IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Other | Date: 6/11/2015 | Project No. |
| New river access with parking | County: | MILLS | Time: 3:00 p.m. | 15-04-65-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $22,400.00 | Contractor: | Hymbaugh Construction | Carley Construction LLC | ||||||||||
| Funding Source: 100% Marine Fuel Tax, | 821 Quiet Harbor | PO Box 2025 | |||||||||||
| Creston IA 50801 | Council Bluffs IA 51502 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 641-340-0232 | 712-256-5818 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Earthwork | 1 | L.S. | $5,000.00 | $5,000.00 | $12,000.00 | $12,000.00 | $0.00 | |||||
| 2 | Clearing & Grubbing | 1 | L.S. | $5,000.00 | $5,000.00 | $9,500.00 | $9,500.00 | $0.00 | |||||
| 3 | Class "E" Riprap | 196 | Tons | $80.00 | $15,680.00 | $75.00 | $14,700.00 | $0.00 | |||||
| 4 | C-4 Concrete Ramp, 5" Thick | 367 | S.F. | $8.00 | $2,936.00 | $18.50 | $6,789.50 | $0.00 | |||||
| 5 | Class "A" Crushed Stone | 110 | Tons | $40.00 | $4,400.00 | $38.75 | $4,262.50 | $0.00 | |||||
| 6 | Seeding, Fertilizer & Mulch | 1 | L.S. | $2,000.00 | $2,000.00 | $2,800.00 | $2,800.00 | $0.00 | |||||
| $35,016.00 | $50,052.00 | $0.00 | |||||||||||