IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Prairie Rose  Date: 2/26/2015  Project No.  
  Rock Chute Increase Storage  County:   SHELBY  Time: 3:00 p.m.  15-04-83-01

 

 
1
2
3
Estimated Cost: $46,000.00
Contractor: 
Joy Dirt ConstructionLamb TilingFaas Construction & Excavating
Funding Source: 100% Lake Restoration, 202 State St
2751 Marion Ave
3407 V18 Rd
Cushing IA  51018-0185Greenfield IA  50849Brooklyn IA  52211
Plan Sets Requested: 0
Quantities
712-384-2700641-743-8312641-522-7082
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Sediment Removal & Disposal Areas 1 & 28000C.Y.$3.50$28,000.00 $4.25$34,000.00 $10.90$87,200.00 
2Site Restoration Areas 1 & 21L.S.$8,500.00$8,500.00 $7,000.00$7,000.00 $4,000.00$4,000.00 
      $36,500.00  $41,000.00  $91,200.00 
Alternate        
3Sediment Removal & Disposal Area 32000C.Y.$3.50$7,000.00 $4.25$8,500.00 $10.90$21,800.00 
Alternate        
4Site Restoration Area 31L.S.$2,930.00$2,930.00 $2,500.00$2,500.00 $6,000.00$6,000.00 
      $46,430.00  $52,000.00  $119,000.00 
 



 