IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Lake Wapello  Date: 9/18/2014  Project No.  
  Sanitary Sewer Lining  County:   DAVIS  Time: 11:00 am  15-05-26-02

 

 
1
2
3
Estimated Cost: $272,000.00
Contractor: 
VISU-SEWER Inc.Municipal Pipe Tool CoSAK Construction LLC
Funding Source: 100% Infrastructure 2015, W230N4855 Betker Dr
515 5th St
PO Box 398
864 Hoff Rd
Pewaukee WI  53072Hudson IA  50643O'Fallon MO  63366
Plan Sets Requested: 1
Quantities
262-695-2340(319) 988-4505636-385-1000
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$7,600.00$7,600.00 $5,300.00$5,300.00 $16,750.00$16,750.00 
2CIPP LINE SEWER PIPE, 8 INCH DIA3232L.F.$23.00$74,336.00 $37.50$121,200.00 $33.00$106,656.00 
3CIPP LINE SEWER PIPE, 6 INCH DIA533L.F.$25.00$13,325.00 $33.00$17,589.00 $44.00$23,452.00 
4POST IMPROVEMENT TELEVISING3765L.F.$1.00$3,765.00 $1.00$3,765.00 $1.00$3,765.00 
5DIG & REPLACE 4 INCH LATERALS WITH 4 INCH PVC SDR 35 PIPE757L.F.$48.50$36,714.50 $93.00$70,401.00 $110.75$83,837.75 
6MANHOLE CCCM INTERIOR LINING WITH EPOXY SEAL170L.F.$270.00$45,900.00 $242.00$41,140.00 $381.25$64,812.50 
7NEW CASTING FOR CCCM LINED MANHOLES17Each$860.00$14,620.00 $1,470.00$24,990.00 $1,562.50$26,562.50 
8SERVICE LATERAL RECONNECTION14Each$270.00$3,780.00 $100.00$1,400.00 $100.00$1,400.00 
9POINT REPAIR - 8 OR 6 INCH SEWER PIPE (Actual No. of pt. repairs to be determined in field by Engr. & pipe lining Contractor)10Each$4,850.00$48,500.00 $5,166.00$51,660.00 $6,150.00$61,500.00 
10PLUG 4 INCH SERVICE LATERAL1Each$275.00$275.00 $2,877.00$2,877.00 $3,425.00$3,425.00 
11SITE RESTORATION AND SEEDING1L.S.$5,500.00$5,500.00 $3,150.00$3,150.00 $5,000.00$5,000.00 
      $254,315.50  $343,472.00  $397,160.75 
 



 

5/1/2024