IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Black Hawk Lake State Park  Date: 1/22/2015  Project No.  
  Boat Storage Addition  County:   SAC  Time: 11:00 a.m.  14-01-81-03

 

 
1
2
3
Estimated Cost: $106,000.00
Contractor: 
Larry Elwood Construction Inc
Funding Source: 50% Federal-Boat Safety (Coast Guard), 50% Marine Fuel Tax, 2401 South Federal Ave


Mason City IA  50401    
Plan Sets Requested: 4
Quantities
641-423-3261
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1CLEARING AND GRUBBING1L.S.$7,722.00$7,722.00 $0.00 $0.00 
2ELECTRICAL DEMOLITION, POLE & METER1L.S.$448.00$448.00 $0.00 $0.00 
3NEW ELECTRICAL WORK1L.S.$11,581.00$11,581.00 $0.00 $0.00 
4FRONT CONCRETE APRON1L.S.$2,500.00$2,500.00 $0.00 $0.00 
5NEW STORAGE ADDITION1L.S.$39,181.00$39,181.00 $0.00 $0.00 
6MOBILIZATION1L.S.$4,316.00$4,316.00 $0.00 $0.00 
7CONSTRUCTION STAKING1L.S.$1,120.00$1,120.00 $0.00 $0.00 
      $66,868.00  $0.00  $0.00 
 



 