 Bids For:  Location:   Black Hawk State Park  Date: 4/16/2015  Project No.  
  Water Patrol Office Sewer Repair  County:   SAC  Time: 3:00 p.m.  15-01-81-02

 

 
1
2
3
Estimated Cost: $7,500.00
Contractor: 
Jeppesen Gravel
Funding Source: 100% Marine Fuel Tax, 719 8th St


Sibley IA  51249    
Plan Sets Requested: 0
Quantities
712-461-0630
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Demolition and Removal of Existing Sanitary Waste Line (Appox 215')1L.S.$1,075.00$1,075.00 $0.00 $0.00 
2Tree Clearing, Grubbing, and Removal3Each$300.00$900.00 $0.00 $0.00 
34" Sanitary Waste Line (PVC SDR 23.5)215L.F.$5.00$1,075.00 $0.00 $0.00 
4Service Wye, (Connect to Existing Sewer)1Each$250.00$250.00 $0.00 $0.00 
5Clean Out2Each$150.00$300.00 $0.00 $0.00 
6Site Restoration1L.S.$1,000.00$1,000.00 $0.00 $0.00 
7Mobilization1L.S.$2,000.00$2,000.00 $0.00 $0.00 
      $6,600.00  $0.00  $0.00 
 



 