IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Rock Creek State Park | Date: 6/18/2015 | Project No. |
| Boat Ramp Replacement | County: | JASPER | Time: 3:00 p.m. | 15-05-50-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $49,772.00 | Contractor: | Strand Excavating Inc | Boulder Contracting, LLC | Cushman Excavation | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 13895 Hwy 6E | 25789 N Ave | 1308 216th PL | ||||||||||
| Grinnell IA 50112 | Grundy Center IA 50638 | Harvey IA 50119 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-498-7373 | 319-269-8680 | 641-891-4728 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $4,000.00 | $4,000.00 | $5,000.00 | $5,000.00 | $6,000.00 | $6,000.00 | ||||
| 2 | Traffic Control | 1 | L.S. | $465.00 | $465.00 | $1,000.00 | $1,000.00 | $3,000.00 | $3,000.00 | ||||
| 3 | Construction Survey | 1 | L.S. | $1,600.00 | $1,600.00 | $1,250.00 | $1,250.00 | $3,000.00 | $3,000.00 | ||||
| 4 | Erosion Control | 1 | L.S. | $1,350.00 | $1,350.00 | $2,500.00 | $2,500.00 | $2,000.00 | $2,000.00 | ||||
| 5 | Subgrade Preparation | 250 | S.Y. | $4.50 | $1,125.00 | $15.00 | $3,750.00 | $20.00 | $5,000.00 | ||||
| 6 | Stone Base | 64 | Tons | $22.00 | $1,408.00 | $50.00 | $3,200.00 | $46.87 | $2,999.68 | ||||
| 7 | Macadam | 24 | Tons | $45.00 | $1,080.00 | $55.00 | $1,320.00 | $137.50 | $3,300.00 | ||||
| 8 | Class D Revetment | 16 | Tons | $65.00 | $1,040.00 | $65.00 | $1,040.00 | $222.50 | $3,560.00 | ||||
| 9 | IDOT Engineering Fabric | 232 | S.Y. | $3.00 | $696.00 | $3.50 | $812.00 | $4.31 | $999.92 | ||||
| 10 | Grooved Boat Ramp | 165 | S.Y. | $120.00 | $19,800.00 | $90.00 | $14,850.00 | $173.97 | $28,705.05 | ||||
| 11 | PCC Pavement | 18 | S.Y. | $78.00 | $1,404.00 | $90.00 | $1,620.00 | $12.00 | $216.00 | ||||
| 12 | Gangway Approach/Landing (PCC w/ Reinforcing) | 4 | C.Y. | $469.00 | $1,876.00 | $500.00 | $2,000.00 | $950.00 | $3,800.00 | ||||
| 13 | Remove Existing Ramp Per Plans | 1 | L.S. | $1,112.00 | $1,112.00 | $7,500.00 | $7,500.00 | $9,500.00 | $9,500.00 | ||||
| 14 | Topsoil: Strip, Stockpile, & Respread (4") | 8 | C.Y. | $80.00 | $640.00 | $95.00 | $760.00 | $187.50 | $1,500.00 | ||||
| 15 | Seed, Mulch, & Fertilize - IDOT Urban Seeding | 65 | S.Y. | $17.00 | $1,105.00 | $50.00 | $3,250.00 | $30.76 | $1,999.40 | ||||
| 16 | ACB Revetment and Anchors | 240 | S.F. | $30.00 | $7,200.00 | $30.00 | $7,200.00 | $43.75 | $10,500.00 | ||||
| $45,901.00 | $57,052.00 | $86,080.05 | |||||||||||
12/22/2025