $9,865.88 | $3,000.00 | $6,000.00 | ||||
| 7 | Granular Shoulder | 34 | Tons | $30.00 | $1,020.00 | $36.20 | $1,230.80 | $35.00 | $1,190.00 | ||||
| 8 | Erosion Stone | 104 | Tons | $40.00 | $4,160.00 | $44.50 | $4,628.00 | $40.00 | $4,160.00 | ||||
| 9 | Revetment, Class E | 1788 | Tons | $50.00 | $89,400.00 | $35.00 | $62,580.00 | $45.00 | $80,460.00 | ||||
| 10 | Engineering Fabric | 1935 | S.Y. | $2.00 | $3,870.00 | $2.00 | $3,870.00 | $3.00 | $5,805.00 | ||||
| 11 | Mobilization | 1 | L.S. | $10,000.00 | $10,000.00 | $18,750.00 | $18,750.00 | $15,000.00 | $15,000.00 | ||||
| $135,280.00 | $138,304.13 | $150,665.00 | |||||||||||
Savage Dirt Works, LLC, Chariton, IA
Leffler Dirtworks, LLC, Oskaloosa, IA
4/1/2026