IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Red Rock Wildlife Unit | Date: 11/16/2017 | Project No. |
Mud Creek Water Diversion Structure | County: | POLK | Time: 11:00 a.m. | 15-05-77-03 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $125,000.00 | Contractor: | Sterk Excavating Inc | Boulder Contractors LLC | Minturn Inc | |||||||||
Funding Source: 50% REAP Land Management, 50% Cash Donation, | 117 - 180th Ave | 25789 N. Avenue | 144 W. Front Street | ||||||||||
Otley IA 50214 | Grundy Center IA 50638 | Brooklyn IA 52211 | |||||||||||
Plan Sets Requested: 3 | Quantities | 641-416-0110 | 319-269-8680 | 641-455-0331 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $9,600.00 | $9,600.00 | $12,500.00 | $12,500.00 | $13,260.00 | $13,260.00 | ||||
2 | PZ22 Sheet Pile, 10' lengths | 953.33 | S.F. | $34.88 | $33,252.15 | $23.00 | $21,926.59 | $41.00 | $39,086.53 | ||||
3 | PZ22 Sheet Pile, 15' lengths | 1457.5 | S.F. | $34.88 | $50,837.60 | $23.00 | $33,522.50 | $32.00 | $46,640.00 | ||||
4 | PZ90, 10' length | 10 | L.F. | $35.00 | $350.00 | $90.00 | $900.00 | $74.00 | $740.00 | ||||
5 | PZ90, 15' length | 15 | L.F. | $33.33 | $499.95 | $90.00 | $1,350.00 | $61.00 | $915.00 | ||||
6 | PZ Joker, 10' length | 10 | L.F. | $65.00 | $650.00 | $90.00 | $900.00 | $100.00 | $1,000.00 | ||||
7 | PZ Joker, 20' length | 20 | L.F. | $60.00 | $1,200.00 | $90.00 | $1,800.00 | $100.00 | $2,000.00 | ||||
8 | PZ Bullhead, 20' length | 20 | L.F. | $60.00 | $1,200.00 | $90.00 | $1,800.00 | $100.00 | $2,000.00 | ||||
9 | 1" Tie-Back Rods | 2 | Each | $250.00 | $500.00 | $650.00 | $1,300.00 | $700.00 | $1,400.00 | ||||
10 | MC8x20 Wales | 48 | L.F. | $47.21 | $2,266.08 | $29.00 | $1,392.00 | $55.00 | $2,640.00 | ||||
11 | Stoplog & Plank Lockdown Devices | 1 | L.S. | $400.00 | $400.00 | $750.00 | $750.00 | $1,500.00 | $1,500.00 | ||||
12 | Install Owner-Supplied Stoplog Bay | 1 | L.S. | $1,000.00 | $1,000.00 | $900.00 | $900.00 | $600.00 | $600.00 | ||||
13 | Walk Plank Supports | 2 | Each | $150.00 | $300.00 | $2,300.00 | $4,600.00 | $1,350.00 | $2,700.00 | ||||
14 | 30"x22' Heavy Duty Walkway Plank | 1 | Each | $5,459.00 | $5,459.00 | $4,200.00 | $4,200.00 | $5,700.00 | $5,700.00 | ||||
15 | Ladder & Handles | 1 | L.S. | $150.00 | $150.00 | $1,500.00 | $1,500.00 | $335.00 | $335.00 | ||||
16 | Class "A" Crushed Stone | 35 | Tons | $21.42 | $749.70 | $51.00 | $1,785.00 | $38.50 | $1,347.50 | ||||
17 | Concrete, Iowa DOT C4 | 45 | C.Y. | $244.45 | $11,000.25 | $467.00 | $21,015.00 | $450.00 | $20,250.00 | ||||
18 | Clearing & Grubbing | 1 | L.S. | $200.00 | $200.00 | $1,500.00 | $1,500.00 | $100.00 | $100.00 | ||||
19 | Class "E" Riprap | 81 | Tons | $45.00 | $3,645.00 | $61.50 | $4,981.50 | $60.00 | $4,860.00 | ||||
20 | Move Existing Riprap | 1 | L.S. | $1,000.00 | $1,000.00 | $1,200.00 | $1,200.00 | $700.00 | $700.00 | ||||
21 | Engineering Fabric | 75 | S.Y. | $2.00 | $150.00 | $3.00 | $225.00 | $5.00 | $375.00 | ||||
