IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Hooper Area | Date: 2/12/2015 | Project No. |
| Parking Lot Stabilization | County: | WARREN | Time: 3:00 p.m. | 15-05-91-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $23,977.00 | Contractor: | Haworth Land Construction | Savage Dirt Works, LLC | Boulder Contracting, LLC | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 12981 Quaker St | 48499 Hy-Vee Rd | 25789 N Ave | ||||||||||
| Indianola IA 50125 | Chariton IA 50049 | Grundy Center IA 50638 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 515-249-4747 | 641-203-2357 | 319-269-8680 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,020.00 | $1,020.00 | $1,500.00 | $1,500.00 | $5,000.00 | $5,000.00 | ||||
| 2 | TrueGrid | 8344.5 | S.F. | $2.13 | $17,773.785 | $2.55 | $21,278.475 | $3.00 | $25,033.50 | ||||
| 3 | Class "A" Crushed Stone | 75 | Tons | $24.50 | $1,837.50 | $20.00 | $1,500.00 | $40.00 | $3,000.00 | ||||
| $20,631.285 | $24,278.475 | $33,033.50 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $23,977.00 | Contractor: | Hymbaugh Construction | Gruss Construction LLC | Linhart Construction, Inc. | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 821 Quiet Harbor | 149 N 58th PL | 4949 South 66th Plaza | ||||||||||
| Creston IA 50801 | Cumming IA 50061 | Omaha NE 68117 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-340-0232 | 515-321-4115 | 402-339-6748 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $5,113.00 | $5,113.00 | $5,400.00 | $5,400.00 | ||||
| 2 | TrueGrid | 8344.5 | S.F. | $3.00 | $25,033.50 | $2.88 | $24,032.16 | $4.18 | $34,880.01 | ||||
| 3 | Class "A" Crushed Stone | 75 | Tons | $60.00 | $4,500.00 | $75.44 | $5,658.00 | $30.08 | $2,256.00 | ||||
| $34,533.50 | $34,803.16 | $42,536.01 | |||||||||||