IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Orleans  Date: 12/22/2016  Project No.  
  Beach Restroom & Boat Ramp Improvements  County:   DICKINSON  Time: 11:00 a.m.  15-01-30-04

 

 
1
2
3
Estimated Cost: $249,000.00
Contractor: 
Diamond Concrete & Construction, Inc.Wilcon Construction, Inc
Funding Source: 100% Marine Fuel Tax, 2360 15th St
1512 7th Ave S

Spirit Lake IA  51360St James MN  56081  
Plan Sets Requested: 3
Quantities
712-336-9062507-375-5464
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1DEMOLITION1L.S.$12,758.00$12,758.00 $8,100.00$8,100.00 $0.00 
2CLEARING AND GRUBBING1L.S.$3,600.00$3,600.00 $3,357.00$3,357.00 $0.00 
3SITE WORK AND UTILITY CONNECTIONS1L.S.$9,235.00$9,235.00 $36,049.00$36,049.00 $0.00 
4GROUP MODULAR PRECAST CONCRETE RESTROOM, COMPLETE1Each$142,912.00$142,912.00 $180,724.00$180,724.00 $0.00 
5DRAIN-DOWN PIT1L.S.$3,962.00$3,962.00 $6,947.00$6,947.00 $0.00 
6EROSION CONTROL340L.F.$4.00$1,360.00 $6.00$2,040.00 $0.00 
7CLASS "A" CRUSHED STONE178Tons$43.31$7,709.18 $56.00$9,968.00 $0.00 
8MACADAM STONE77Tons$43.90$3,380.30 $49.00$3,773.00 $0.00 
93/8" MINUS CRUSHED STONE28Tons$25.96$726.88 $80.00$2,240.00 $0.00 
10ENGINEERING FABRIC272S.Y.$4.50$1,224.00 $7.00$1,904.00 $0.00 
11PAVING, P.C. CONCRETE, 6"161S.Y.$55.00$8,855.00 $87.00$14,007.00 $0.00 
12WATER MAIN, 2" COPPER190L.F.$96.52$18,338.80 $77.00$14,630.00 $0.00 
13ELECTRICAL SERVICE1L.S.$5,200.00$5,200.00 $12,524.00$12,524.00 $0.00 
14SIDEWALK, PCC, 5"195S.Y.$49.00$9,555.00 $89.00$17,355.00 $0.00 
15FURNISH AND INSTALL LIGHT FIXTURE2Each$1,167.00$2,334.00 $1,640.00$3,280.00 $0.00 
16LIGHT POLE AND BASE, COMPLETE2Each$1,037.14$2,074.28 $2,319.00$4,638.00 $0.00 
17FURNISH AND INSTALL ELECTRIC METER1Each$550.00$550.00 $2,780.00$2,780.00 $0.00 
18RETAINING WALL CURB, 6"1L.S.$1,265.00$1,265.00 $1,647.00$1,647.00 $0.00 
19DETECTABLE WARNING PANEL12L.F.$58.00$696.00 $125.00$1,500.00 $0.00 
20REMOVAL OF POWER POLE AND ELECTRICAL BOX1Each$250.00$250.00 $1,415.00$1,415.00 $0.00 
21REMOVAL OF LIGHT POLE1Each$250.00$250.00 $1,088.00$1,088.00 $0.00 
22REMOVAL OF ELECTRICAL OUTLET1Each$200.00$200.00 $1,056.00$1,056.00 $0.00 
23REMOVAL OF PAVEMENT55S.Y.$25.08$1,379.40 $46.00$2,530.00 $0.00 
24REMOVAL OF RAIL56L.F.$8.00$448.00 $21.00$1,176.00 $0.00 
25RAIL, STEEL TUBE, GALVANIZED56L.F.$105.25$5,894.00 $115.00$6,440.00 $0.00 
26EXTERIOR SHOWER, COMPLETE1L.S.$7,500.00$7,500.00 $9,964.00$9,964.00 $0.00 
27CONSTRUCTION STAKING1L.S.$1,200.00$1,200.00 $4,383.00$4,383.00 $0.00 
28MOBILIZATION1L.S.$4,000.00$4,000.00 $6,113.00$6,113.00 $0.00 
      $256,856.84  $361,628.00  $0.00 
 



 

9/28/2024