| Bids For: | Location: | Honey Creek Resort SP | Date: 5/21/2015 | Project No. |
| Entrance Portals | County: | MARION | Time: 11:00 a.m. | 15-05-63-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $149,000.00 | Contractor: | Hartland Bobcat Services LLC | Vieco Dev. & Construction Co. Inc. | ||||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 19561 205th Avenue | 5180 SE 70th Rd | |||||||||||
| Centerville IA 52544 | Saint Joseph MO 64507 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 641-895-2127 | 816-232-9044 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION | 1 | L.S. | $6,000.00 | $6,000.00 | $8,000.00 | $8,000.00 | $0.00 | |||||
| 2 | GRADING | 1 | L.S. | $1,000.00 | $1,000.00 | $3,250.00 | $3,250.00 | $0.00 | |||||
| 3 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $1,500.00 | $1,500.00 | $3,400.00 | $3,400.00 | $0.00 | |||||
| 4 | ELECTRIC | 1 | L.S. | $3,150.00 | $3,150.00 | $9,800.00 | $9,800.00 | $0.00 | |||||
| 5 | CONSTRUCTION STAKING | 1 | L.S. | $1,874.25 | $1,874.25 | $2,200.00 | $2,200.00 | $0.00 | |||||
| 6 | PORTAL BLOCK "A" | 5 | Each | $7,884.20 | $39,421.00 | $5,300.00 | $26,500.00 | $0.00 | |||||
| 7 | PORTAL BLOCK "B" | 2 | Each | $18,313.15 | $36,626.30 | $15,400.00 | $30,800.00 | $0.00 | |||||
| 8 | 19'-0" ENTRANCE PORTAL | 1 | L.S. | $88,285.00 | $88,285.00 | $161,000.00 | $161,000.00 | $0.00 | |||||
| $177,856.55 | $244,950.00 | $0.00 | |||||||||||
| Alternate | |||||||||||||
| 9 | 16'-0" ENTRANCE PORTAL | 1 | L.S. | $75,246.34 | $75,246.34 | $146,200.00 | $146,200.00 | $0.00 | |||||
| Alternate | |||||||||||||
| 10 | 13'-0" ENTRANCE PORTAL | 1 | L.S. | $56,390.78 | $56,390.78 | $134,400.00 | $134,400.00 | $0.00 | |||||
| $309,493.67 | $525,550.00 | $0.00 | |||||||||||