IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Sweet Marsh WMA | Date: 5/28/2015 | Project No. |
| PCC Observation Deck | County: | BREMER | Time: 3:00 p.m. | 14-03-09-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $15,000.00 | Contractor: | Lansing Brothers Construction Co. Inc. | Nate Moeller Const | Matt Construction Inc. | |||||||||
| Funding Source: 100% Federal-SWG, | 101 East 1st St PO Box 36 | 706 7th Ave SW | 203 Y Ave | ||||||||||
| Luxemburg IA 52056 | Tripoli IA 50676 | Sumner IA 50674 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-543-7360 | 319-882-3600 | 563-578-8418 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $2,500.00 | $2,500.00 | $500.00 | $500.00 | $2,000.00 | $2,000.00 | ||||
| 2 | Tree Removal | 27 | Units | $30.00 | $810.00 | $50.00 | $1,350.00 | $20.00 | $540.00 | ||||
| 3 | Site Grading | 1 | L.S. | $1,000.00 | $1,000.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | ||||
| 4 | Limestone Fill Material | 400 | Tons | $10.00 | $4,000.00 | $10.50 | $4,200.00 | $11.00 | $4,400.00 | ||||
| 5 | PC Deck Concrete, 6" Class C, Fiber Reinforced | 573 | S.F. | $8.00 | $4,584.00 | $8.25 | $4,727.25 | $7.00 | $4,011.00 | ||||
| 6 | Top Soil, Furnish & Spread | 55 | C.Y. | $20.00 | $1,100.00 | $40.00 | $2,200.00 | $32.00 | $1,760.00 | ||||
| 7 | Cr. Stone Surfacing | 24 | Tons | $25.00 | $600.00 | $15.00 | $360.00 | $23.00 | $552.00 | ||||
| 8 | Stabilizing Crop Seeding | 1 | L.S. | $1,000.00 | $1,000.00 | $1,200.00 | $1,200.00 | $2,500.00 | $2,500.00 | ||||
| $15,594.00 | $17,037.25 | $18,263.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $15,000.00 | Contractor: | Boulder Contracting, LLC | Jonas Raber Construction LLC | Bacon Concrete, LLC | |||||||||
| Funding Source: 100% Federal-SWG, | 25789 N Ave | 1296 145th St | 370 N Bancroft St | ||||||||||
| Grundy Center IA 50638 | Fairbank IA 50629 | Postville IA 52162-0188 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 319-269-8680 | 319-551-9346 | 563-864-7602 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,500.00 | $1,500.00 | $1,250.00 | $1,250.00 | $1,800.00 | $1,800.00 | ||||
| 2 | Tree Removal | 27 | Units | $40.00 | $1,080.00 | $20.00 | $540.00 | $100.00 | $2,700.00 | ||||
| 3 | Site Grading | 1 | L.S. | $2,500.00 | $2,500.00 | $3,650.00 | $3,650.00 | $2,000.00 | $2,000.00 | ||||
| 4 | Limestone Fill Material | 400 | Tons | $15.00 | $6,000.00 | $10.50 | $4,200.00 | $18.50 | $7,400.00 | ||||
| 5 | PC Deck Concrete, 6" Class C, Fiber Reinforced | 573 | S.F. | $6.00 | $3,438.00 | $14.29 | $8,188.17 | $7.20 | $4,125.60 | ||||
| 6 | Top Soil, Furnish & Spread | 55 | C.Y. | $50.00 | $2,750.00 | $19.00 | $1,045.00 | $27.50 | $1,512.50 | ||||
| 7 | Cr. Stone Surfacing | 24 | Tons | $50.00 | $1,200.00 | $14.25 | $342.00 | $20.00 | $480.00 | ||||
| 8 | Stabilizing Crop Seeding | 1 | L.S. | $1,000.00 | $1,000.00 | $500.00 | $500.00 | $1,000.00 | $1,000.00 | ||||
| $19,468.00 | $19,715.17 | $21,018.10 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $15,000.00 | Contractor: | Chad Heim Excavating and Trucking | |||||||||||
| Funding Source: 100% Federal-SWG, | 1920 Joy Ave | ||||||||||||
| Waverly IA 50677 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 319-230-0153 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $800.00 | $800.00 | $0.00 | $0.00 | ||||||
| 2 | Tree Removal | 27 | Units | $60.00 | $1,620.00 | $0.00 | $0.00 | ||||||
| 3 | Site Grading | 1 | L.S. | $4,800.00 | $4,800.00 | $0.00 | $0.00 | ||||||
| 4 | Limestone Fill Material | 400 | Tons | $9.625 | $3,850.00 | $0.00 | $0.00 | ||||||
| 5 | PC Deck Concrete, 6" Class C, Fiber Reinforced | 573 | S.F. | $8.00 | $4,584.00 | $0.00 | $0.00 | ||||||
| 6 | Top Soil, Furnish & Spread | 55 | C.Y. | $25.00 | $1,375.00 | $0.00 | $0.00 | ||||||
| 7 | Cr. Stone Surfacing | 24 | Tons | $28.00 | $672.00 | $0.00 | $0.00 | ||||||
| 8 | Stabilizing Crop Seeding | 1 | L.S. | $3,800.00 | $3,800.00 | $0.00 | $0.00 | ||||||
| $21,501.00 | $0.00 | $0.00 | |||||||||||
Jonas Raber Construction LLC, Fairbank, IA
12/22/2025