IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Backbone State Park | Date: 12/10/2015 | Project No. |
| Cabin Remodel | County: | DELAWARE | Time: 11:00 am | 15-03-28-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $207,000.00 | Contractor: | Sheets Design Build | Matt Construction, Inc. | Loecke Building Services, Inc. | |||||||||
| Funding Source: 100% Infrastructure 2015, | 18284 Hwy 64 W | 203 Y Ave | 1501 210th St | ||||||||||
| Maquoketa IA 52060 | Sumner IA 50674 | Manchester IA 52057 | |||||||||||
| Plan Sets Requested: 3 | Quantities | 563-652-8399 | 563-578-8418 | 563-927-5677 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | DEMOLITION | 1 | L.S. | $10,602.00 | $10,602.00 | $19,200.00 | $19,200.00 | $13,080.00 | $13,080.00 | ||||
| 2 | UPSTAIRS RESTROOM REMODEL (CABINS 9-12) | 4 | Each | $7,535.75 | $30,143.00 | $9,850.00 | $39,400.00 | $14,420.00 | $57,680.00 | ||||
| 3 | RESTROOM REMODEL (CABINS A-D) | 4 | Each | $7,455.75 | $29,823.00 | $9,850.00 | $39,400.00 | $14,600.00 | $58,400.00 | ||||
| 4 | MECHANICAL (CABINS A-D) | 4 | Each | $4,905.75 | $19,623.00 | $5,180.50 | $20,722.00 | $4,620.00 | $18,480.00 | ||||
| 5 | ELECTRICAL | 1 | L.S. | $6,818.00 | $6,818.00 | $12,986.00 | $12,986.00 | $12,075.00 | $12,075.00 | ||||
| 6 | WINDOWS (CABINS A-D) | 40 | Each | $578.15 | $23,126.00 | $798.75 | $31,950.00 | $760.00 | $30,400.00 | ||||
| 7 | DOORS AND HARDWARE | 12 | Each | $1,471.58 | $17,658.96 | $1,166.00 | $13,992.00 | $1,683.00 | $20,196.00 | ||||
| 8 | MOBILIZATION | 1 | L.S. | $12,741.00 | $12,741.00 | $15,000.00 | $15,000.00 | $2,000.00 | $2,000.00 | ||||
| $150,534.96 | $192,650.00 | $212,311.00 | |||||||||||
| Alternate | |||||||||||||
| 9 | FLOORING THROUGHOUT (CABINS A-D) | 1 | L.S. | $16,325.00 | $16,325.00 | $16,870.00 | $16,870.00 | $16,632.00 | $16,632.00 | ||||
| $166,859.96 | $209,520.00 | $228,943.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $207,000.00 | Contractor: | The Wilson Group, Inc. | |||||||||||
| Funding Source: 100% Infrastructure 2015, | 1606 W Main St | ||||||||||||
| Greenwood MO 64034 | |||||||||||||
| Plan Sets Requested: 3 | Quantities | 816-537-0212 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | DEMOLITION | 1 | L.S. | $9,314.00 | $9,314.00 | $0.00 | $0.00 | ||||||
| 2 | UPSTAIRS RESTROOM REMODEL (CABINS 9-12) | 4 | Each | $8,969.00 | $35,876.00 | $0.00 | $0.00 | ||||||
| 3 | RESTROOM REMODEL (CABINS A-D) | 4 | Each | $9,216.00 | $36,864.00 | $0.00 | $0.00 | ||||||
| 4 | MECHANICAL (CABINS A-D) | 4 | Each | $10,421.00 | $41,684.00 | $0.00 | $0.00 | ||||||
| 5 | ELECTRICAL | 1 | L.S. | $7,662.00 | $7,662.00 | $0.00 | $0.00 | ||||||
| 6 | WINDOWS (CABINS A-D) | 40 | Each | $1,378.00 | $55,120.00 | $0.00 | $0.00 | ||||||
| 7 | DOORS AND HARDWARE | 12 | Each | $1,132.00 | $13,584.00 | $0.00 | $0.00 | ||||||
| 8 | MOBILIZATION | 1 | L.S. | $1,500.00 | $1,500.00 | $0.00 | $0.00 | ||||||
| Alternate | |||||||||||||
| 9 | FLOORING THROUGHOUT (CABINS A-D) | 1 | L.S. | $27,632.00 | $27,632.00 | $0.00 | $0.00 | ||||||
| $229,236.00 | $0.00 | $0.00 | |||||||||||
12/23/2025