IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Fairport Recreation Area | Date: 8/20/2015 | Project No. |
| campground electric upgrade | County: | MUSCATINE | Time: 11:00 a.m. | 15-06-70-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $157,702.00 | Contractor: | Triple B Construction | Home Town Plumbing & Heating | Smith Seeding Inc | |||||||||
| Funding Source: 100% Infrastructure 2015, | 2272 Spicer Ave | 13606 118th Ave | 219 N 1st Street | ||||||||||
| Wilton IA 52778 | Davenport IA 52804 | Eldridge IA 52748 | |||||||||||
| Plan Sets Requested: 2 | Quantities | 563-299-2399 | (563) 381-4800 | 563-285-2604 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Demolition | 1 | L.S. | $2,500.00 | $2,500.00 | $6,405.00 | $6,405.00 | $7,000.00 | $7,000.00 | ||||
| 2 | 1-inch HDPE Pipe | 979 | L.F. | $16.00 | $15,664.00 | $14.65 | $14,342.35 | $13.00 | $12,727.00 | ||||
| 3 | 1.5-inch HDPE Pipe | 291 | L.F. | $18.00 | $5,238.00 | $20.20 | $5,878.20 | $13.00 | $3,783.00 | ||||
| 4 | Woodford Model S-3 Sanitary Yard Hydrants | 11 | Each | $2,200.00 | $24,200.00 | $1,958.00 | $21,538.00 | $2,000.00 | $22,000.00 | ||||
| 5 | 1x1x1 HDPE Tee | 5 | Each | $100.00 | $500.00 | $480.00 | $2,400.00 | $150.00 | $750.00 | ||||
| 6 | 1.5x1.5x1.5 HDPE Tee | 5 | Each | $200.00 | $1,000.00 | $525.00 | $2,625.00 | $150.00 | $750.00 | ||||
| 7 | 1.5x1 HDPE Reducers | 6 | Each | $100.00 | $600.00 | $330.00 | $1,980.00 | $150.00 | $900.00 | ||||
| 8 | 1.5-inch Curb Stop | 1 | Each | $650.00 | $650.00 | $525.00 | $525.00 | $900.00 | $900.00 | ||||
| 9 | 1-inch Watertight Cap | 1 | Each | $50.00 | $50.00 | $530.00 | $530.00 | $150.00 | $150.00 | ||||
| 10 | Disinfection | 1 | L.S. | $1,500.00 | $1,500.00 | $1,410.00 | $1,410.00 | $1,500.00 | $1,500.00 | ||||
| 11 | Electrical Improvements | 1 | L.S. | $82,475.00 | $82,475.00 | $101,300.00 | $101,300.00 | $100,000.00 | $100,000.00 | ||||
| 12 | Seeding, Fertilizing and Mulching | 1 | L.S. | $7,000.00 | $7,000.00 | $3,300.00 | $3,300.00 | $3,000.00 | $3,000.00 | ||||
| 13 | Traffic Control | 1 | L.S. | $1,000.00 | $1,000.00 | $1,100.00 | $1,100.00 | $1,500.00 | $1,500.00 | ||||
| 14 | Construction Survey Staking | 1 | L.S. | $5,000.00 | $5,000.00 | $4,410.00 | $4,410.00 | $4,500.00 | $4,500.00 | ||||
| 15 | Mobilization | 1 | L.S. | $13,000.00 | $13,000.00 | $9,430.00 | $9,430.00 | $19,000.00 | $19,000.00 | ||||
| $160,377.00 | $177,173.55 | $178,460.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $157,702.00 | Contractor: | Nelson Electric, Inc | Miller Trucking & Excav | ||||||||||
| Funding Source: 100% Infrastructure 2015, | 703 Clay Street | 3033 John Deere Rd | |||||||||||
| Muscatine IA 52761 | Silvis IL 61282 | ||||||||||||
| Plan Sets Requested: 2 | Quantities | 563-203-7319 | (309) 755-7644 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Demolition | 1 | L.S. | $2,000.00 | $2,000.00 | $15,000.00 | $15,000.00 | $0.00 | |||||
| 2 | 1-inch HDPE Pipe | 979 | L.F. | $10.00 | $9,790.00 | $35.00 | $34,265.00 | $0.00 | |||||
| 3 | 1.5-inch HDPE Pipe | 291 | L.F. | $10.25 | $2,982.75 | $40.00 | $11,640.00 | $0.00 | |||||
| 4 | Woodford Model S-3 Sanitary Yard Hydrants | 11 | Each | $1,500.00 | $16,500.00 | $1,800.00 | $19,800.00 | $0.00 | |||||
| 5 | 1x1x1 HDPE Tee | 5 | Each | $350.00 | $1,750.00 | $64.00 | $320.00 | $0.00 | |||||
| 6 | 1.5x1.5x1.5 HDPE Tee | 5 | Each | $350.00 | $1,750.00 | $72.00 | $360.00 | $0.00 | |||||
| 7 | 1.5x1 HDPE Reducers | 6 | Each | $36.00 | $216.00 | $69.00 | $414.00 | $0.00 | |||||
| 8 | 1.5-inch Curb Stop | 1 | Each | $1,500.00 | $1,500.00 | $470.00 | $470.00 | $0.00 | |||||
| 9 | 1-inch Watertight Cap | 1 | Each | $350.00 | $350.00 | $60.00 | $60.00 | $0.00 | |||||
| 10 | Disinfection | 1 | L.S. | $2,500.00 | $2,500.00 | $1,200.00 | $1,200.00 | $0.00 | |||||
| 11 | Electrical Improvements | 1 | L.S. | $129,000.00 | $129,000.00 | $115,000.00 | $115,000.00 | $0.00 | |||||
| 12 | Seeding, Fertilizing and Mulching | 1 | L.S. | $2,500.00 | $2,500.00 | $8,000.00 | $8,000.00 | $0.00 | |||||
| 13 | Traffic Control | 1 | L.S. | $200.00 | $200.00 | $1,400.00 | $1,400.00 | $0.00 | |||||
| 14 | Construction Survey Staking | 1 | L.S. | $1,500.00 | $1,500.00 | $4,800.00 | $4,800.00 | $0.00 | |||||
| 15 | Mobilization | 1 | L.S. | $15,896.25 | $15,896.25 | $20,000.00 | $20,000.00 | $0.00 | |||||
| $188,435.00 | $232,729.00 | $0.00 | |||||||||||