$124,409.73 | $120,047.59 | $148,149.03 | |||||||||||
Alternate | |||||||||||||
22 | Macadam Stone | 338 | Tons | $21.15 | $7,148.70 | $31.00 | $10,478.00 | $34.40 | $11,627.20 | ||||
Alternate | |||||||||||||
23 | Jib Crane, Trolley, Hand Hoist | 1 | L.S. | $6,000.00 | $6,000.00 | $13,250.00 | $13,250.00 | $8,750.00 | $8,750.00 | ||||
$137,558.43 | $143,775.59 | $168,526.23 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $125,000.00 | Contractor: | Landwehr Construction Inc | Jensen Construction Co | RW EXCAVATING SOLUTIONS LC | |||||||||
Funding Source: 50% REAP Land Management, 50% Cash Donation, | 846 33rd Street South | 5550 NE 22nd St Box 3345 | 13293 S 88TH AVE W | ||||||||||
St Cloud MN 56302 | Des Moines IA 50313 | PRAIRIE CITY IA 50228 | |||||||||||
Plan Sets Requested: 3 | Quantities | 320-252-1494 | 515-266-5173 | 515-994-2648 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $26,000.00 | $26,000.00 | $18,000.00 | $18,000.00 | $25,000.00 | $25,000.00 | ||||
2 | PZ22 Sheet Pile, 10' lengths | 953.33 | S.F. | $30.00 | $28,599.90 | $21.00 | $20,019.93 | $34.88 | $33,252.15 | ||||
3 | PZ22 Sheet Pile, 15' lengths | 1457.5 | S.F. | $35.00 | $51,012.50 | $19.00 | $27,692.50 | $34.88 | $50,837.60 | ||||
4 | PZ90, 10' length | 10 | L.F. | $125.00 | $1,250.00 | $75.00 | $750.00 | $60.00 | $600.00 | ||||
5 | PZ90, 15' length | 15 | L.F. | $105.00 | $1,575.00 | $75.00 | $1,125.00 | $60.00 | $900.00 | ||||
6 | PZ Joker, 10' length | 10 | L.F. | $130.00 | $1,300.00 | $80.00 | $800.00 | $116.50 | $1,165.00 | ||||
7 | PZ Joker, 20' length | 20 | L.F. | $100.00 | $2,000.00 | $80.00 | $1,600.00 | $116.50 | $2,330.00 | ||||
8 | PZ Bullhead, 20' length | 20 | L.F. | $100.00 | $2,000.00 | $80.00 | $1,600.00 | $116.50 | $2,330.00 | ||||
9 | 1" Tie-Back Rods | 2 | Each | $850.00 | $1,700.00 | $950.00 | $1,900.00 | $400.00 | $800.00 | ||||
10 | MC8x20 Wales | 48 | L.F. | $78.00 | $3,744.00 | $95.00 | $4,560.00 | $45.34 | $2,176.32 | ||||
11 | Stoplog & Plank Lockdown Devices | 1 | L.S. | $2,200.00 | $2,200.00 | $4,000.00 | $4,000.00 | $1,000.00 | $1,000.00 | ||||
12 | Install Owner-Supplied Stoplog Bay | 1 | L.S. | $1,500.00 | $1,500.00 | $7,000.00 | $7,000.00 | $15,000.00 | $15,000.00 | ||||
13 | Walk Plank Supports | 2 | Each | $650.00 | $1,300.00 | $5,000.00 | $10,000.00 | $2,000.00 | $4,000.00 | ||||
14 | 30"x22' Heavy Duty Walkway Plank | 1 | Each | $3,000.00 | $3,000.00 | $9,000.00 | $9,000.00 | $5,000.00 | $5,000.00 | ||||
15 | Ladder & Handles | 1 | L.S. | $1,000.00 | $1,000.00 | $1,300.00 | $1,300.00 | $2,000.00 | $2,000.00 | ||||
16 | Class "A" Crushed Stone | 35 | Tons | $58.00 | $2,030.00 | $26.00 | $910.00 | $27.52 | $963.20 | ||||
17 | Concrete, Iowa DOT C4 | 45 | C.Y. | $330.00 | $14,850.00 | $1,025.00 | $46,125.00 | $500.00 | $22,500.00 | ||||
18 | Clearing & Grubbing | 1 | L.S. | $600.00 | $600.00 | $6,000.00 | $6,000.00 | $3,500.00 | $3,500.00 | ||||
19 | Class "E" Riprap | 81 | Tons | $73.00 | $5,913.00 | $55.00 | $4,455.00 | $62.40 | $5,054.40 | ||||
