IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Box Car Access | Date: 3/19/2015 | Project No. |
Roadway Reconstruction | County: | MARION | Time: 11:00 A.M. | 15-05-63-03 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $127,000.00 | Contractor: | Savage Dirt Works LLC | RW Excavating & Dozing | H & H Construction & Development LLC | |||||||||
Funding Source: 100% Marine Fuel Tax, | 48499 Hy-Vee Rd | 13293 S 88th Ave W | 60559 Hwy 64 | ||||||||||
Chariton IA 50049 | Prairie City IA 50228 | Sabula IA 52070 | |||||||||||
Plan Sets Requested: 7 | Quantities | 641-203-2357 | 515-994-2648 | 563-357-1849 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization & Miscellaneous | 1 | L.S. | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 | $21,500.00 | $21,500.00 | ||||
2 | Traffic Control / Signage | 1 | L.S. | $700.00 | $700.00 | $1,000.00 | $1,000.00 | $1,250.00 | $1,250.00 | ||||
3 | Construction Survey | 1 | L.S. | $4,800.00 | $4,800.00 | $3,000.00 | $3,000.00 | $5,000.00 | $5,000.00 | ||||
4 | Excavation | 3000 | C.Y. | $5.00 | $15,000.00 | $2.60 | $7,800.00 | $14.86 | $44,580.00 | ||||
5 | Erosion Control | 1 | L.S. | $2,500.00 | $2,500.00 | $8,000.00 | $8,000.00 | $12,000.00 | $12,000.00 | ||||
6 | Subgrade Preparation (+2' on either side of granular surfacing) | 7400 | S.Y. | $2.00 | $14,800.00 | $1.23 | $9,102.00 | $0.30 | $2,220.00 | ||||
7 | Erosion Stone | 1500 | Tons | $20.30 | $30,450.00 | $22.50 | $33,750.00 | $26.30 | $39,450.00 | ||||
8 | Granular Surfacing | 1900 | Tons | $17.05 | $32,395.00 | $19.20 | $36,480.00 | $23.55 | $44,745.00 | ||||
9 | Topsoil: Strip, Stockpile & Respread (4") | 450 | C.Y. | $7.50 | $3,375.00 | $4.50 | $2,025.00 | $5.50 | $2,475.00 | ||||
10 | Seeding - Stabilization Crop | 4000 | S.Y. | $0.625 | $2,500.00 | $1.00 | $4,000.00 | $0.87 | $3,480.00 | ||||
$111,520.00 | $115,157.00 | $176,700.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $127,000.00 | Contractor: | Kevin Kent Construction | Sandstone Management LTD | TK Concrete Inc | |||||||||
Funding Source: 100% Marine Fuel Tax, | 15157 US Hwy 34 | 15 School St | 1608 Fifield Rd | ||||||||||
Lucas IA 50151 | Carlisle IA 50047 | Pella IA 50219 | |||||||||||
Plan Sets Requested: 7 | Quantities | 641-766-6126 | (515) 989-0557 | 641-628-4590 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization & Miscellaneous | 1 | L.S. | $10,000.00 | $10,000.00 | $6,096.00 | $6,096.00 | $90,000.00 | $90,000.00 | ||||
2 | Traffic Control / Signage | 1 | L.S. | $1,000.00 | $1,000.00 | $1,524.00 | $1,524.00 | $5,000.00 | $5,000.00 | ||||
3 | Construction Survey | 1 | L.S. | $7,500.00 | $7,500.00 | $8,385.00 | $8,385.00 | $10,000.00 | $10,000.00 | ||||
4 | Excavation | 3000 | C.Y. | $18.00 | $54,000.00 | $15.31 | $45,930.00 | $20.00 | $60,000.00 | ||||
5 | Erosion Control | 1 | L.S. | $7,800.00 | $7,800.00 | $8,723.00 | $8,723.00 | $10,000.00 | $10,000.00 | ||||
6 | Subgrade Preparation (+2' on either side of granular surfacing) | 7400 | S.Y. | $2.00 | $14,800.00 | $1.19 | $8,806.00 | $2.75 | $20,350.00 | ||||
7 | Erosion Stone | 1500 | Tons | $30.00 | $45,000.00 | $30.48 | $45,720.00 | $32.50 | $48,750.00 | ||||
8 | Granular Surfacing | 1900 | Tons | $21.25 | $40,375.00 | $23.37 | $44,403.00 | $30.00 | $57,000.00 | ||||
9 | Topsoil: Strip, Stockpile & Respread (4") | 450 | C.Y. | $10.00 | $4,500.00 | $38.68 | $17,406.00 | $22.50 | $10,125.00 | ||||
10 | Seeding - Stabilization Crop | 4000 | S.Y. | $1.00 | $4,000.00 | $1.02 | $4,080.00 | $1.10 | $4,400.00 | ||||
$188,975.00 | $191,073.00 | $315,625.00 | |||||||||||
5/3/2024