 Bids For:  Location:   Bellevue State Park  Date: 11/12/2015  Project No.  
  Shower Building Replacement  County:   JACKSON  Time: 11:00 a.m.  15-06-49-04

 

 
1
2
3
Estimated Cost: $300,000.00
Contractor: 
F.L. Krapfl Inc.Portzen Construction, Inc.Miller Trucking & Excavating
Funding Source: 50% Infrastructure 2015, 50% Federal-Land and Water Conservation Fund,
PO Box 303
205 Stone Valley Drive
3303 John Deere Rd
Dyersville IA  52040Dubuque IA  52003Silvis IL  61282
Plan Sets Requested: 4
Quantities
563-875-8938563-557-7642309-755-7644
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1CLEARING AND GRUBBING1L.S.$500.00$500.00 $937.00$937.00 $1,200.00$1,200.00 
2GRADING1L.S.$1,712.00$1,712.00 $3,700.00$3,700.00 $3,500.00$3,500.00 
38" FILTER SOCK150L.F.$3.35$502.50 $3.25$487.50 $10.00$1,500.00 
4SEEDING, FERTILIZING AND MULCHING1L.S.$1,303.00$1,303.00 $1,000.00$1,000.00 $4,200.00$4,200.00 
52" WATER SERVICE (PVC SDR 21 OR HDPE)1L.S.$845.00$845.00 $2,700.00$2,700.00 $2,500.00$2,500.00 
64" SCHEDULE 40 PVC SANITARY SEWER AND CLEANOUTS1L.S.$1,180.00$1,180.00 $1,600.00$1,600.00 $3,500.00$3,500.00 
75" REINFORCED PCC SIDEWALK & GRANULAR SUBBASE1L.S.$7,129.00$7,129.00 $5,700.00$5,700.00 $9,025.00$9,025.00 
8CAST IRON ADA DETECTION TILES (24" X 30")3Each$160.00$480.00 $160.00$480.00 $675.00$2,025.00 
9DEMOLITION1L.S.$4,825.00$4,825.00 $3,900.00$3,900.00 $17,800.00$17,800.00 
10ELECTRICAL SERVICE1L.S.$2,075.00$2,075.00 $1,600.00$1,600.00 $5,050.00$5,050.00 
11DRAIN-DOWN PIT1L.S.$4,400.00$4,400.00 $3,000.00$3,000.00 $7,500.00$7,500.00 
126" REINFORCED PCC PARKING AREA AND HANDICAP STRIPING1L.S.$6,193.00$6,193.00 $6,300.00$6,300.00 $8,150.00$8,150.00 
13PRECAST CONCRETE SHOWER/RESTROOM1Each$206,734.00$206,734.00 $203,500.00$203,500.00 $230,000.00$230,000.00 
14CONSTRUCTION SURVEY STAKING1L.S.$500.00$500.00 $800.00$800.00 $4,400.00$4,400.00 
15MOBILIZATION1L.S.$5,000.00$5,000.00 $17,500.00$17,500.00 $15,000.00$15,000.00 
      $243,378.50  $253,204.50  $315,350.00 
 



 