20 | Move Existing Riprap | 1 | L.S. | $2,000.00 | $2,000.00 | $4,500.00 | $4,500.00 | $5,000.00 | $5,000.00 | ||||
21 | Engineering Fabric | 75 | S.Y. | $6.00 | $450.00 | $10.00 | $750.00 | $4.00 | $300.00 | ||||
Alternate | |||||||||||||
22 | Macadam Stone | 338 | Tons | $34.00 | $11,492.00 | $25.00 | $8,450.00 | $32.00 | $10,816.00 | ||||
Alternate | |||||||||||||
23 | Jib Crane, Trolley, Hand Hoist | 1 | L.S. | $9,000.00 | $9,000.00 | $8,500.00 | $8,500.00 | $7,500.00 | $7,500.00 | ||||
$174,516.40 | $189,037.43 | $202,024.67 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $125,000.00 | Contractor: | Peterson Contractors Inc | |||||||||||
Funding Source: 50% REAP Land Management, 50% Cash Donation, | 104 Blackhawk St | ||||||||||||
Reinbeck IA 50669 | |||||||||||||
Plan Sets Requested: 3 | Quantities | 319-345-2713 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $45,000.00 | $45,000.00 | $0.00 | $0.00 | ||||||
2 | PZ22 Sheet Pile, 10' lengths | 953.33 | S.F. | $30.00 | $28,599.90 | $0.00 | $0.00 | ||||||
3 | PZ22 Sheet Pile, 15' lengths | 1457.5 | S.F. | $30.00 | $43,725.00 | $0.00 | $0.00 | ||||||
4 | PZ90, 10' length | 10 | L.F. | $75.00 | $750.00 | $0.00 | $0.00 | ||||||
5 | PZ90, 15' length | 15 | L.F. | $69.00 | $1,035.00 | $0.00 | $0.00 | ||||||
6 | PZ Joker, 10' length | 10 | L.F. | $80.00 | $800.00 | $0.00 | $0.00 | ||||||
7 | PZ Joker, 20' length | 20 | L.F. | $69.00 | $1,380.00 | $0.00 | $0.00 | ||||||
8 | PZ Bullhead, 20' length | 20 | L.F. | $69.00 | $1,380.00 | $0.00 | $0.00 | ||||||
9 | 1" Tie-Back Rods | 2 | Each | $265.00 | $530.00 | $0.00 | $0.00 | ||||||
10 | MC8x20 Wales | 48 | L.F. | $70.00 | $3,360.00 | $0.00 | $0.00 | ||||||
11 | Stoplog & Plank Lockdown Devices | 1 | L.S. | $5,460.00 | $5,460.00 | $0.00 | $0.00 | ||||||
12 | Install Owner-Supplied Stoplog Bay | 1 | L.S. | $5,075.00 | $5,075.00 | $0.00 | $0.00 | ||||||
13 | Walk Plank Supports | 2 | Each | $1,813.00 | $3,626.00 | $0.00 | $0.00 | ||||||
14 | 30"x22' Heavy Duty Walkway Plank | 1 | Each | $1,201.00 | $1,201.00 | $0.00 | $0.00 | ||||||
15 | Ladder & Handles | 1 | L.S. | $550.00 | $550.00 | $0.00 | $0.00 | ||||||
16 | Class "A" Crushed Stone | 35 | Tons | $63.00 | $2,205.00 | $0.00 | $0.00 | ||||||
17 | Concrete, Iowa DOT C4 | 45 | C.Y. | $946.00 | $42,570.00 | $0.00 | $0.00 | ||||||
18 | Clearing & Grubbing | 1 | L.S. | $3,500.00 | $3,500.00 | $0.00 | $0.00 | ||||||
19 | Class "E" Riprap | 81 | Tons | $38.00 | $3,078.00 | $0.00 | $0.00 | ||||||
20 | Move Existing Riprap | 1 | L.S. | $1,957.00 | $1,957.00 | $0.00 | $0.00 | ||||||
21 | Engineering Fabric | 75 | S.Y. | $10.00 | $750.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
22 | Macadam Stone | 338 | Tons | $36.00 | $12,168.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
23 | Jib Crane, Trolley, Hand Hoist | 1 | L.S. | $22,227.00 | $22,227.00 | $0.00 | $0.00 | ||||||
$230,926.90 | $0.00 | $0.00 | |||||||||||