IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Little Wall Lake | Date: 1/15/2015 | Project No. |
| Boat Ramp Extensions | County: | HAMILTON | Time: 3:00 p.m. | 15-02-40-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $18,000.00 | Contractor: | Boulder Contracting, LLC | Richards Construction Co., Inc. | Hymbaugh Construction | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 25789 N Ave | 2721 Sierra Ave | 821 Quiet Harbor | ||||||||||
| Grundy Center IA 50638 | Sac City IA 50583 | Creston IA 50801 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 319-269-8680 | 712-662-4421 | 641-340-0232 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,500.00 | $3,500.00 | $2,500.00 | $2,500.00 | $3,000.00 | $3,000.00 | ||||
| 2 | Sub-Grade Preparation | 1 | L.S. | $1,500.00 | $1,500.00 | $3,000.00 | $3,000.00 | $1,100.00 | $1,100.00 | ||||
| 3 | Armorflex Articulating Concrete Block Revetment System | 384 | S.F. | $27.80 | $10,675.20 | $30.00 | $11,520.00 | $50.00 | $19,200.00 | ||||
| 4 | Furnish & Install Revetment Backfill (Class “A”) | 8 | Tons | $50.00 | $400.00 | $100.00 | $800.00 | $200.00 | $1,600.00 | ||||
| $16,075.20 | $17,820.00 | $24,900.00 | |||||||||||
12/21/2025