IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Pine Lake | Date: 7/23/2015 | Project No. |
| Storage Building | County: | HARDIN | Time: 11:00 A.M. | 15-02-42-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $232,790.00 | Contractor: | Larry Elwood Construction | Hymbaugh Construction | King Construction Inc. | |||||||||
| Funding Source: 67% Infrastructure 2015, 33% Marine Fuel Tax, | 2401 S Federal | 821 Quiet Harbor | 1205 N. Oak St | ||||||||||
| Mason City IA 50401 | Creston IA 50801 | Iowa Falls IA 50126 | |||||||||||
| Plan Sets Requested: 5 | Quantities | 641-423-3261 | 641-340-0232 | 641-648-5464 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | CLEARING AND GRUBBING | 1 | L.S. | $6,105.00 | $6,105.00 | $5,000.00 | $5,000.00 | $6,315.00 | $6,315.00 | ||||
| 2 | GRADING | 1 | L.S. | $21,608.93 | $21,608.93 | $20,000.00 | $20,000.00 | $26,315.00 | $26,315.00 | ||||
| 3 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $5,550.00 | $5,550.00 | $2,000.00 | $2,000.00 | $5,260.00 | $5,260.00 | ||||
| 4 | 8" FILTER SOCK | 230 | L.F. | $3.05 | $701.50 | $10.00 | $2,300.00 | $3.20 | $736.00 | ||||
| 5 | DRAINING PIPE | 1 | L.S. | $1,998.00 | $1,998.00 | $2,000.00 | $2,000.00 | $2,635.00 | $2,635.00 | ||||
| 6 | CLASS "A" CRUSHED STONE | 20 | Tons | $30.53 | $610.60 | $50.00 | $1,000.00 | $26.50 | $530.00 | ||||
| 7 | FENCING RECONSTRUCTION | 1 | L.S. | $2,064.00 | $2,064.00 | $5,000.00 | $5,000.00 | $2,900.00 | $2,900.00 | ||||
| 8 | ELECTRICAL | 1 | L.S. | $16,527.90 | $16,527.90 | $20,000.00 | $20,000.00 | $21,000.00 | $21,000.00 | ||||
| 9 | NEW STORAGE BUILDING | 1 | L.S. | $130,765.08 | $130,765.08 | $158,600.00 | $158,600.00 | $174,800.00 | $174,800.00 | ||||
| 10 | MOBILIZATION | 1 | L.S. | $4,229.10 | $4,229.10 | $20,000.00 | $20,000.00 | $4,010.00 | $4,010.00 | ||||
| 11 | CONSTRUCTION STAKING | 1 | L.S. | $1,110.00 | $1,110.00 | $2,000.00 | $2,000.00 | $1,600.00 | $1,600.00 | ||||
| $191,270.11 | $237,900.00 | $246,101.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $232,790.00 | Contractor: | Larson Contracting | R H Grabau Construction Inc | OEL Construction Services Inc. | |||||||||
| Funding Source: 67% Infrastructure 2015, 33% Marine Fuel Tax, | 508 W Main St Box 68 | 871 "P" Ave PO Box | 21072 Y Avenue | ||||||||||
| Lake Mills IA 50450 | Boone IA 50036 | Steamboat Rock IA 50672 | |||||||||||
| Plan Sets Requested: 5 | Quantities | 641-592-5800 | (515) 432-6935 | 641-858-5090 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | CLEARING AND GRUBBING | 1 | L.S. | $6,779.00 | $6,779.00 | $10,000.00 | $10,000.00 | $6,632.00 | $6,632.00 | ||||
| 2 | GRADING | 1 | L.S. | $28,245.00 | $28,245.00 | $30,000.00 | $30,000.00 | $27,632.00 | $27,632.00 | ||||
| 3 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $5,649.00 | $5,649.00 | $2,000.00 | $2,000.00 | $7,792.00 | $7,792.00 | ||||
| 4 | 8" FILTER SOCK | 230 | L.F. | $3.40 | $782.00 | $4.35 | $1,000.50 | $3.30 | $759.00 | ||||
| 5 | DRAINING PIPE | 1 | L.S. | $3,304.00 | $3,304.00 | $3,000.00 | $3,000.00 | $2,763.00 | $2,763.00 | ||||
| 6 | CLASS "A" CRUSHED STONE | 20 | Tons | $28.25 | $565.00 | $50.00 | $1,000.00 | $28.00 | $560.00 | ||||
| 7 | FENCING RECONSTRUCTION | 1 | L.S. | $4,500.00 | $4,500.00 | $500.00 | $500.00 | $2,272.00 | $2,272.00 | ||||
| 8 | ELECTRICAL | 1 | L.S. | $20,085.00 | $20,085.00 | $20,000.00 | $20,000.00 | $21,221.00 | $21,221.00 | ||||
| 9 | NEW STORAGE BUILDING | 1 | L.S. | $169,996.00 | $169,996.00 | $170,703.50 | $170,703.50 | $190,297.00 | $190,297.00 | ||||
| 10 | MOBILIZATION | 1 | L.S. | $4,862.00 | $4,862.00 | $28,000.00 | $28,000.00 | $15,511.00 | $15,511.00 | ||||
| 11 | CONSTRUCTION STAKING | 1 | L.S. | $3,954.00 | $3,954.00 | $2,000.00 | $2,000.00 | $1,840.00 | $1,840.00 | ||||
| $248,721.00 | $268,204.00 | $277,279.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $232,790.00 | Contractor: | Smith-Gehrls Inc | |||||||||||
| Funding Source: 67% Infrastructure 2015, 33% Marine Fuel Tax, | 504 Lawler | ||||||||||||
| Iowa Falls IA 50126 | |||||||||||||
| Plan Sets Requested: 5 | Quantities | 641-648-4661 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | CLEARING AND GRUBBING | 1 | L.S. | $6,600.00 | $6,600.00 | $0.00 | $0.00 | ||||||
| 2 | GRADING | 1 | L.S. | $27,500.00 | $27,500.00 | $0.00 | $0.00 | ||||||
| 3 | SEEDING, FERTILIZING AND MULCHING | 1 | L.S. | $4,400.00 | $4,400.00 | $0.00 | $0.00 | ||||||
| 4 | 8" FILTER SOCK | 230 | L.F. | $3.26 | $749.80 | $0.00 | $0.00 | ||||||
| 5 | DRAINING PIPE | 1 | L.S. | $2,750.00 | $2,750.00 | $0.00 | $0.00 | ||||||
| 6 | CLASS "A" CRUSHED STONE | 20 | Tons | $30.00 | $600.00 | $0.00 | $0.00 | ||||||
| 7 | FENCING RECONSTRUCTION | 1 | L.S. | $4,400.00 | $4,400.00 | $0.00 | $0.00 | ||||||
| 8 | ELECTRICAL | 1 | L.S. | $17,500.00 | $17,500.00 | $0.00 | $0.00 | ||||||
| 9 | NEW STORAGE BUILDING | 1 | L.S. | $221,000.00 | $221,000.00 | $0.00 | $0.00 | ||||||
| 10 | MOBILIZATION | 1 | L.S. | $8,600.00 | $8,600.00 | $0.00 | $0.00 | ||||||
| 11 | CONSTRUCTION STAKING | 1 | L.S. | $900.00 | $900.00 | $0.00 | $0.00 | ||||||
| $294,999.80 | $0.00 | $0.00 | |||||||||||
Larson Contracting, Lake Mills, IA
Hymbaugh Construction, Creston, IA