IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Elk Rock State Park  Date: 6/18/2015  Project No.  
  Shoreline Armoring  County:   MARION  Time: 11:00 A.M.  15-05-63-02

 

 
1
2
3
Estimated Cost: $293,865.00
Contractor: 
TK Concrete IncStrand Excavating Inc.Hammes Bulldozing Inc.
Funding Source: 100% Marine Fuel Tax, 1608 Fifield Rd
PO Box 111
13895 Highway 6 E
PO Box 109
Pella IA  50219Grinnell IA  50112Sigourney IA  52591
Plan Sets Requested: 5
Quantities
641-628-4590641-498-7373641-660-1610
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$10,000.00$10,000.00 $17,000.00$17,000.00 $11,470.00$11,470.00 
2Bank Shaping1L.S.$5,000.00$5,000.00 $5,500.00$5,500.00 $3,000.00$3,000.00 
3Class 'E' Revetment4400Tons$39.75$174,900.00 $41.50$182,600.00 $45.95$202,180.00 
4Bedding Stone1500Tons$21.00$31,500.00 $21.40$32,100.00 $19.90$29,850.00 
5Seeding & Site Restoration1L.S.$6,500.00$6,500.00 $11,000.00$11,000.00 $3,000.00$3,000.00 
      $227,900.00  $248,200.00  $249,500.00 
 
 
4
5
6
Estimated Cost: $293,865.00
Contractor: 
Cole Construction Company IncRW Excavating & DozingLegacy Corporation of Illinois
Funding Source: 100% Marine Fuel Tax, 24100 Queen Ave
13293 S. 88th Avenue W
16322 Barstow Rd
Keosauqua IA  525658329Prairie City IA  50228East Moline IL  61244
Plan Sets Requested: 5
Quantities
319-592-3103515-994-2648309-314-4588
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$7,500.00$7,500.00 $5,000.00$5,000.00 $15,000.00$15,000.00 
2Bank Shaping1L.S.$7,500.00$7,500.00 $2,000.00$2,000.00 $10,000.00$10,000.00 
3Class 'E' Revetment4400Tons$47.50$209,000.00 $53.95$237,380.00 $50.00$220,000.00 
4Bedding Stone1500Tons$23.90$35,850.00 $23.85$35,775.00 $35.00$52,500.00 
5Seeding & Site Restoration1L.S.$3,000.00$3,000.00 $1,500.00$1,500.00 $5,000.00$5,000.00 
      $262,850.00  $281,655.00  $302,500.00 
 
7
8
9
Estimated Cost: $293,865.00
Contractor: 
Niewohner Construction Inc.Superior Seawalls & Docks
Funding Source: 100% Marine Fuel Tax, 309 East Iowa Avenue
11900 315th St Court West

Onawa IA  51040Illinoijs City IL  61259  
Plan Sets Requested: 5
Quantities
712-423-3805877-875-2463
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$15,000.00$15,000.00 $13,390.00$13,390.00 $0.00 
2Bank Shaping1L.S.$2,000.00$2,000.00 $14,000.00$14,000.00 $0.00 
3Class 'E' Revetment4400Tons$58.95$259,380.00 $60.00$264,000.00 $0.00 
4Bedding Stone1500Tons$22.90$34,350.00 $35.80$53,700.00 $0.00 
5Seeding & Site Restoration1L.S.$3,000.00$3,000.00 $10,000.00$10,000.00 $0.00 
      $313,730.00  $355,090.00  $0.00 
 


The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low.


TK Concrete Inc, Pella, IA
 

DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

4/28/2024