IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Red Haw State Park  Date: 6/23/2016  Project No.  
  Campground Improvements  County:   LUCAS  Time: 11:00 a.m.  15-05-59-02

 

 
1
2
3
Estimated Cost: $141,199.00
Contractor: 
Shekar EngineeringHymbaugh ConstructionVieco Development & Construction Co Inc
Funding Source: 100% Infrastructure 2015, 2600 MLK Jr Pkwy
821 Quiet Harbor
5180 SE 70th Rd
Des Moines IA  50310Creston IA  50801St Joseph MO  64507
Plan Sets Requested: 4
Quantities
515-334-5062641-340-0232816-387-1884
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Tree Removals6Each$1,382.96$8,297.76 $400.00$2,400.00 $2,300.00$13,800.00 
2Demolition1L.S.$6,985.60$6,985.60 $3,000.00$3,000.00 $9,000.00$9,000.00 
3Grading1L.S.$2,950.00$2,950.00 $6,000.00$6,000.00 $8,000.00$8,000.00 
48" Filter Sock300L.F.$3.25$975.00 $5.00$1,500.00 $5.00$1,500.00 
5Waterline Connection to Existing1Each$1,937.56$1,937.56 $300.00$300.00 $2,000.00$2,000.00 
6Woodford Model S-3 Sanitary Yard Hydrant3Each$3,068.00$9,204.00 $400.00$1,200.00 $1,500.00$4,500.00 
71-Inch HDPE Pipe121L.F.$16.01$1,937.21 $10.00$1,210.00 $20.00$2,420.00 
8Engineering Fabric2216S.Y.$2.95$6,537.20 $3.00$6,648.00 $2.00$4,432.00 
9Macadam Stone540Tons$41.42$22,366.80 $40.00$21,600.00 $32.00$17,280.00 
10Class "A" Roadstone350Tons$47.61$16,663.50 $40.00$14,000.00 $29.00$10,150.00 
11Traffic Control1L.S.$354.00$354.00 $2,000.00$2,000.00 $500.00$500.00 
12Seed, Fertilizer with Hydromulch1.4Acres$5,310.00$7,434.00 $5,000.00$7,000.00 $5,000.00$7,000.00 
13Electrical Improvements1L.S.$41,318.91$41,318.91 $68,000.00$68,000.00 $34,000.00$34,000.00 
14NPDES General Permit #2 & SWPPP1L.S.$1,239.00$1,239.00 $5,000.00$5,000.00 $5,500.00$5,500.00 
15Mobilization1L.S.$5,900.00$5,900.00 $2,000.00$2,000.00 $7,900.00$7,900.00 
16Romart Water Tower and Sign1Each$4,956.00$4,956.00 $4,000.00$4,000.00 $3,200.00$3,200.00 
17Kiosk1L.S.$10,620.00$10,620.00 $4,000.00$4,000.00 $23,000.00$23,000.00 
      $149,676.54  $149,858.00  $154,182.00 
 
4
5
6
Estimated Cost: $141,199.00
Contractor: 
McGee Concrete and Landscaping
Funding Source: 100% Infrastructure 2015, 219 N Fryer St


Russell IA  50238    
Plan Sets Requested: 4
Quantities
641-203-0721
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Tree Removals6Each$1,166.67$7,000.02 $0.00 $0.00 
2Demolition1L.S.$3,000.00$3,000.00 $0.00 $0.00 
3Grading1L.S.$1,250.00$1,250.00 $0.00 $0.00 
48" Filter Sock300L.F.$9.33$2,799.00 $0.00 $0.00 
5Waterline Connection to Existing1Each$375.00$375.00 $0.00 $0.00 
6Woodford Model S-3 Sanitary Yard Hydrant3Each$1,550.00$4,650.00 $0.00 $0.00 
71-Inch HDPE Pipe121L.F.$9.26$1,120.46 $0.00 $0.00 
8Engineering Fabric2216S.Y.$2.17$4,808.72 $0.00 $0.00 
9Macadam Stone540Tons$50.00$27,000.00 $0.00 $0.00 
10Class "A" Roadstone350Tons$50.00$17,500.00 $0.00 $0.00 
11Traffic Control1L.S.$800.00$800.00 $0.00 $0.00 
12Seed, Fertilizer with Hydromulch1.4Acres$5,142.86$7,200.004 $0.00 $0.00 
13Electrical Improvements1L.S.$62,000.00$62,000.00 $0.00 $0.00 
14NPDES General Permit #2 & SWPPP1L.S.$600.00$600.00 $0.00 $0.00 
15Mobilization1L.S.$7,500.00$7,500.00 $0.00 $0.00 
16Romart Water Tower and Sign1Each$1,580.00$1,580.00 $0.00 $0.00 
17Kiosk1L.S.$11,300.00$11,300.00 $0.00 $0.00 
      $160,483.204  $0.00  $0.00 
 



 