IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake Manawa State Park | Date: 8/20/2015 | Project No. |
| 2015 Dredging (Alternate Bid) | County: | POTTAWATTAMIE | Time: 11:00 AM | 14-04-78-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $5,150,000.00 | Contractor: | JF Brennan Co Inc | Great Lakes Dredge & Dock Company, LLC | Dubuque Barge and Fleeting Svc Co dba Newt Marine | |||||||||
| Funding Source: 100% Lake Restoration, | 820 Bainbridge St PO Box 2557 | 2122 York Road | 5 Jones St | ||||||||||
| LaCrosse WI 54603 | Oak Brook IL 60523 | Dubuque IA 52001 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 608-784-7173 | 630-574-3000 | 563-557-1855 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization / Demobilization | 1 | L.S. | $797,700.00 | $797,700.00 | $1,200,000.00 | $1,200,000.00 | $555,000.00 | $555,000.00 | ||||
| 2 | In-Lake Buoy / Park Safety Plan | 1 | L.S. | $20,000.00 | $20,000.00 | $12,000.00 | $12,000.00 | $22,000.00 | $22,000.00 | ||||
| 3 | Stormwater Pollution Prevention Plan | 1 | L.S. | $12,500.00 | $12,500.00 | $6,000.00 | $6,000.00 | $15,000.00 | $15,000.00 | ||||
| 4 | Handling of Water | 1 | L.S. | $14,000.00 | $14,000.00 | $6,000.00 | $6,000.00 | $110,000.00 | $110,000.00 | ||||
| 5 | Instrumentation - Piezometer Repairs | 3 | Each | $4,000.00 | $12,000.00 | $2,000.00 | $6,000.00 | $1,500.00 | $4,500.00 | ||||
| 6 | Instrumentation - Data Loggers | 11 | Each | $1,826.00 | $20,086.00 | $2,000.00 | $22,000.00 | $1,900.00 | $20,900.00 | ||||
| 7 | Instrumentation - Mosquito Creek Flow Meter | 1 | L.S. | $24,000.00 | $24,000.00 | $20,000.00 | $20,000.00 | $22,000.00 | $22,000.00 | ||||
| 8 | Instrumentation - Upper Indian Creek Flow Meter | 1 | L.S. | $13,000.00 | $13,000.00 | $12,000.00 | $12,000.00 | $13,000.00 | $13,000.00 | ||||
| 9 | Instrumentation - Lower Indian Creek Flow Meter | 1 | L.S. | $13,000.00 | $13,000.00 | $12,000.00 | $12,000.00 | $13,000.00 | $13,000.00 | ||||
| 10 | Instrumentation - Lake Piezometer and Staff Gauge | 1 | L.S. | $4,500.00 | $4,500.00 | $4,000.00 | $4,000.00 | $7,500.00 | $7,500.00 | ||||
| 11 | Instrumentation - Tipping Bucket Rain Gauge System | 1 | L.S. | $5,800.00 | $5,800.00 | $6,000.00 | $6,000.00 | $5,500.00 | $5,500.00 | ||||
| 12 | Seeding | 1 | L.S. | $14,000.00 | $14,000.00 | $25,000.00 | $25,000.00 | $73,500.00 | $73,500.00 | ||||
| $950,586.00 | $1,331,000.00 | $861,900.00 | |||||||||||
| Alternate | |||||||||||||
| 14 | Dredged Sand Stockpile "A" | 300000 | C.Y. | $6.50 | $1,950,000.00 | $8.91 | $2,673,000.00 | $20.07 | $6,021,000.00 | ||||
| Alternate | |||||||||||||
| 15 | Dredged Sand Stockpile "B" | 200000 | C.Y. | $6.50 | $1,300,000.00 | $8.91 | $1,782,000.00 | $20.07 | $4,014,000.00 | ||||
| $4,200,586.00 | $5,786,000.00 | $10,896,900.00 | |||||||||||