IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Stephens State Forest- Whitebreast Unit  Date: 9/15/2016  Project No.  
  450th Street Pond Repair  County:   LUCAS  Time: 3:00 p.m.  16-05-59-01

 

 
1
2
3
Estimated Cost: $20,500.00
Contractor: 
Dingman Const.Savage Dirt Works, LLCNagle Land Tiling Inc
Funding Source: 100% REAP OS Acquisition & Development, 1265 240th St
48499 Hy-Vee Rd
1326 230th St
Creston IA  50801Chariton IA  50049Garwin IA  50632
Plan Sets Requested: 0
Quantities
641-247-1431641-203-2357641-751-8614
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
180'x30" SMP with two diaphragms1L.S.$4,050.00$4,050.00 $7,900.00$7,900.00 $6,200.00$6,200.00 
2Remove Cable Rail1L.S.$540.00$540.00 $250.00$250.00 $3,500.00$3,500.00 
3Clearing & Grubbing1L.S.$3,500.00$3,500.00 $1,845.00$1,845.00 $8,500.00$8,500.00 
4Seeding1L.S.$3,150.00$3,150.00 $1,000.00$1,000.00 $3,500.00$3,500.00 
5Removal of Existing CMP1L.S.$560.00$560.00 $500.00$500.00 $8,500.00$8,500.00 
6Provide & Compact Fill Dirt1L.S.$9,300.00$9,300.00 $10,000.00$10,000.00 $10,500.00$10,500.00 
7Mobilization1L.S.$2,100.00$2,100.00 $1,500.00$1,500.00 $4,000.00$4,000.00 
8Traffic Control1L.S.$1,000.00$1,000.00 $2,000.00$2,000.00 $3,000.00$3,000.00 
      $24,200.00  $24,995.00  $47,700.00 
 



 