IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lost Grove Lake W.M.A. | Date: 5/21/2015 | Project No. |
| Vaults | County: | SCOTT | Time: 3:00 p.m. | 15-06-82-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $84,000.00 | Contractor: | Triple B Construction Corporation | Valley Construction Company | Boulder Contracting, LLC | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 2272 Spicer Ave | 3610 78th Ave West | 25789 N Ave | ||||||||||
| Wilton IA 52778 | Rock Island IL 61201 | Grundy Center IA 50638 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 319-631-0320 | 309-787-0292 | 319-269-8680 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | SITE WORK | 1 | L.S. | $8,000.00 | $8,000.00 | $11,001.50 | $11,001.50 | $1,500.00 | $1,500.00 | ||||
| 2 | HC-IOWA DNR - RIGHT ENTRY PIT | 1 | Each | $30,840.00 | $30,840.00 | $32,900.00 | $32,900.00 | $28,000.00 | $28,000.00 | ||||
| 3 | HC-IOWA DNR - DOUBLE PIT | 1 | $44,350.00 | $44,350.00 | $46,300.00 | $46,300.00 | $39,500.00 | $39,500.00 | |||||
| 4 | CLASS "A' CRUSHED STONE | 5 | Tons | $50.00 | $250.00 | $180.00 | $900.00 | $50.00 | $250.00 | ||||
| 5 | SIDEWALK, PCC, 6" | 17 | S.Y. | $60.00 | $1,020.00 | $122.00 | $2,074.00 | $65.00 | $1,105.00 | ||||
| 6 | SIGNING | 1 | Each | $1,000.00 | $1,000.00 | $475.00 | $475.00 | $350.00 | $350.00 | ||||
| 7 | EROSION CONTROL | 233 | L.F. | $5.00 | $1,165.00 | $2.50 | $582.50 | $750.00 | $174,750.00 | ||||
| 8 | PAINTED PAVEMENT MARKINGS, WATERBORNE/SOLVENT | 1 | L.S. | $550.00 | $550.00 | $400.00 | $400.00 | $500.00 | $500.00 | ||||
| 9 | DETECTABLE WARNING PANEL | 24 | S.F. | $20.00 | $480.00 | $31.00 | $744.00 | $35.00 | $840.00 | ||||
| 10 | CONSTRUCTION STAKING | 1 | L.S. | $500.00 | $500.00 | $900.00 | $900.00 | $800.00 | $800.00 | ||||
| 11 | MOBILIZATION | 1 | L.S. | $2,000.00 | $2,000.00 | $7,500.00 | $7,500.00 | $2,250.00 | $2,250.00 | ||||
| $90,155.00 | $103,777.00 | $249,845.00 | |||||||||||